.md · 4 sections · 44228 characters
workbench: Research Packages/Federal Science Operating System/FEDERAL_FUSION_PROJECT_CAPITAL_REGULATORY_REGISTRY_2022-2035.md
Canonical source SHA-256: 83ff6562a2d3e0a567832670f003266c7d7509b92c14fe229c6f32c6a5e67ea2
Served copy SHA-256: 83ff6562a2d3e0a567832670f003266c7d7509b92c14fe229c6f32c6a5e67ea2
Owner evidence cutoffs: {"federal-science-operating-system": "2026-10-12", "federal-fusion-commercialization": "2026-08-15", "genesis-mission": "2026-10-13"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: federal-science-operating-system, federal-fusion-commercialization, genesis-mission
Section 1 of 4
# Federal fusion project, capital and regulatory registry, 2022–2035
Evidence cutoff: 2026-08-15
Status: current workbench research; object-level implementation registry
Scope: the eight companies in DOE's Milestone-Based Fusion Development Program, their machines and sites, public capital, verified milestones, regulatory and grid objects, and the Genesis-linked implementation layer
Authority boundary: federal, state, utility, laboratory and local-government records control public-program and regulatory state. Company records establish company designs, contracts, experiments and claims only at the verb and boundary the source supports.
DOE's eight Milestone companies are one funding cohort, not eight equivalent U.S. fusion power plants. At the cutoff:
The durable plot is therefore:
appropriation -> program allocation -> selection -> executed instrument -> obligation -> verified milestone -> outlay -> technical output -> commissioned capability -> licensed operation -> net electricity -> grid delivery
No current object reaches the end of that chain.
selected, negotiating, executed, obligated, verified, outlaid,
completed and closed are different capital states.## Federal Milestone Program baseline
DOE selected the eight recipients on May 31, 2023 and announced that all eight had signed Technology Investment Agreements on June 6, 2024. Payments are conditional on satisfactory review of negotiated milestones. DOE initially obligated $46 million for the first 18 months; the $415 million program figure is a statutory authorization through FY2027, not an appropriation or an award already paid.
DOE's January 16, 2025 public update independently identified five completed
early milestones: two for Focused Energy, one for Realta Fusion and two for
Thea Energy. It said CFS, Tokamak Energy, Type One, Xcimer and Zap were still
working on early science-and-technology milestones at that time. The June 2026
roadmap lists all eight as participating as of April 2026. Later company
releases report additional DOE approvals; those retain the provenance
company-reported DOE approval unless a DOE action record is cited.
Sources: DOE award list · DOE June 2024 strategy and agreements · DOE January 2025 milestone update · DOE 2026 roadmap
## Eight-company field registry
### Commonwealth Fusion Systems
| Field | Current defensible state |
|---|---|
| Legal/program object | Commonwealth Fusion Systems, LLC; Milestone recipient |
| Approach | high-field HTS tokamak |
| Current machine | SPARC, under construction at CFS's Devens, Massachusetts campus; no first plasma or Q > 1 result at cutoff |
| Power-plant object | ARC / Fall Line Fusion Power Station, proposed at the James River Industrial Center, Chesterfield County, Virginia |
| DOE milestone state | first-phase agreement described by CFS as worth $15 million; CFS reported DOE validation of its full-scale toroidal-field magnet milestone and an $8 million payment on 2025-09-30 |
| Regulatory/site state | Massachusetts broad-scope radioactive-materials license for SPARC reported granted 2024-10-24; Chesterfield conditional-use permit approved in September 2025 |
| Commercial state | Google 200 MW PPA announced 2025-06-30; Eni PPA described as more than $1 billion announced 2025-09-22 |
| Grid state | CFS announced a PJM Cycle 1 interconnection application 2026-04-28; PJM confirmed fusion among Cycle 1 applicants 2026-04-29; no completed study or executed interconnection agreement located |
| Power claim | ARC design about 1.1 GW fusion / 400 MWe net; target only |
| Missing promotion proof | SPARC first plasma and gain; ARC final design/FID, construction authorization, interconnection studies/agreement, commissioning and measured electricity |
The CFS chain is the strongest current example of commercial objects moving in parallel without yet constituting a plant: license for the research machine, land-use approval for the proposed plant, PPAs and a grid application are four different states.
