Federal fusion project, capital and regulatory registry, 2022–2035

.md · 4 sections · 44228 characters

Source, owner, and dates

workbench: Research Packages/Federal Science Operating System/FEDERAL_FUSION_PROJECT_CAPITAL_REGULATORY_REGISTRY_2022-2035.md

Canonical source SHA-256: 83ff6562a2d3e0a567832670f003266c7d7509b92c14fe229c6f32c6a5e67ea2

Served copy SHA-256: 83ff6562a2d3e0a567832670f003266c7d7509b92c14fe229c6f32c6a5e67ea2

Owner evidence cutoffs: {"federal-science-operating-system": "2026-10-12", "federal-fusion-commercialization": "2026-08-15", "genesis-mission": "2026-10-13"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: federal-science-operating-system, federal-fusion-commercialization, genesis-mission

Federal fusion project, capital and regulatory registry, 2022–2035

Section 1 of 4

# Federal fusion project, capital and regulatory registry, 2022–2035

Evidence cutoff: 2026-08-15
Status: current workbench research; object-level implementation registry
Scope: the eight companies in DOE's Milestone-Based Fusion Development Program, their machines and sites, public capital, verified milestones, regulatory and grid objects, and the Genesis-linked implementation layer
Authority boundary: federal, state, utility, laboratory and local-government records control public-program and regulatory state. Company records establish company designs, contracts, experiments and claims only at the verb and boundary the source supports.

## Short answer

DOE's eight Milestone companies are one funding cohort, not eight equivalent U.S. fusion power plants. At the cutoff:

The durable plot is therefore:

appropriation -> program allocation -> selection -> executed instrument -> obligation -> verified milestone -> outlay -> technical output -> commissioned capability -> licensed operation -> net electricity -> grid delivery

No current object reaches the end of that chain.

## Object and state rules

  1. A company, legal recipient, machine, site, program award and power plant are separate objects.
  2. selected, negotiating, executed, obligated, verified, outlaid, completed and closed are different capital states.
  3. A preconceptual-design review does not establish machine performance, site control, construction, licensing, interconnection or electricity.
  4. An operating laser, magnet, plasma or repetitive-pulse platform is not silently promoted to an operating fusion power plant.
  5. A PPA, letter of intent, land-use approval or interconnection application is meaningful commercial execution, but none proves construction or grid delivery.
  6. Company power figures remain design or target values until a measured plant record defines heat, gross electricity, internal/recirculating load, net electricity and export.
  7. Foreign-parent, foreign-machine and foreign-site facts remain visible. A U.S. DOE recipient is not automatically a U.S.-sited power project.

## Federal Milestone Program baseline

DOE selected the eight recipients on May 31, 2023 and announced that all eight had signed Technology Investment Agreements on June 6, 2024. Payments are conditional on satisfactory review of negotiated milestones. DOE initially obligated $46 million for the first 18 months; the $415 million program figure is a statutory authorization through FY2027, not an appropriation or an award already paid.

DOE's January 16, 2025 public update independently identified five completed early milestones: two for Focused Energy, one for Realta Fusion and two for Thea Energy. It said CFS, Tokamak Energy, Type One, Xcimer and Zap were still working on early science-and-technology milestones at that time. The June 2026 roadmap lists all eight as participating as of April 2026. Later company releases report additional DOE approvals; those retain the provenance company-reported DOE approval unless a DOE action record is cited.

Sources: DOE award list · DOE June 2024 strategy and agreements · DOE January 2025 milestone update · DOE 2026 roadmap

## Eight-company field registry

### Commonwealth Fusion Systems

Field Current defensible state
Legal/program object Commonwealth Fusion Systems, LLC; Milestone recipient
Approach high-field HTS tokamak
Current machine SPARC, under construction at CFS's Devens, Massachusetts campus; no first plasma or Q > 1 result at cutoff
Power-plant object ARC / Fall Line Fusion Power Station, proposed at the James River Industrial Center, Chesterfield County, Virginia
DOE milestone state first-phase agreement described by CFS as worth $15 million; CFS reported DOE validation of its full-scale toroidal-field magnet milestone and an $8 million payment on 2025-09-30
Regulatory/site state Massachusetts broad-scope radioactive-materials license for SPARC reported granted 2024-10-24; Chesterfield conditional-use permit approved in September 2025
Commercial state Google 200 MW PPA announced 2025-06-30; Eni PPA described as more than $1 billion announced 2025-09-22
Grid state CFS announced a PJM Cycle 1 interconnection application 2026-04-28; PJM confirmed fusion among Cycle 1 applicants 2026-04-29; no completed study or executed interconnection agreement located
Power claim ARC design about 1.1 GW fusion / 400 MWe net; target only
Missing promotion proof SPARC first plasma and gain; ARC final design/FID, construction authorization, interconnection studies/agreement, commissioning and measured electricity

The CFS chain is the strongest current example of commercial objects moving in parallel without yet constituting a plant: license for the research machine, land-use approval for the proposed plant, PPAs and a grid application are four different states.

