Funds Drawn and Risk-Holder Matrix — Six Deep Dives

.md · 1 sections · 6823 characters

Source, owner, and dates

workbench: Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/FUNDS_DRAWN_AND_RISK_HOLDER_MATRIX.md

Canonical source SHA-256: 9204fdb906170a1ccd39f82de9776938b6a2c9f43726c7f12e553914bb819738

Served copy SHA-256: 9204fdb906170a1ccd39f82de9776938b6a2c9f43726c7f12e553914bb819738

Owner evidence cutoffs: {"us-inbound-investment-industrial-capex": "2026-07-31", "ai-infrastructure-capital-stack-risk-transfer": "2026-08-10", "industrial-project-finance-digital-rails": "2026-07-31"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: us-inbound-investment-industrial-capex, ai-infrastructure-capital-stack-risk-transfer, industrial-project-finance-digital-rails

Opening section

Section 1 of 1

# Funds Drawn and Risk-Holder Matrix — Six Deep Dives

## Reading rule

For each project, preserve these three non-additive measures:

  1. facility commitment — maximum credit or stated equity commitment;
  2. actual advance / funded signal — cash advance, loan availability reduction or other hard funding evidence; and
  3. actual construction spend — capitalized project cost or other observed deployment.

The holder of an economic claim can change through syndication, refinancing, restructuring, a guarantee, or sale of the asset. A named arranger is not necessarily the final risk holder.

Project Legal borrower and facility Commitment Actual advance / funded signal Restricted use and spend evidence Presently identified risk holder / residual claimant Crucial gap
CP2 LNG Phase 1 CP2 LNG LLC; guarantors CP2 Procurement and CP Express. $11.3B construction term loan + $850M working-capital/LC; CP2 Holdings separately has $2.8B equity bridge + $191M interest reserve. $15.1B disclosed Phase-1 financial-close stack. At 2025 year-end, $9.39B construction and $740M WC/LC capacity available, implying roughly $1.91B and $110M used/outstanding/LC—but not a separately stated cash-draw series. Facility use: finance/develop/construct/place in service. $9.9B total CP2 Phases 1–2 project cost paid at year-end is not attributable solely to Phase 1/new facilities. Project assets/guarantors and secured lenders; 10-K says project debt has no parent recourse/guarantee. Facility-exhibit extraction for originating lender list; Phase-1-only draw and spend.
Rio Grande LNG Train 5 Rio Grande LNG Train 5, LLC. $3.59B senior-secured non-recourse term loan + $500M senior-secured private-placement notes; equity through Train 5 JVCo. $4.09B project debt; $2.58B committed equity. Close established, but no public aggregate cash-draw balance. Notes fund in tranches December 2025–October 2026. Project construction and collateral/security use; full NTP, but no numeric spend. Secured lenders/noteholders, then JV equity; sponsor has upstream borrowing to fund its contribution. Draw balance, lender/noteholder schedule and construction spend.
Thacker Pass Phase 1 Lithium Nevada LLC, owned by Lithium Nevada Ventures LLC LAC–GM JV. DOE ATVM facility; Citibank collateral/depositary accounts. Expected maximum $2.23B after amendment ($1.97B principal). $867M: $435M 2025-10-20 + $432M 2026-02-24. Restricted accounts; advances typically quarterly, spent monthly. $611.6M 2025 capitalized construction/project cost; later Q1 record reports $1.277B cumulative capitalized project costs at 2026-03-31. DOE secured lender; LAC completion/debt guarantor; GM/LAC residual equity; GM offtake supports revenue. All LN assets/equity and tax-credit-monetization proceeds are secured. Advance-to-vendor/use-of-proceeds schedule.
BlueOval SK Original borrower BOSK; successor structure after May 2026: Ford Energy Battery holds Kentucky plants/assumed note for one advanced KY plant; SK Battery America controls BOSK/Tennessee. Up to $9.63304B DOE/FFB multi-draw facility. $7.83554B actual BOSK advances reported before restructure. Construction use for KY/TN battery plants. KY Facility 1 certificate of occupancy and Facility 2 building complete; advance is not spend. Post-restructure: Ford Energy Battery assumed $3.80504B DOE note associated with a Kentucky plant; SKBA/BOSK Tennessee exposure requires successor schedule. Ford's former $6.6B support obligation ended. Allocation of remaining advances/notes and post-restructure spend/operations.
TSMC Arizona TSMC Arizona Corporation, wholly owned by TSMC; Fab 21. CHIPS direct-funding agreement and government-loan agreements; existing Arizona notes. Up to $6.6B direct funding + up to $5B government loans; $4.5B 2021 parent-guaranteed notes; up to $20B parent capital increase authorized. No public direct-funding disbursement, government-loan draw, or paid-in parent-capital amount identified. Award/loan funds subject to milestones and conditions. Fab 1 HVM; Fabs 2/3 construction milestones demonstrate build but not cost/draw. Parent gives Commerce unconditional guarantee; parent guarantees Arizona notes; award/loan availability conditional. Paid-in parent equity, award disbursement, loan draw and fab-specific spend.
Abilene DC 1 Abilene DC 1 LLC, wholly owned by Longhorn JV (92.3% BOREC/Blue Owl; 7.7% Crusoe). $2.288B construction loan; $926.847M equity contributions as of 2025-12-31. Construction-loan proceeds are restricted for development; lender and numeric draw not public. Two buildings/eight halls delivered; Oracle rent began March/July 2025; power station under development; no numeric spend. Construction lender, then BOREC/Crusoe equity. Oracle is 100% tenant and reimburses specified construction costs under build-to-suit lease. Lender, actual loan balance/draw and project spend.

## First conclusion

Only Thacker Pass has a clean public chain from facility to stated advances to a numeric capitalized-cost figure. BlueOval has a large advance figure, but a post-advance ownership/borrower restructuring. CP2 has an availability-based funding signal and combined-phases spend. The other three demonstrate financing architecture or construction, not published draw-to-spend cash paths.

This is why the eventual numerator must retain separate columns for committed, advanced, spent and operating—not collapse them into a single "investment" amount.

## Sources