Federal Data Center Legal Spine 2025-2026

.md · 2 sections · 13483 characters

Source, owner, and dates

workbench: Research Packages/Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md

Canonical source SHA-256: ddcaa3ed100c2ddfd21492f365e393b49caa13d4f860bbf83233b83550c76e13

Served copy SHA-256: ddcaa3ed100c2ddfd21492f365e393b49caa13d4f860bbf83233b83550c76e13

Owner evidence cutoffs: {"data-center-federal-legal-spine": "2026-10-05"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: data-center-federal-legal-spine

Opening section

Section 1 of 2

# Federal data-center legal spine, 2025–2026

## In plain English

Question: Which federal legal objects actually govern U.S. data-center buildout, and which proposed, issued, authorized, constructed and operating states remain separate?

Answer: No federal law bans data centers or sets rules for their power queues, water or emissions. The July 2025 executive order to speed them up has produced real leases, selections and permit changes, but no finished project or blanket exemption.

Evidence checked through: 2026-08-20

The detailed record below keeps the legal wording, source limits and open questions.

## Short answer

The federal contest is not presently one nationwide legal “war” with two operative codes. It is an asymmetric field:

The strongest public evidence is therefore not a political statement. It is an exact object: a final rule, guidance document, solicitation, lease, right-of-way decision, covered-project posting, permit, enacted section or official bill action.

## 1. What is law now

### Operative executive direction

EO 14318, signed July 23, 2025 and published at 90 FR 35385, defines a “Data Center Project” as a facility requiring more than 100 MW of new load for specified AI workloads. Its “Qualifying Project” routes include at least $500 million in capital expenditure, more than 100 MW of new load, national-security protection, or a Secretary-designated project. It directs:

The order is an operative instruction to executive agencies. It is not itself an appropriation, private grant, project permit, lease, pollution waiver or construction approval. It also expressly preserves applicable law and appropriations.

Primary authority: EO 14318, 90 FR 35385.

### Narrow enacted congressional provisions

The FY2026 NDAA, Public Law 119-60, contains two material enacted provisions:

Primary authority: P.L. 119-60.

These are planning and pilot duties, not a general commercial siting, water, emissions or rate code.

## 2. What EO 14318 has actually returned

Lane Strongest public return by cutoff Exact state Still required before a stronger claim
Federal land — DOE Portsmouth: DOE publicly confirms an SB Energy affiliate is leasing an initial 189 federal acres; groundbreaking occurred March 20, 2026. Publicly confirmed lease and construction-stage announcement; public release is not the full lease. Executed instrument/terms, project-by-project permits, full campus land boundary, financing and operating evidence.
Federal land — DOE Savannah River: Amentum selected July 20, 2026 for phased-lease negotiations. Conditional selection; not a final lease award. Successful negotiations, lease, safety/security review, permits and approvals.
Federal land — DOE Paducah: Brookfield selected for a 1.8 GW campus; NextEra for associated energy; approximately 785 acres. Sponsor selection/partnership announcement. Power service agreement remains subject to Kentucky PSC approval. Final agreements and leases, PSC order, other permits, construction and operation.
Federal land — DOD Army conditionally selected Carlyle at Fort Bliss and CyrusOne at Dugway under 10 U.S.C. 2667. Exclusive lease negotiations; expressly not final. Executed enhanced-use leases, permits, construction and IOC.
Federal land — DOI BLM approved the Townsite data-center right-of-way in Nevada. Agency decision remains in the decision/appeal period on BLM's NEPA register. Final, unappealable authorization and later project approvals.
Permitting coordination QTS Richmond DC5 and PORTS Technology Campus appear as FAST-41 covered projects. Covered and in progress; coverage supplies schedules and coordination. Completion of each listed authorization; FAST-41 is not a permit.
CERCLA/Brownfields EPA issued January 2026 reuse guidance and public mapping/screening tools. Nonbinding site-reuse guidance and discovery resources. Site-specific cleanup, remedy consistency, liability, land-use and permitting determinations.
TSCA EPA accepts qualifying new-chemical submissions for priority handling from September 29, 2025. Queue priority under existing TSCA standards. Substantive TSCA review and any authorization; no standard or deadline was waived.
CWA/RHA Army reissued nationwide permits; NWP 39 expressly lists data centers and took effect March 15, 2026. Final general-permit framework, generally capped at ½ acre of waters loss with notification and conditions. Project eligibility, regional/general conditions, district review and any ESA/other permits.
Clean Air Act EPA published a data-center resource hub and a fact-dependent Acid Rain Program interpretation for truly islanded private-supply generators. Assistance plus nonbinding interpretive memo. Facility facts and all other applicable CAA programs; the memo expressly leaves them untouched.

