White House Ballroom Primary-Source Ledger and Watchboard 2025-2026

.md · 2 sections · 16531 characters

Source, owner, and dates

workbench: Research Packages/White House Ballroom Lawfare 2025-2026/WHITE_HOUSE_BALLROOM_PRIMARY_SOURCE_LEDGER_AND_WATCHBOARD_2025-2026.md

Canonical source SHA-256: f5d5481ec6e191cdf2d9363191ad7f9265130158d0dcfe8ba872c5d04582e6b8

Served copy SHA-256: f5d5481ec6e191cdf2d9363191ad7f9265130158d0dcfe8ba872c5d04582e6b8

Owner evidence cutoffs: {"white-house-ballroom-lawfare-2025-2026": "2026-08-23"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: white-house-ballroom-lawfare-2025-2026

Opening section

Section 1 of 2

# White House Ballroom — Primary-Source Ledger and Watchboard

## Evidence rule

Every source below is a primary object or the exact image of one: statute, official government page, executed agreement, agency record, pleading, brief, order, opinion, FOIA request or administrative referral. A non-government host is used only where it serves the filed or produced primary document. Host identity does not change the evidence state: a complaint remains an allegation; an opinion remains a judicial ruling; an official statement remains the named speaker's representation.

## A. Core litigation ledger

ID Date Object What it proves Evidence limit
CT-01 2025-10-23 Voorhees emergency application Plaintiffs sought a halt using NCPC/CFA/NHPA theories. Allegations only; no complaint and no ruling.
CT-02 2025-10-28 Voorhees docket Filing defects and voluntary dismissal. Docket evidence; no merits.
CT-03 2025-12-12 National Trust original complaint Original APA/NCPC/CFA/NEPA/§8106/constitutional theories. Party allegations.
CT-04 2025-12-17 TRO denial No imminent irreparable above-grade harm on the record then; court relied on government construction/review representations. TRO-stage findings, not final merits.
CT-05 2026-02-26 First PI denial, official GovInfo Likely standing, but Executive Residence not an APA agency and no pleaded ultra vires claim. Preliminary procedural/merits assessment.
CT-06 2026-03-02 Second amended complaint Added ultra vires construction, funding and control-transfer theories. Allegations and legal claims.
CT-07 2026-03-31 PI opinion and order District court found likely lack of statutory authority and enjoined development. Preliminary, later clarified and stayed.
CT-08 2026-04-11 D.C. Circuit remand order Required clearer security boundary/evidence. Interlocutory order.
CT-09 2026-04-16 Clarified opinion and amended PI Barred above-ground ballroom while allowing specified below-ground and necessary security/safety work. PI now stayed by Chief Justice.
CT-10 2026-08-07 D.C. Circuit opinion 2–1 affirmance; majority and Rao dissent supply full competing analysis. Preliminary-relief appeal, not final merits.
CT-11 2026-08-13 Government Supreme Court stay application Government's standing, authority, security, integration, cost and progress account. Advocacy and declarations; not Court findings.
CT-12 2026-08-18 Trust opposition Trust's response on standing, statutes, equities and alleged race beyond review. Advocacy and record citations.
CT-13 2026-08-19 Government reply Government's final emergency-stage reply. Advocacy.
CT-14 2026-08-21 Supreme Court docket/order, No. 26A203 Chief Justice stayed April 16 PI pending further order. No reasons; no merits inference.

## B. Project, funding and review ledger

ID Date Object What it proves Evidence limit
PR-01 2025-07-31 White House announcement Initial public scope, team, start, seating, cost and private-funding representations. Announcement clock, not audited state.
PR-02 2025-08-18 NPS museum/tree categorical exclusion Pre-work object/tree preparation record. Bounded action only.
PR-03 2025-08-28 NPS EA Alternatives, project effects and agency analysis. Agency analysis; was not public before demolition.
PR-04 2025-08-28 NPS FONSI NPS no-significant-impact/no-impairment determination. Agency conclusion challenged in court.
PR-05 2025-08-28 NPS NHPA/exemption record White House-grounds exemption and no-effect conclusion for bounded off-site work. Does not decide non-NHPA statutes.
PR-06 2025-10-08 Philanthropic Support Agreement Donation intake, vetting, anonymity, fees, project requests and transfer mechanics. Not complete donor/amount, contract or expenditure ledger.
PR-07 2025-10-15 Official presidential dinner remarks Attributed demolition, excavation, capacity, financing and in-kind contribution statements. Speaker claims; values not audited.
PR-08 2026-01-08 NCPC information sheet First NCPC information presentation; no vote. Information stage.
PR-09 2026-01 NCPC FAQ NCPC's jurisdictional position on federal property, demolition, site prep and below-grade work. Agency's account of its review scope.
PR-10 2026-01-22 CFA official minutes Information presentation, project scale, prior demolition and design concerns. No action at this meeting.
PR-11 2026-02-19 CFA final project action CFA final design approval and closing letter. Design review, not §8106 authorization.
PR-12 2026-03-05 NCPC staff report Project dimensions, staff analysis, comments/testimony and deferred vote. Staff report, not final Commission action.
PR-13 2026-04-02 NCPC Commission Action Preliminary and final site/building-plan approval. Planning approval, not congressional authorization.
PR-14 2026-04-02 NCPC FONSI NCPC's NEPA adoption/no-significant-impact determination. Agency conclusion; prospective review state.
PR-15 current hub NPS project record Official document family and current access route. Mutable index; use dated objects for clocks.
PR-16 current hub NCPC project record Complete NCPC meeting/action/material index. Mutable index; use dated action objects.