Sources: SPARC · ARC · $15 million agreement · DOE magnet validation and payment reported by CFS · SPARC license · Chesterfield permit · Google PPA · Eni PPA · CFS PJM application · PJM confirmation

### Focused Energy

Field Current defensible state
Legal/program object Focused Energy Inc.; Milestone recipient with U.S. and German operations
Approach direct-drive laser inertial fusion plus proton fast ignition; LightHouse architecture and Pearl D-T targets
Current facilities Darmstadt targetry laboratory; Austin target-tracking and engagement facility reported open in early 2026; announced Bay Area laser-development facility not proven operating
Plant/site object Biblis, Germany is the current industrialization/pilot-plant site lane; no named U.S. power-plant site located
DOE milestone state DOE independently identifies completed high-gain-target modeling and ion-beam-focusing milestones; Focused reports DOE verification of both
Capital state $240 million Series A announced 2026-05-27; RWE entered as investor and site/approval partner
Power target company roadmap: diagnostic chamber first light 2031, implosion 2033, pilot plant 2035 and first grid MWh 2037
Missing promotion proof approved preconceptual design, U.S. project site, license, construction, PPA/interconnection and architecture-specific ignition/gain

NIF's indirect-drive ignition record is not proof for Focused's distinct driver, target, proton-fast-ignition, chamber or repetition-rate architecture.

Sources: Focused early milestones · company and roadmap · $240 million Series A · Biblis hub

### Realta Fusion

Field Current defensible state
Legal/program object Realta Fusion, Inc.; Milestone recipient
Approach high-field axisymmetric/tandem magnetic mirror
Current machine WHAM, a 17 T research prototype at UW–Madison's Physical Sciences Laboratory in Stoughton, Wisconsin; first plasma 2024-07-15
Next project/site Hammir planned at The Realta Forge, OM Station/former Oscar Mayer plant, Madison; site and incentives announced, construction not begun at cutoff
DOE milestone state DOE identifies completed whole-device modeling of simple-mirror equilibria toward a tandem-mirror scientific-gain goal of at least 5; no public full preconceptual-design approval located
Physical result on 2026-06-19 a WHAM direct-energy converter drew multiple amps at about 100 volts during plasma operation, enough for a few lightbulbs
Boundary most converted energy was externally supplied plasma-heating input; Realta expressly says the result was neither net electricity nor large-scale conversion of fusion-born power
Site capital Wisconsin and Madison support described as up to $55 million; publication 2026-07-15 08:00 ET; groundbreaking expected before year-end, not completed
Missing promotion proof Hammir construction/commissioning, fusion-dominant direct conversion, gain, power-plant site, license, PPA/interconnection and net electricity

This is a real intermediate rung between plasma operation and power conversion, but it sits below engineering gain, net generation and grid delivery.

Sources: UW first plasma · WHAM direct-energy-conversion technical account · exact publication clock · Forge/Hammir site announcement · WEDC confirmation

Thea Energy

Section 2 of 4

### Thea Energy

Field Current defensible state
Legal/program object Thea Energy, Inc.; Milestone recipient
Approach software-controlled stellarator using arrays of planar HTS shaping coils
Current hardware full-size, full-current, full-field Eos shaping coil reported operated at Kearny, New Jersey on 2026-05-13
Machine/plant objects Eos, planned D-D neutron-source and integrated demonstration machine; Helios, D-T pilot/commercial design; Eos site not announced
DOE milestone state DOE independently confirms optimized-equilibria downselection and operation of one HTS planar-coil building block; Thea reported DOE certification/approval of the Helios preconceptual design on 2026-01-13
Genesis/AI join Helios digital twin and surrogate-model collaboration with NVIDIA, Synopsys, Argonne and PPPL announced 2026-06-08; design/model infrastructure, not DCP operation or a plant result
Supply-chain capital ARPA-E selected Thea on 2026-07-09 for up to $20 million to scale domestic modular HTS-magnet production; selection/maximum is not a paid amount
Power target Helios design about 1.1 GW thermal / 400 MWe net in the 2030s
Missing promotion proof Eos site/build/operation, independent DOE approval object, license, plant site, PPA/interconnection and electricity

