Tribal data centers — factual field registry

.md · 2 sections · 21201 characters

Source, owner, and dates

workbench: Research Packages/Sovereign Compute/TRIBAL_DATA_CENTER_FIELD_REGISTRY.md

Canonical source SHA-256: 6a542fa4960bb601ff3253f8e7fdc98bdf64e02298d9cd8257a71e97350e977b

Served copy SHA-256: 6a542fa4960bb601ff3253f8e7fdc98bdf64e02298d9cd8257a71e97350e977b

Owner evidence cutoffs: {"sovereign-compute": "2026-10-05"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: sovereign-compute

Tribal data centers — factual field registry

Section 1 of 2

# Tribal data centers — factual field registry

Updated: 2026-07-11
Status: working field map; pre-synthesis
Scope: data centers, AI compute, related power infrastructure, and digital-sovereignty projects involving federally recognized Tribal Nations, tribal enterprises, tribal trust or restricted land, reservations, and Indigenous treaty or cultural interests in the United States.

## Purpose

This record establishes the vocabulary and entity boundaries for the tribal-data-center research track. It exists to prevent four common collapses:

  1. treating every project near an Indigenous community as a project on tribal land;
  2. treating all land connected to a Tribe as having the same legal status;
  3. treating an announcement, lease, power agreement, permit, groundbreaking, and operating facility as the same event;
  4. treating tribal sovereignty as either complete regulatory immunity or merely another form of local government.

The research order is: establish each entity and its own dated actions; establish the exact parcel and legal authority; establish the project clocks; interweave only after those records are stable.

## Factual rules

## 1. Land-status vocabulary

Land state Working definition Research consequence
Tribal trust land The United States holds title in trust for a federally recognized Tribe Determine whether BIA approval, approved HEARTH regulations, a TERA/TEDO, or another authority governs the lease or right-of-way
Restricted-fee tribal land The Tribe holds title subject to federal restrictions on alienation or encumbrance Do not assume the same approval path as ordinary fee land; verify the governing restriction and lease authority
Individually allotted trust or restricted land An individual Indian owner or owners hold beneficial or restricted interests, often fractionated A tribal government announcement may not establish consent or control over the parcel; ownership and approval must be traced separately
Tribe-owned fee-simple land A Tribe or tribal entity owns land outside trust or restricted status State and local rules may apply differently; tribal ownership alone does not make the parcel trust land
Reservation territory Land within a federally recognized reservation boundary The boundary does not by itself establish parcel ownership, trust status, or exclusive tribal jurisdiction
Oklahoma reservation / jurisdictional territory Reservation and Indian-country questions may involve a jurisdictional patchwork of trust, restricted, fee, allotted, municipal, and non-Indian parcels Record parcel ownership and governmental jurisdiction separately; never infer land status from the reservation label alone
Ceded or treaty-protected territory Land outside the present reservation in which a Tribe asserts treaty, cultural, hunting, fishing, religious, or consultation interests This may create consultation, cultural-resource, treaty-right, or political stakes without making the project tribally owned or tribally permitted
Ancestral or cultural landscape A broader historic or cultural connection asserted by a Tribe or Indigenous community Record the claim and the legal mechanism, if any; do not label the project “on tribal land” without parcel evidence

Primary legal starting point: BIA — Leasing on Individual Indian and Tribal Lands

## 2. Authority vocabulary

Authority What it can establish What it does not automatically establish
BIA-approved HEARTH regulations The Tribe may negotiate and enter covered surface leases under its approved rules without further Interior approval for each lease That a particular lease exists; that federal environmental, right-of-way, utility, water, or other law does not apply
BIA lease approval under 25 CFR Part 162 Interior approved the identified lease or lease action Completion of every non-leasing permit or construction milestone
Tribal Energy Resource Agreement (TERA) A Tribe may manage covered energy leases, business agreements, and rights-of-way under the approved agreement Authority outside the agreement's scope or proof of a data-center deal
Certified Tribal Energy Development Organization (TEDO) A qualifying majority tribally owned organization may enter covered energy agreements without individual Interior approval A blanket exemption for a non-energy data-center lease
Section 17 federal corporation A federally chartered tribal corporation separates specified business assets from the tribal government and may carry identified tax and sovereign attributes Ownership of a parcel, approval of a lease, or immunity for every subsidiary and counterparty
Tribal-law corporation or LLC An entity organized under tribal law A uniform tax, immunity, or land rule; examine the charter, ownership, waivers, and contract
Tribal council resolution or executive order The issuing tribal government took the stated governmental action Approval by affected citizens, landowners, federal agencies, utilities, or outside governments unless the instrument says so
Federal executive or agency action The federal entity took the stated action under claimed authority Application to tribal land unless the text includes it or a later action applies it

Primary references: BIA — HEARTH Act Leasing; BIA — TERAs and TEDOs; BIA — Choosing a Tribal Business Structure

## 3. Project-stage ladder

Every project is assigned the highest publicly verified stage. Stages are not skipped by inference.