Sources: SPARC · ARC · $15 million agreement · DOE magnet validation and payment reported by CFS · SPARC license · Chesterfield permit · Google PPA · Eni PPA · CFS PJM application · PJM confirmation
| Field | Current defensible state |
|---|---|
| Legal/program object | Focused Energy Inc.; Milestone recipient with U.S. and German operations |
| Approach | direct-drive laser inertial fusion plus proton fast ignition; LightHouse architecture and Pearl D-T targets |
| Current facilities | Darmstadt targetry laboratory; Austin target-tracking and engagement facility reported open in early 2026; announced Bay Area laser-development facility not proven operating |
| Plant/site object | Biblis, Germany is the current industrialization/pilot-plant site lane; no named U.S. power-plant site located |
| DOE milestone state | DOE independently identifies completed high-gain-target modeling and ion-beam-focusing milestones; Focused reports DOE verification of both |
| Capital state | $240 million Series A announced 2026-05-27; RWE entered as investor and site/approval partner |
| Power target | company roadmap: diagnostic chamber first light 2031, implosion 2033, pilot plant 2035 and first grid MWh 2037 |
| Missing promotion proof | approved preconceptual design, U.S. project site, license, construction, PPA/interconnection and architecture-specific ignition/gain |
NIF's indirect-drive ignition record is not proof for Focused's distinct driver, target, proton-fast-ignition, chamber or repetition-rate architecture.
Sources: Focused early milestones · company and roadmap · $240 million Series A · Biblis hub
| Field | Current defensible state |
|---|---|
| Legal/program object | Realta Fusion, Inc.; Milestone recipient |
| Approach | high-field axisymmetric/tandem magnetic mirror |
| Current machine | WHAM, a 17 T research prototype at UW–Madison's Physical Sciences Laboratory in Stoughton, Wisconsin; first plasma 2024-07-15 |
| Next project/site | Hammir planned at The Realta Forge, OM Station/former Oscar Mayer plant, Madison; site and incentives announced, construction not begun at cutoff |
| DOE milestone state | DOE identifies completed whole-device modeling of simple-mirror equilibria toward a tandem-mirror scientific-gain goal of at least 5; no public full preconceptual-design approval located |
| Physical result | on 2026-06-19 a WHAM direct-energy converter drew multiple amps at about 100 volts during plasma operation, enough for a few lightbulbs |
| Boundary | most converted energy was externally supplied plasma-heating input; Realta expressly says the result was neither net electricity nor large-scale conversion of fusion-born power |
| Site capital | Wisconsin and Madison support described as up to $55 million; publication 2026-07-15 08:00 ET; groundbreaking expected before year-end, not completed |
| Missing promotion proof | Hammir construction/commissioning, fusion-dominant direct conversion, gain, power-plant site, license, PPA/interconnection and net electricity |
This is a real intermediate rung between plasma operation and power conversion, but it sits below engineering gain, net generation and grid delivery.
Sources: UW first plasma · WHAM direct-energy-conversion technical account · exact publication clock · Forge/Hammir site announcement · WEDC confirmation
Section 2 of 4
| Field | Current defensible state |
|---|---|
| Legal/program object | Thea Energy, Inc.; Milestone recipient |
| Approach | software-controlled stellarator using arrays of planar HTS shaping coils |
| Current hardware | full-size, full-current, full-field Eos shaping coil reported operated at Kearny, New Jersey on 2026-05-13 |
| Machine/plant objects | Eos, planned D-D neutron-source and integrated demonstration machine; Helios, D-T pilot/commercial design; Eos site not announced |
| DOE milestone state | DOE independently confirms optimized-equilibria downselection and operation of one HTS planar-coil building block; Thea reported DOE certification/approval of the Helios preconceptual design on 2026-01-13 |
| Genesis/AI join | Helios digital twin and surrogate-model collaboration with NVIDIA, Synopsys, Argonne and PPPL announced 2026-06-08; design/model infrastructure, not DCP operation or a plant result |
| Supply-chain capital | ARPA-E selected Thea on 2026-07-09 for up to $20 million to scale domestic modular HTS-magnet production; selection/maximum is not a paid amount |
| Power target | Helios design about 1.1 GW thermal / 400 MWe net in the 2030s |
| Missing promotion proof | Eos site/build/operation, independent DOE approval object, license, plant site, PPA/interconnection and electricity |
Sources: DOE stellarator account · Helios design certification reported by Thea · full-scale coil · digital twin
| Field | Current defensible state |
|---|---|