Sources: DOE stellarator account · Helios design certification reported by Thea · full-scale coil · digital twin

### Tokamak Energy Inc.

Field Current defensible state
Legal/program object U.S. subsidiary at Bruceton Mills, West Virginia; Milestone recipient; operating machine belongs to the UK-centered company system
Approach high-field spherical tokamak
Current machine ST40 at Oxfordshire, UK; reported 1 MA plasma current and triple product about (8 +/- 2 x 10^18) m^-3 keV s in 2025, then paused for the LEAPS upgrade
DOE milestone state DOE said the company was still working on early milestones in January 2025; no public preconceptual-design approval located
Public-private capital $52 million ST40 upgrade announced 2024-12-05, divided evenly among DOE, UK DESNZ and Tokamak Energy
U.S. plant object no named U.S. pilot site, license, PPA or interconnection located
Power target current U.S. design page: 800 MW fusion / 85 MWe net in the mid-2030s; supersedes older up to 200 MWe public language
Boundary temperature, current and triple product are not energy gain or electricity

Sources: U.S. program page · fusion technology · $52 million ST40 upgrade · ST40 2025 result

### Type One Energy — Project Infinity / Bull Run

Project Infinity is an umbrella containing several separate objects:

Field Current defensible state
Approach optimized stellarator with non-planar HTS magnets
DOE milestone state DOE's January 2025 state was working on early milestones; Type One's 2025 initial design review was company-chaired with outside experts, not DOE certification
Utility execution TVA Power Service Shops fabrication/welding contracts announced 2025-07-22; actual limited contracts and site preparation, not Infinity Two construction
Commercial state TVA letter of intent announced 2025-09-19 for potential deployment once commercially ready; not a PPA and expressly gated by TVA Board, planning and regulatory review
Licensing state Type One reported an initial byproduct-material application submitted 2026-01-29; no public application, receipt, docket, completeness finding, disposition, license, inspection or operating authorization located
State framework Tennessee Chapter 0400-20-14 filed 2026-03-11 at 10:37 a.m., timezone unstated, and effective 2026-06-09; a framework is not a project license
Site-control state TVA ownership/control and Type One's authorized physical use are publicly established; exact lease/access/site-use instrument and final Infinity Two footprint are not public
Workforce/capital commitment Tennessee Nuclear Fund database: $4.5 million contracted award, 330-job commitment and $223.5 million investment commitment; commitments are not realized totals
Grid state no public Infinity Two queue request, study, agreement or point of interconnection located

#### The 350/400 MWe seam

Dated 2025 releases, the January 2026 licensing announcement, TVA's current page and NRC's current page retain 350 MWe. Current Type One copy and TDEC's June 2026 release use 400 MWe from the same stated 800 MW fusion design. No primary change-control record explains the increase. Preserve the values as source versions; do not average them or treat them as two plants.

The January package cannot have been a completed application under Chapter 0400-20-14, which was filed in March and effective in June. Type One calls it an initial filing and TDEC says it laid groundwork for subsequent submissions. Its exact scope—Infinity One, Infinity Two, both, or a staged campus safety basis—remains unresolved.

Sources: TVA fusion page · TVA FY2025 Form 10-K · TVA/Type One cooperative agreement release · PSS contracts · TVA LOI · initial application announcement · TDEC rules release · operative Tennessee rule · NRC Agreement-State activities · ORNL high-heat-flux facility · Tennessee Nuclear Fund

### Xcimer Energy

Field Current defensible state
Legal/program object Xcimer Energy Inc.; Milestone recipient
Approach KrF excimer-laser inertial fusion with stimulated Brillouin scattering and a HYLIFE-type liquid-wall chamber
Current platform Phoenix, operating in a 74,000-square-foot Denver laser bay; demonstrated integrated laser amplification/compression and more than 1 kJ, not a fusion shot or ignition
Next machines Anvil, planned 200 kJ-on-target step for 2028; Vulcan, planned 4 MJ and upgradeable 12 MJ engineering-breakeven machine at an unselected site
Plant object Athena, planned roughly 400 MWe architecture in the mid-2030s
DOE milestone state Xcimer reported DOE approval of Athena's preconceptual design and technology roadmap on 2026-06-10
Missing promotion proof DOE action object, Anvil/Vulcan site/build/operation, architecture-specific ignition/gain, license, PPA/interconnection and electricity

NIF's result does not establish performance of Xcimer's KrF driver, target, liquid chamber, repetition rate or wall-plug loop.