  1. Marketed — a developer or intermediary advertises tribal or sovereign-land capacity.
  2. Approached — a Tribe or community confirms that a developer made contact.
  3. Under study — a government or enterprise is evaluating sites, policy, or project terms.
  4. Announced partnership — named parties publicly announce an intended collaboration.
  5. Site identified — the parcel or sufficiently precise location is public.
  6. Land control documented — ownership, option, lease, or other site-control instrument is verified.
  7. Tribal authorization — the relevant tribal governmental body approves the identified action.
  8. Lease approved or effective — the lease has the approvals required by its actual legal path.
  9. Power path documented — utility service, power-purchase agreement, onsite generation, interconnection, or transmission plan is verified.
  10. Permits substantially obtained — identify each permit; never use one approval as a stand-in for all permits.
  11. Financed / final investment decision — committed financing or an equivalent final decision is verified.
  12. Under construction — physical construction begins at the identified site.
  13. Energized — the facility or first phase receives operating power.
  14. Compute activated — the facility begins serving workloads.
  15. Revenue operating — the tribal counterparty begins receiving verified lease, power, service, ownership, or tax revenue.
  16. Expanded, suspended, cancelled, transferred, or decommissioned — later state changes receive their own events.

## 4. The clocks to keep separate

Clock Anchor events
Tribal-government clock citizen notice; committee action; council vote; executive order; referendum; ordinance; moratorium
Land clock acquisition; trust status; HEARTH approval; option; lease execution; BIA approval; right-of-way
Developer clock incorporation; fundraising; marketed site; partnership; tenant agreement; construction; operator transfer
Power clock generation proposal; fuel supply; power purchase; interconnection request; transmission study; energization
Water/environment clock water rights; supply agreement; air permit; environmental review; cultural consultation; litigation
Capital clock incentive agreement; grant; loan; tax treatment; financing; final investment decision
Compute clock equipment order; installation; commissioning; first workload; capacity expansion
Revenue clock lease payment; power sale; tax or payment in lieu; service income; dividend; revenue share
Resistance clock citizen meeting; petition; protest; moratorium; administrative appeal; complaint; injunction
National-security clock federal designation; defense contract; classified authorization; emergency or security intervention

## 5. Revenue architecture

Record each layer separately. “A data-center deal” may include only one or several.

DOE's February 2026 tribal-data-center webinar expressly distinguished land rent from power sales, operations, infrastructure, and ownership opportunities. It also warned that hyperscale projects can create relatively few permanent jobs and that Tribes should investigate brokers and counterparties. DOE — Beyond Land Leases transcript