| Legal/program object | U.S. subsidiary at Bruceton Mills, West Virginia; Milestone recipient; operating machine belongs to the UK-centered company system |
| Approach | high-field spherical tokamak |
| Current machine | ST40 at Oxfordshire, UK; reported 1 MA plasma current and triple product about (8 +/- 2 x 10^18) m^-3 keV s in 2025, then paused for the LEAPS upgrade |
| DOE milestone state | DOE said the company was still working on early milestones in January 2025; no public preconceptual-design approval located |
| Public-private capital | $52 million ST40 upgrade announced 2024-12-05, divided evenly among DOE, UK DESNZ and Tokamak Energy |
| U.S. plant object | no named U.S. pilot site, license, PPA or interconnection located |
| Power target | current U.S. design page: 800 MW fusion / 85 MWe net in the mid-2030s; supersedes older up to 200 MWe public language |
| Boundary | temperature, current and triple product are not energy gain or electricity |
Sources: U.S. program page · fusion technology · $52 million ST40 upgrade · ST40 2025 result
### Type One Energy — Project Infinity / Bull Run
Project Infinity is an umbrella containing several separate objects:
| Field | Current defensible state |
|---|---|
| Approach | optimized stellarator with non-planar HTS magnets |
| DOE milestone state | DOE's January 2025 state was working on early milestones; Type One's 2025 initial design review was company-chaired with outside experts, not DOE certification |
| Utility execution | TVA Power Service Shops fabrication/welding contracts announced 2025-07-22; actual limited contracts and site preparation, not Infinity Two construction |
| Commercial state | TVA letter of intent announced 2025-09-19 for potential deployment once commercially ready; not a PPA and expressly gated by TVA Board, planning and regulatory review |
| Licensing state | Type One reported an initial byproduct-material application submitted 2026-01-29; no public application, receipt, docket, completeness finding, disposition, license, inspection or operating authorization located |
| State framework | Tennessee Chapter 0400-20-14 filed 2026-03-11 at 10:37 a.m., timezone unstated, and effective 2026-06-09; a framework is not a project license |
| Site-control state | TVA ownership/control and Type One's authorized physical use are publicly established; exact lease/access/site-use instrument and final Infinity Two footprint are not public |
| Workforce/capital commitment | Tennessee Nuclear Fund database: $4.5 million contracted award, 330-job commitment and $223.5 million investment commitment; commitments are not realized totals |
| Grid state | no public Infinity Two queue request, study, agreement or point of interconnection located |
Dated 2025 releases, the January 2026 licensing announcement, TVA's current page and NRC's current page retain 350 MWe. Current Type One copy and TDEC's June 2026 release use 400 MWe from the same stated 800 MW fusion design. No primary change-control record explains the increase. Preserve the values as source versions; do not average them or treat them as two plants.
The January package cannot have been a completed application under Chapter 0400-20-14, which was filed in March and effective in June. Type One calls it an initial filing and TDEC says it laid groundwork for subsequent submissions. Its exact scope—Infinity One, Infinity Two, both, or a staged campus safety basis—remains unresolved.
Sources: TVA fusion page · TVA FY2025 Form 10-K · TVA/Type One cooperative agreement release · PSS contracts · TVA LOI · initial application announcement · TDEC rules release · operative Tennessee rule · NRC Agreement-State activities · ORNL high-heat-flux facility · Tennessee Nuclear Fund
| Field | Current defensible state |
|---|---|
| Legal/program object | Xcimer Energy Inc.; Milestone recipient |
| Approach | KrF excimer-laser inertial fusion with stimulated Brillouin scattering and a HYLIFE-type liquid-wall chamber |
| Current platform | Phoenix, operating in a 74,000-square-foot Denver laser bay; demonstrated integrated laser amplification/compression and more than 1 kJ, not a fusion shot or ignition |
| Next machines | Anvil, planned 200 kJ-on-target step for 2028; Vulcan, planned 4 MJ and upgradeable 12 MJ engineering-breakeven machine at an unselected site |
| Plant object | Athena, planned roughly 400 MWe architecture in the mid-2030s |
| DOE milestone state | Xcimer reported DOE approval of Athena's preconceptual design and technology roadmap on 2026-06-10 |
| Missing promotion proof | DOE action object, Anvil/Vulcan site/build/operation, architecture-specific ignition/gain, license, PPA/interconnection and electricity |
NIF's result does not establish performance of Xcimer's KrF driver, target, liquid chamber, repetition rate or wall-plug loop.