Sources: Phoenix operations · Athena design approval reported by Xcimer · current project ladder · commercialization roadmap

### Zap Energy

Field Current defensible state
Legal/program object Zap Energy, Inc.; Milestone recipient
Approach sheared-flow-stabilized Z pinch without external confinement magnets or lasers
Plasma machines FuZE-Q and FuZE-3; FuZE-3's 2025 pressure result is a preliminary path-to-gain metric, not Q > 1
Engineering platform Century, an operating repetitive pulsed-power/liquid-metal test platform using ordinary hydrogen/helium; it does not produce fusion reactions or neutrons
DOE milestone state Zap reported DOE-certified completion on 2025-02-25 of a three-hour, 1,080-shot Century milestone; it reported DOE approval on 2026-05-19 of an approximately 50 MWe-net-per-module preconceptual design
Power boundary Century's reported 39 kW average on 2025-09-30 was electrical input delivered to cables, not generated output
Site/grid state no selected pilot-plant site, license/application, PPA or interconnection located; Centralia was a feasibility study, not a selected Zap plant
Missing promotion proof DOE action object, fusion-producing integrated platform, gain, plant site, license, commercial contract, interconnection and electricity

Sources: Century milestone · Century input-power result · FuZE-3 pressure result · pilot-design approval reported by Zap

## Public-capital ledger

Appropriation and request clocks

Section 3 of 4

### Appropriation and request clocks

All values are nominal dollars. FY2026 is enacted control; FY2027 is a budget request and must not be reported as funded.

Object FY2026 enacted FY2027 request Ruling
FES research $634.973M $677.751M enacted vs request
U.S. ITER construction $170.684M $77.500M enacted vs requested reduction
Total FES $805.657M $755.251M FY2027 request is $50.406M below FY2026 enacted
Public-Private Partnerships $100.000M $135.000M parent program line, not award ledger
Closing the Fusion Cycle $56.238M $89.000M enacted vs request
Fusion Materials/Internal Components $76.411M $68.000M enacted vs request
Theory/Simulation $65.776M $72.540M enacted vs request
Sustain a Burning Plasma $141.661M $140.000M enacted vs request
Discovery Plasma S&T $65.000M $55.900M enacted vs request
DIII-D operations $74.000M $61.000M requested operating reduction
NSTX-U operations $50.200M $47.000M requested operating reduction
MPEX operations $0 $1.000M startup request, not operation
Office of Fusion separate account $0 $10.000M first requested standalone account; not enacted

FY2026 directs at least $70 million of the $100 million PPP line to the Milestone Program. Absent transfers or other accounts, no more than $30 million within that parent line remains for INFUSE, Private Facility Research and Fusion BRIDGE collectively. A public execution breakout was not located. FIRE is distributed through core FES research lines and must not be added to the PPP line as a separate subaccount.

The FY2026 explanatory statement gives MPEX $25.473 million while DOE's FY2027 capital table reports FY2026 enacted at $25.180 million. Preserve the discrepancy until an execution/control table resolves it. The FY2027 request also includes $8 million for Integrated Blanket/Fuel Cycle Test Facility design; design money is not construction authority.

Sources: P.L. 119-74 · FY2026 explanatory statement · FY2027 FES request · FY2027 Office of Fusion request

### Milestone award accounting

USAspending data current through 2026-08-15 records the eight Technology Investment Agreements with cumulative obligations of $110.685 million and linked outlays of $28.490 million.

Recipient / award Cumulative obligation Linked outlay Displayed award end
Commonwealth Fusion Systems — DESC0024885 $33.085M $9.700M 2025-12-04
Zap Energy — DESC0024886 $17.800M $4.000M 2027-06-04
Thea Energy — DESC0024881 $13.700M $3.000M 2027-06-04
Xcimer Energy — DESC0024890 $13.500M $1.500M 2026-03-31
Type One Energy — DESC0024888 $9.500M $2.000M 2025-12-04
Realta Fusion — DESC0024887 $8.100M $3.140M 2025-12-04
Tokamak Energy — DESC0024889 $7.500M $3.000M 2026-01-31
Focused Energy — DESC0024883 $7.500M $2.150M 2025-12-04

The initial June 2024 obligations total exactly $46 million. January 10–15, 2025 revisions add $36.6 million. Only Zap (+$8.3 million on June 1), Thea (+$6.2 million on June 9) and CFS (+$13.585 million on July 13) show positive 2026 revisions in the checked data.