## C. Records and compliance pressure

ID Date Object State
RC-01 2025-10-21 Democracy Forward FOIA request packet Administrative requests; no ballroom-specific resulting suit or complete production found.
RC-02 2025-10-23 ADAO safety/disclosure letter Prelitigation request; allegations/questions, not findings.
RC-03 2025-12-22 Public Citizen FOIA complaint Funding agreement later produced; case dismissed.
RC-04 2026-01-07 ADAO FOIA complaint Ongoing records case.
RC-05 2026-04-06 CLC LD-203 referral Enforcement request; no public USAO disposition found.
RC-06 2026-08-05 ADAO FOIA opinion Timeliness ruling and agency-status boundaries; no asbestos-safety merits.

## D. Statute and doctrine ledger

ID Object Controlling question
LA-01 40 U.S.C. § 8106 What statute supplies express congressional authority?
LA-02 3 U.S.C. § 105(d) Appropriation authorization only, or substantive alteration/improvement power?
LA-03 54 U.S.C. § 100101 Can NPS authorize/fund an action that impairs protected values?
LA-04 Pub. L. 87-286, 75 Stat. 586 How do NPS administration and presidential official use coexist?
LA-05 40 U.S.C. § 8722 What required NCPC consultation/approval, and when?
LA-06 40 U.S.C. § 9102 and Executive Order 1259 What was CFA's advisory-review timing rule?
LA-07 42 U.S.C. § 4336 Was EA/FONSI procedure and scope lawful; was an EIS required?
LA-08 54 U.S.C. § 307104 White House and grounds NHPA exemption.
LA-09 54 U.S.C. § 101101 and 31 U.S.C. § 1321 Donation authority, statutory purpose and trust-fund status.
LA-10 31 U.S.C. § 1535 Did the interagency order satisfy Economy Act conditions?
LA-11 NRC v. Texas Ultra vires relief requires action entirely beyond authority and contrary to a clear mandatory limit.
LA-12 Seven County Infrastructure Coalition v. Eagle County NEPA review is procedural and receives substantial deference on scope/detail.

E. Congressional objects

Section 2 of 2

## E. Congressional objects

These are primary legislative records. None is treated as enacted law.

Object Introduced / action Function
S.3191, Stop Ballroom Bribery Act 2025-11-18 Proposed donation restrictions and disclosure.
H.R.6085, Stop Ballroom Bribery Act 2025-11-18 House companion proposal.
S.3361, No Palaces Act 2025-12-04 Proposed NCPC approval requirements/limits.
H.R.6761, People's White House Historic Preservation Act 2025-12-16 Proposed preservation/approval response.
H.R.8537 2026-04-28 Proposed project authorization.
H.R.8543, Build the Ballroom Act 2026-04-28 Proposed project authorization.
Congressional Record, April 29 2026-04-29 Rand Paul sought unanimous consent for authorization; Elizabeth Warren objected. No enactment by that route.
S.4486 Senate calendar 2026-05-12 Proposed Title 3 process; not enacted at cutoff.

## Return watchboard

Priority Return object Exact state change it can support Where to watch
1 Full-Court order on 26A203 Stay granted, denied, narrowed, or interim order superseded. SCOTUS docket
1 Certiorari petition and disposition Supreme Court merits-review clock opens or closes. Same docket/new merits docket.
1 D.D.C. final merits order/judgment Final legality and remedy, subject to appeal. D.D.C. No. 1:25-cv-04316-RJL.
1 Post-August 5 ADAO entries Agency determinations, production schedule, released records or noncompliance. D.D.C. No. 1:26-cv-00029-RJL.
2 Released asbestos/hazard records Inspection, abatement, air, worker/public protection and disposal facts. Agency production or court filing; do not infer from silence.
2 USAO response/case on LD-203 referral Investigation, declination, enforcement or no-action object. USAO-DC primary release/case record.
2 Transaction-level funding records Donor, amount, date, vetting, deposit, project request, obligation, transfer, invoice, disbursement. NPS/EXR/Trust records; official disclosures; court exhibits.
2 Enacted public law Express authorization, restriction, disclosure or process change. Congress.gov/GovInfo public-law and enrolled-bill record.
3 Revised NPS/NCPC/CFA record Scope/design/impact mitigation or approval-condition change. Official project hubs and dated actions.
3 Construction declaration plus verifiable milestone Below-grade/above-grade completion state and remedy/equities change. Filed declaration, official progress record; preserve attribution.

## Negative-result log at cutoff