Sources: Phoenix operations · Athena design approval reported by Xcimer · current project ladder · commercialization roadmap
| Field | Current defensible state |
|---|---|
| Legal/program object | Zap Energy, Inc.; Milestone recipient |
| Approach | sheared-flow-stabilized Z pinch without external confinement magnets or lasers |
| Plasma machines | FuZE-Q and FuZE-3; FuZE-3's 2025 pressure result is a preliminary path-to-gain metric, not Q > 1 |
| Engineering platform | Century, an operating repetitive pulsed-power/liquid-metal test platform using ordinary hydrogen/helium; it does not produce fusion reactions or neutrons |
| DOE milestone state | Zap reported DOE-certified completion on 2025-02-25 of a three-hour, 1,080-shot Century milestone; it reported DOE approval on 2026-05-19 of an approximately 50 MWe-net-per-module preconceptual design |
| Power boundary | Century's reported 39 kW average on 2025-09-30 was electrical input delivered to cables, not generated output |
| Site/grid state | no selected pilot-plant site, license/application, PPA or interconnection located; Centralia was a feasibility study, not a selected Zap plant |
| Missing promotion proof | DOE action object, fusion-producing integrated platform, gain, plant site, license, commercial contract, interconnection and electricity |
Sources: Century milestone · Century input-power result · FuZE-3 pressure result · pilot-design approval reported by Zap
Section 3 of 4
### Appropriation and request clocks
All values are nominal dollars. FY2026 is enacted control; FY2027 is a budget request and must not be reported as funded.
| Object | FY2026 enacted | FY2027 request | Ruling |
|---|---|---|---|
| FES research | $634.973M | $677.751M | enacted vs request |
| U.S. ITER construction | $170.684M | $77.500M | enacted vs requested reduction |
| Total FES | $805.657M | $755.251M | FY2027 request is $50.406M below FY2026 enacted |
| Public-Private Partnerships | $100.000M | $135.000M | parent program line, not award ledger |
| Closing the Fusion Cycle | $56.238M | $89.000M | enacted vs request |
| Fusion Materials/Internal Components | $76.411M | $68.000M | enacted vs request |
| Theory/Simulation | $65.776M | $72.540M | enacted vs request |
| Sustain a Burning Plasma | $141.661M | $140.000M | enacted vs request |
| Discovery Plasma S&T | $65.000M | $55.900M | enacted vs request |
| DIII-D operations | $74.000M | $61.000M | requested operating reduction |
| NSTX-U operations | $50.200M | $47.000M | requested operating reduction |
| MPEX operations | $0 | $1.000M | startup request, not operation |
| Office of Fusion separate account | $0 | $10.000M | first requested standalone account; not enacted |
FY2026 directs at least $70 million of the $100 million PPP line to the Milestone Program. Absent transfers or other accounts, no more than $30 million within that parent line remains for INFUSE, Private Facility Research and Fusion BRIDGE collectively. A public execution breakout was not located. FIRE is distributed through core FES research lines and must not be added to the PPP line as a separate subaccount.
The FY2026 explanatory statement gives MPEX $25.473 million while DOE's FY2027 capital table reports FY2026 enacted at $25.180 million. Preserve the discrepancy until an execution/control table resolves it. The FY2027 request also includes $8 million for Integrated Blanket/Fuel Cycle Test Facility design; design money is not construction authority.
