workbench: Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/AI_INFRASTRUCTURE_DOCUMENT_RETURN_GATES_2026-08-10.md
Canonical source SHA-256: 80379a98e79d8a4bc7de5cfeaf585cd01cfc75ebcc7515a27f90fba6a8e9eee7
Served copy SHA-256: 80379a98e79d8a4bc7de5cfeaf585cd01cfc75ebcc7515a27f90fba6a8e9eee7
Owner evidence cutoffs: {"ai-infrastructure-capital-stack-risk-transfer": "2026-08-10", "us-inbound-investment-industrial-capex": "2026-07-31", "industrial-project-finance-digital-rails": "2026-07-31"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: ai-infrastructure-capital-stack-risk-transfer, us-inbound-investment-industrial-capex, industrial-project-finance-digital-rails
Section 1 of 1
# AI Infrastructure Document Return Gates — 2026-08-10
This file prevents a new financing announcement from being promoted into GPU ownership, funded debt, operating cash flow or a completed loss waterfall before the governing documents exist.
## Minimum complete transaction chain
capital provider
-> fund / sponsor
-> legal borrower or equipment owner
-> executed debt, lease or service instrument
-> identified GPU / property / power asset
-> customer payment obligation
-> advance or asset acquisition
-> deployment and acceptance
-> controlled debt-service cash flow
-> collateral and guarantee response
-> residual recovery and final loss holder
| Case | Current state | Exact document or event that changes the ruling |
|---|---|---|
| NVIDIA six platforms | MOU-only | final partner agreement identifying capital vehicle, owner/borrower, instrument, customer criteria, NVIDIA support and loss waterfall |
| IREN Hardware 3 | definitive financing | tranche draw/closing evidence; GPU delivery/acceptance; first Microsoft service fee; later DSCR or remarketing event |
| CoreWeave DDTL 4.0 | partially drawn | collateral serial schedule; customer identity or unredacted MSA; later draws; DSCR/cash-trap state; default or recovery record |
| CoreWeave corporate stack | operating | debt-to-customer-contract crosswalk; GPU title/lease schedule by facility; actual refresh/redeployment recoveries |
| VCI / xAI | acquisition and lease announced | executed lease/financing instrument disclosing rent, guarantee, security, capital seniority, purchase/termination and residual terms |
| Abilene DC 1 | property operating | GPU bill of sale/lease/prepayment schedule; full construction credit agreement; Oracle hardware/customer allocation |
| AIP / Aligned | equity acquisition closed | acquisition financing/ownership schedule; tenant concentration and minimum-payment data; site debt and collateral map |
| Brookfield / NAVER | nonbinding term sheet | definitive Brookfield/Radiant agreement resolving GPU title, NAVER role, customer minimums, collateral and residual risk |
| Brookfield / Bloom | framework plus bounded commitments | named project SPV, creditor, draw, customer take-or-pay, placed-in-service and operating payment record |
| Campus AI France | development JV | shareholder agreement, equity subscriptions, debt facility, Mistral offtake, construction close and first operation |
Every future GPU-finance row must answer:
## Highest-priority source queue
No row in this package shows tokenized GPU title, tokenized project debt, stablecoin funding or DLT settlement. Reopen that lane only when an executed financing, custody, servicing or settlement document names the tokenized legal claim and completes the existing project-finance digital-rail return gate.
## Return-governance reconciliation — 2026-08-27
The 10 named gates, the six-item source queue and the digital-rail gate are
package_context_only. They remain claim-level document tests within this
package; this batch creates no broad Return Ledger or canonical-watch expansion
and does not advance the evidence cutoff.