Primary routes: Portsmouth DOE return, Savannah River selection, Paducah selection, Army conditional selections, QTS FAST-41 posting, PORTS FAST-41 posting, EPA reuse guidance, Army nationwide permits.

## 3. What Congress is proposing

The direct bills divide into distinct legal models. None should be reported as current law.

Proposed model Measures Threshold or trigger Proposed effect State at cutoff
Federal moratorium S.4214 / H.R.9442 AI-at-scale, or >20 MW plus specified density/cooling features Bar new construction/upgrades until Congress later enacts enumerated protections and expressly ends the moratorium. Introduced; referred.
Interconnection and rate allocation S.3682 / H.R.8241 >50 MW FERC data-center load queues, reliability/affordability gates and local transmission-upgrade cost allocation. Introduced; referred.
Self-generation / clean-energy duty H.R.6983 ≥50 MW daily use Annual matching generation; 75% clean in 2035 and 100% in 2040; civil penalties. Introduced; referred.
Energy/water transparency H.R.6984; S.4213 / H.R.9825; S.5054; H.R.10005 Varies: 25 MW, AI-use/tax test, or voluntary EPA/EIA reporting, operator disclosures, tax conditions or voluntary NTIA survey. Introduced; referred.
Emissions fee S.1475 / H.R.6179 >100 kW IT nameplate Declining regional baseline and fee for excess emissions intensity. Introduced; referred; proposed early clocks passed without effect.
Federal acceleration / litigation limits H.R.5927; H.R.8037 Varies DPA priority/finance and consolidated review, or remand-without-vacatur and expedited review. Introduced; referred.
Full cost allocation H.R.8033; H.R.9655 >50 MW or >75 MW Prevent specified utility upgrade costs from shifting to other customers. Introduced; referred.
Local control / notice H.R.8488; H.R.9262 AI focus or ≥20 MW Pre-development disclosure, public outreach, local-agreement conditions and limits on federal challenges to local denials. Introduced; referred.
Federal-land prohibition H.R.9939 AI-at-scale or >20 MW plus features Prohibit and begin removal of covered AI data centers/supporting infrastructure on federal land. Introduced; referred.
Environmental study/reporting S.4727 / H.R.9183; H.R.9372; H.R.5227 >50 MW or study mandate Impact studies, hearings, standards research and operator reporting. Introduced; referred.
Excise tax H.R.10102 >1 MW One cent per kWh federal excise tax with earmarked trust-fund allocations. Introduced Aug. 13, 2026; referred.

The full measure-by-measure registry and official GovInfo links are in the legislation registry.

Three broader permitting bills—H.R.4776, H.R.4503 and H.R.3898—passed the House and could affect energy infrastructure used by data centers, according to CRS. They are not direct data-center codes and had not become law by the cutoff.

## 4. Environmental-law ruling

The issued returns chiefly alter process, not the substantive existence of environmental law:

The correct sentence is therefore: some federal review pathways have been accelerated or clarified; ordinary project-level environmental gates remain unless a competent authority has issued the relevant instrument.

5. Current public gaps

Section 2 of 2

## 5. Current public gaps

The following were not located as public official records by the cutoff:

These are no-public-record findings, not proof that an internal submission never occurred or that an agency violated the order.

## 6. Research consequence

The next unit of evidence should always be the object that changes a row:

That is the factual spine on which later public-opposition, ratepayer, resource, national-security or astrology layers can safely be joined.