Sources: P.L. 119-74 · FY2026 explanatory statement · FY2027 FES request · FY2027 Office of Fusion request
### Milestone award accounting
USAspending data current through 2026-08-15 records the eight Technology Investment Agreements with cumulative obligations of $110.685 million and linked outlays of $28.490 million.
| Recipient / award | Cumulative obligation | Linked outlay | Displayed award end |
|---|---|---|---|
Commonwealth Fusion Systems — DESC0024885 |
$33.085M | $9.700M | 2025-12-04 |
Zap Energy — DESC0024886 |
$17.800M | $4.000M | 2027-06-04 |
Thea Energy — DESC0024881 |
$13.700M | $3.000M | 2027-06-04 |
Xcimer Energy — DESC0024890 |
$13.500M | $1.500M | 2026-03-31 |
Type One Energy — DESC0024888 |
$9.500M | $2.000M | 2025-12-04 |
Realta Fusion — DESC0024887 |
$8.100M | $3.140M | 2025-12-04 |
Tokamak Energy — DESC0024889 |
$7.500M | $3.000M | 2026-01-31 |
Focused Energy — DESC0024883 |
$7.500M | $2.150M | 2025-12-04 |
The initial June 2024 obligations total exactly $46 million. January 10–15, 2025 revisions add $36.6 million. Only Zap (+$8.3 million on June 1), Thea (+$6.2 million on June 9) and CFS (+$13.585 million on July 13) show positive 2026 revisions in the checked data.
These accounting objects do not supply a one-to-one milestone/payment join. That requires the TIA amendment, verification memorandum, invoice and payment record. An outlay is a disbursement linked to an award; it does not establish the recipient's cash-receipt instant or the technical milestone settled.
CFS's displayed award period ends 2025-12-04 while its current total includes a July 2026 revision. The July amendment and period-of-performance record are a high-priority retrieval item rather than grounds to silently correct the public display.
Sources: USAspending freshness · DOE FES public-private partnerships
## Other federal program states
| Program | Highest demonstrated rung | Missing next proof |
|---|---|---|
| Milestone Program | executed TIAs -> obligations -> some outlays -> publicly identified verified milestones | amendment-level milestone/payment join, results and closeout |
| INFUSE | recurring selections/vouchers; 20 one-year projects totaling $6.1 million selected 2025-09-10 | executed CRADA/subcontract, exact voucher value, lab work and delivered result |
| FIRE round 1 | six teams selected 2025-01-16 | executed award/FWP IDs, obligations, work packages and outputs |
| FIRE round 2 | seven teams selected 2025-09-10 | same |
| Private Facility Research | FY2025 pilot named in budget/roadmap | project list, host facility, instrument and open research output |
| Fusion BRIDGE | funded parent-account narrative and roadmap program design | solicitation, consortium agreement, award, cost share, site, construction and operation |
| Genesis fusion/DCP | RFA issued; 278 cross-domain projects selected 2026-07-22 for negotiations | executed OTA/FWP, amount, platform access, logged workflow and experiment/result |
| Office of Fusion | organizational office and roadmap mandate | named successor, enacted operating account, staff/FTE, governance and reporting cadence |
| MPEX | construction project | reconciled baseline/TPC, commissioning, CD-4 and operating test output |
| IB-FCTF / FPNS | studies, design or mission-need stage | CD-0/1, site, construction appropriation, build and operation |
FIRE announcements mix current-year tranches, selected multi-year scope and contingent outyears. Official selection material preserves the negotiation/no- commitment disclaimer; do not convert $107 million or $128 million headlines into obligations without PAMS/FWP records. INFUSE selections likewise require the executed instrument and delivered laboratory result.
Sources: FIRE round 1 list · FIRE/INFUSE September 2025 release · INFUSE selections
## Genesis and AI-Fusion DCP implementation
The March 17, 2026 Genesis RFA anticipated $293.76 million across all subjects, not fusion alone. Phase I was described as $500,000–$750,000 for nine months; Phase II as $6–$15 million over three years. Laboratory work may use Field Work Proposals while non-laboratory awards may use Other Transaction Authority, so a USAspending-only audit is incomplete.
The RFA makes the fusion DCP more concrete than the roadmap alone. It calls for:
The July 22 selection list includes named work on fusion design orchestration, control twins, structural-material creep/fatigue, born-digital interfaces, REBCO and magnet manufacturing, a D-T process-loop replica, a multimodal multi-device foundation model, plant lifecycle engineering, Realta neutral-beam optimization, PPPL gyrotron delivery, target manufacturing, diagnostic edge AI, lithium-isotope separation, stellarator blanket/neutronics optimization and structural-alloy scale-up.