6. Initial entity registry

Section 2 of 2

## 6. Initial entity registry

Entity Type Current verified relationship to the field Highest verified stage
DOE Office of Indian Energy Policy and Programs Federal office Published tribal-data-center opportunity material, held a dedicated webinar, supplied technical/legal assistance, and announced work toward a Tribal Data Center Convening Federal program active
Bureau of Indian Affairs / Division of Real Estate Services Federal bureau Approves or administers trust/restricted-land leasing routes and HEARTH regulations Legal gate / registry
FERC Independent federal regulator Acting on large-load grid interconnection, cost allocation, co-location, and ratepayer safeguards Federal rulemaking/orders active
Forest County Potawatomi Community Tribal Nation Owns Data Holdings through its economic-development group; facility is on trust land Operating
Potawatomi Ventures Tribal enterprise Parent/diversification entity for Data Holdings Operating parent
Data Holdings Tribal data-center enterprise Enterprise colocation/private-cloud facility on trust land in Milwaukee Operating since 2013
Cachil Dehe Band of Wintun Indians / Colusa Indian Community Tribal Nation Landowner and owner of Colusa Indian Energy; named in announced AI-and-energy campus Announced partnership; existing microgrid operating
Colusa Indian Energy Section 17 tribal corporation Announced AI-and-energy infrastructure partnership with Strata Expanse; presented tribal data-center model through DOE Announced partnership
Strata Expanse Private REIT / infrastructure developer Named Colusa partner; supplies energy-first site and gray-space infrastructure model Announced partnership
Caddo Nation of Oklahoma Tribal Nation BIA approved agriculture, business, and residential HEARTH regulations on 2026-06-22; public reporting identifies data-center interest, but no official project instrument has been located in this pass Legal capacity verified; project unverified
Cherokee Nation Tribal Nation Created a task force to study data-center economic and environmental effects within the reservation Government study
Quechan Indian Tribe Tribal Nation Official 2026-05-07 notice granted permission to conduct due diligence for a potential 200-MW solar-microgrid and AI data center on 900–1,000 leased acres; operator and executed agreement are not public Active due diligence
Seminole Nation of Oklahoma Tribal Nation Tribal Council reportedly adopted a moratorium on generative AI and data-center development Moratorium reported; primary resolution requested
Muscogee (Creek) Nation Tribal Nation NCA 25-077 to establish a Mvskoke Technology and Innovation Park passed joint committee 8-1, then failed the National Council 4-11 on 2025-11-15 Terminated precursor
Shoshone-Bannock Tribes Tribal Nations Officially oppose a proposed Pocatello project within ceded lands; project is not described as tribal land Formal opposition; adjacent/ceded-land interest
Confederated Tribes and Bands of the Yakama Nation Tribal Nation Members and leaders oppose an energy-storage project at a sacred site reportedly linked to prospective data-center demand Formal/cultural opposition; data-center linkage not finally verified
Ute Mountain Ute Tribe Tribal Nation Solar-and-storage infrastructure under construction on tribal land will supply some power to an off-reservation Meta data center Energy construction; indirect data-center link
Southern Ute Indian Tribe Tribal Nation Signed the first TERA, expanding tribal administration of covered energy leases, agreements, and rights-of-way; no data-center project identified Enabling authority only
UnityCloud Private developer/marketer Markets AI-native data centers on “sovereign tribal land,” faster deployment, and tax advantages; no named tribal site is public on its website Marketed; sites/counterparties undisclosed
Oneida Indian Nation of New York Tribal Nation / enterprise owner Oneida Innovations Group states that the Nation's commercial system includes four Tier III data centers and a 230-mile private dark-fiber ring; exact parcels, land status, MW, workloads, and third-party hosting are not public in the sources reviewed Operating tribal-enterprise compute; hyperscale expansion unverified
Oneida Innovations Group Tribal technology enterprise Architectures and operates the Nation's four Tier III data centers; performs data-center, cloud, network, telecom, cyber, and federal defense work Operating technology platform
Tonawanda Seneca Nation Tribal Nation Maintains a long consultation and opposition record concerning STAMP; Stream's proposed 500-MW Project Double Reed is immediately adjacent to Nation territory but is not a tribal project Active adjacent-project consultation/resistance
Saint Regis Mohawk Tribe / Mohawk Networks Tribal Nation / telecom enterprise Operates a mature tribal fiber and fixed-wireless platform and sought trust status for a 140-acre infrastructure parcel; no tribal data-center deal located Operating digital infrastructure; compute project unverified
Mohawk Council of Akwesasne First Nations government Formally opposed the proposed 635-MW NCCS/NYDIG data-center expansion at the former Alcoa East/Reynolds site near Akwesasne on 2026-05-22 Formal opposition to adjacent project
Seneca Nation of Indians / Seneca Technologies Tribal Nation / technology enterprise Seneca Technologies markets cloud, cyber, data, DevSecOps, and responsible-AI services to federal customers; no Nation-site data-center instrument located Operating technology services; physical hosting unverified
Shinnecock Indian Nation / Shinnecock Power Tribal Nation / energy-telecom enterprise Building a gigabit-capable fiber network and operating a renewable-energy and telecommunications parent; no data-center project located Enabling digital infrastructure
Tuscarora Nation Tribal Nation A 19-mile fiber-to-the-premises network is funded for the reservation; no data-center project or developer approach located Broadband buildout; compute project unverified

## 7. Required project record

Each confirmed project should contain:

## 8. Boundary before synthesis

This registry does not yet conclude that federal agencies and private developers are using tribal sovereignty as a coordinated regulatory bypass. It establishes the mechanisms that could create speed or cost advantages and the entities publicly positioning themselves around those mechanisms.

The later overlap layer must distinguish:

## Open verification items