All 278 projects remain selections for award negotiation in the public
record. The list gives neither phase nor project amount, and the promise that
awardees will gain platform access is prospective. The separate more than
$800 million partner figure mixes compute credits, model access, cloud
infrastructure, expertise, partnerships and some direct funding; it is neither
all cash nor fusion-specific.
Operating promotion test: an authenticated user or system accesses a named DCP resource, executes a logged cross-resource workflow, calls or informs a physical experiment and receives a traceable result with model, data, instrument, identity, time and correction state.
Sources: Genesis RFA announcement · full RFA · July 22 selections · project list · partner commitments · DIII-D Diag2Diag result
## Bottleneck and facility registry
The commercialization race is not only a confinement race. Promote these named bottleneck objects independently of company plant schedules:
| Object | Current state | Required next proof |
|---|---|---|
| MPEX | construction; FY2027 request recognizes cost pressure and retains January 2028 CD-4 target | reconciled baseline/TPC, commissioning and accepted operating result |
| Integrated Blanket/Fuel Cycle Test Facility | FY2027 request includes design funding | approved mission need/baseline, site, construction money, build and operation |
| Fusion Prototypic Neutron Source | planning/mission-need lane | CD state, site, representative test envelope, construction and qualified output |
| Bull Run high-heat-flux facility | site conditioning; end-2027 completion target | site/instrument record, commissioning and qualified material/component result |
| Tritium/helium-3 availability | directed report clock; public report not located | report, inventory/supply, transport, recovery, accountancy and breeding evidence |
| HTS/REBCO supply chain | company and Genesis projects active | conductor capacity, repeatable cable/coil fabrication, joints, quench protection, irradiation performance and QA |
| Remote maintenance / hot cells | roadmap and Genesis project lane | radiation-compatible robotics, component exchange, recovery demonstration and RAMI record |
| DIII-D / NSTX-U | operating/recovery assets with FY2027 requested reductions | actual availability, weeks of operation, NSTX-U commissioning and experiment results |
Section 4 of 4
## Material event and publication clocks
These clocks preserve primary-source precision for later astrology. A publication timestamp is not substituted for the underlying agreement, experiment, filing or legal act. A dateline is not proof of web-publication location. The D.C. chart convention and chart selection remain in the separate fusion date/time/place ledger.
| Clock ID | Object | Source clock | Locus / precision ruling |
|---|---|---|---|
FUS-MILESTONE-SELECT-20230531 |
eight Milestone recipients selected | 2023-05-31; time not stated | DOE selection; date-only |
FUS-MILESTONE-TIA-20240603-05 |
eight TIAs signed | 2024-06-03 through 2024-06-05 | signature window; exact recipient/signature times and places unretrieved; not a point chart |
FUS-MILESTONE-PUB-20240606 |
DOE announces all eight agreements | 2024-06-06; time not stated | online publication; date-only |
FUS-REALTA-WHAM-20240715 |
WHAM first plasma | 2024-07-15; time not stated | physical event, Stoughton, Wisconsin; date-only |
FUS-CFS-LIC-20241024 |
SPARC radioactive-materials license reported granted | 2024-10-24; time not stated | Massachusetts regulatory object; exact issuance clock/place not in checked release |
FUS-MILESTONE-UPDATE-20250116 |
DOE identifies five completed early milestones | 2025-01-16; time not stated | DOE publication; date-only; underlying verification clocks unresolved |
FUS-ZAP-CENTURY-20250225 |
Zap reports DOE certification of Century milestone | 2025-02-25; time not stated | company publication; underlying DOE verification time unresolved |
FUS-TYPEONE-IDR-PUB-20250527 |
Type One initial design review release | 2025-05-27T20:14:26Z / 4:14:26 p.m. EDT |
exact publication second; Knoxville dateline only, not publication location |
FUS-CFS-GOOGLE-20250630 |
Google 200 MW PPA announced | 2025-06-30; time not stated | contract/publication date; signature clock/place unresolved |
FUS-TYPEONE-PSS-PUB-20250722 |
first TVA PSS contracts released | 2025-07-22T20:13:40Z / 4:13:40 p.m. EDT |
exact publication second; execution time unresolved |
FUS-TYPEONE-LOI-PUB-20250919 |
TVA/Type One LOI released | 2025-09-20T00:36:27Z / 2025-09-19 8:36:27 p.m. EDT |
exact publication second; LOI issuance/signature time unresolved |
FUS-CFS-ENI-20250922 |
Eni PPA announced | 2025-09-22; time not stated | contract/publication date; signature clock/place unresolved |
FUS-CFS-MAGNET-20250930 |
CFS reports DOE magnet validation and $8M payment | 2025-09-30; time not stated | company publication; validation/payment clocks unresolved |
FUS-THEA-DESIGN-20260113 |
Thea reports DOE certification of Helios preconceptual design | 2026-01-13; time not stated | company publication; DOE decision clock unresolved |
FUS-TYPEONE-APP-PUB-20260129 |
Type One initial-application announcement | 2026-01-29T14:36:00Z / 9:36 a.m. EST |
exact publication minute; filing time/place unresolved |
FUS-TN-RULE-FILE-20260311 |
rule filing received by Tennessee Secretary of State | 2026-03-11 10:37 a.m.; timezone unstated | stamped minute; Nashville administrative form locus, delivery mode unresolved |
FUS-REALTA-CFS-PUB-20260402 |
Realta/CFS magnet partnership publication | 2026-04-02 5:00 a.m. ET / 09:00Z |
exact publication minute; not contract-signature clock |
FUS-CFS-PJM-20260428 |
CFS announces PJM interconnection application | 2026-04-28; time not stated | application/announcement date; PJM receipt/queue-validation clock unresolved |
FUS-THEA-COIL-20260513 |
Thea full-scale shaping-coil operation announced | 2026-05-13; test time not stated | hardware result; Kearny, New Jersey; date-only |
FUS-ZAP-DESIGN-20260519 |
Zap reports DOE approval of pilot design | 2026-05-19; time not stated | company publication; DOE decision clock unresolved |
FUS-FOCUSED-SERIESA-20260527 |
Focused announces $240M Series A | 2026-05-27; time not stated | transaction/publication date; close/signature clock unresolved |
FUS-XCIMER-PHOENIX-20260603 |
Xcimer announces Phoenix operations | 2026-06-03; operating-start time not stated | Denver physical platform; date-only publication, not proof of fusion shot |
FUS-THEA-TWIN-20260608 |
Helios digital-twin collaboration announced | 2026-06-08; time not stated | distributed design/model program; date-only |
FUS-XCIMER-DESIGN-20260610 |
Xcimer reports DOE approval of Athena design/roadmap | 2026-06-10; time not stated | company publication; DOE decision clock unresolved |
FUS-REALTA-DEC-20260619 |
WHAM direct-energy-conversion experiment | 2026-06-19; time not stated | physical event, Stoughton, Wisconsin; date-only |
FUS-REALTA-DEC-PUB-20260630 |
Realta DEC release publication | 2026-06-30 7:00 a.m. ET / 11:00Z |
exact publication minute; not experiment time |
FUS-THEA-SCALEUP-20260709 |
ARPA-E selects Thea for up to $20M | 2026-07-09; time not stated | federal selection date; not obligation/payment |
FUS-CFS-OBL-20260713 |
USAspending positive obligation revision | 2026-07-13; transaction time not supplied | federal award-accounting date; technical milestone not identified |
FUS-REALTA-FORGE-PUB-20260715 |
Forge/Hammir site and incentives announced | 2026-07-15 8:00 a.m. ET / 12:00Z |
exact publication minute; project site Madison, publication origin unresolved |
GEN-FUSION-SELECT-20260722 |
Genesis project selections announced | 2026-07-22; time not stated | selection for negotiation, not award or platform access |
FUS-FOCUSED-BIBLIS-20260729 |
Biblis selected as German laser-fusion hub | 2026-07-29; time not stated | Biblis, Germany; date-only |
Partial future dates remain non-point-chartable: Infinity Two construction
as early as 2028, Infinity One commissioning/startup 2029, Xcimer Anvil
2028, Eos by 2030, and the various mid-2030s plant targets.
## Source defects and unresolved seams
not funded
under the Milestone Program. DOE's award list, roadmap, CFS agreement and
reported payment contradict that sentence. Preserve it as an apparent NRC
page error pending correction.not publicly located,
not noncompliance.### Event candidates for canonical Energy review