These accounting objects do not supply a one-to-one milestone/payment join. That requires the TIA amendment, verification memorandum, invoice and payment record. An outlay is a disbursement linked to an award; it does not establish the recipient's cash-receipt instant or the technical milestone settled.

CFS's displayed award period ends 2025-12-04 while its current total includes a July 2026 revision. The July amendment and period-of-performance record are a high-priority retrieval item rather than grounds to silently correct the public display.

Sources: USAspending freshness · DOE FES public-private partnerships

## Other federal program states

Program Highest demonstrated rung Missing next proof
Milestone Program executed TIAs -> obligations -> some outlays -> publicly identified verified milestones amendment-level milestone/payment join, results and closeout
INFUSE recurring selections/vouchers; 20 one-year projects totaling $6.1 million selected 2025-09-10 executed CRADA/subcontract, exact voucher value, lab work and delivered result
FIRE round 1 six teams selected 2025-01-16 executed award/FWP IDs, obligations, work packages and outputs
FIRE round 2 seven teams selected 2025-09-10 same
Private Facility Research FY2025 pilot named in budget/roadmap project list, host facility, instrument and open research output
Fusion BRIDGE funded parent-account narrative and roadmap program design solicitation, consortium agreement, award, cost share, site, construction and operation
Genesis fusion/DCP RFA issued; 278 cross-domain projects selected 2026-07-22 for negotiations executed OTA/FWP, amount, platform access, logged workflow and experiment/result
Office of Fusion organizational office and roadmap mandate named successor, enacted operating account, staff/FTE, governance and reporting cadence
MPEX construction project reconciled baseline/TPC, commissioning, CD-4 and operating test output
IB-FCTF / FPNS studies, design or mission-need stage CD-0/1, site, construction appropriation, build and operation

FIRE announcements mix current-year tranches, selected multi-year scope and contingent outyears. Official selection material preserves the negotiation/no- commitment disclaimer; do not convert $107 million or $128 million headlines into obligations without PAMS/FWP records. INFUSE selections likewise require the executed instrument and delivered laboratory result.

Sources: FIRE round 1 list · FIRE/INFUSE September 2025 release · INFUSE selections

## Genesis and AI-Fusion DCP implementation

The March 17, 2026 Genesis RFA anticipated $293.76 million across all subjects, not fusion alone. Phase I was described as $500,000–$750,000 for nine months; Phase II as $6–$15 million over three years. Laboratory work may use Field Work Proposals while non-laboratory awards may use Other Transaction Authority, so a USAspending-only audit is incomplete.

The RFA makes the fusion DCP more concrete than the roadmap alone. It calls for:

The July 22 selection list includes named work on fusion design orchestration, control twins, structural-material creep/fatigue, born-digital interfaces, REBCO and magnet manufacturing, a D-T process-loop replica, a multimodal multi-device foundation model, plant lifecycle engineering, Realta neutral-beam optimization, PPPL gyrotron delivery, target manufacturing, diagnostic edge AI, lithium-isotope separation, stellarator blanket/neutronics optimization and structural-alloy scale-up.

All 278 projects remain selections for award negotiation in the public record. The list gives neither phase nor project amount, and the promise that awardees will gain platform access is prospective. The separate more than $800 million partner figure mixes compute credits, model access, cloud infrastructure, expertise, partnerships and some direct funding; it is neither all cash nor fusion-specific.

Operating promotion test: an authenticated user or system accesses a named DCP resource, executes a logged cross-resource workflow, calls or informs a physical experiment and receives a traceable result with model, data, instrument, identity, time and correction state.

Sources: Genesis RFA announcement · full RFA · July 22 selections · project list · partner commitments · DIII-D Diag2Diag result

## Bottleneck and facility registry

The commercialization race is not only a confinement race. Promote these named bottleneck objects independently of company plant schedules:

Object Current state Required next proof
MPEX construction; FY2027 request recognizes cost pressure and retains January 2028 CD-4 target reconciled baseline/TPC, commissioning and accepted operating result
Integrated Blanket/Fuel Cycle Test Facility FY2027 request includes design funding approved mission need/baseline, site, construction money, build and operation
Fusion Prototypic Neutron Source planning/mission-need lane CD state, site, representative test envelope, construction and qualified output
Bull Run high-heat-flux facility site conditioning; end-2027 completion target site/instrument record, commissioning and qualified material/component result
Tritium/helium-3 availability directed report clock; public report not located report, inventory/supply, transport, recovery, accountancy and breeding evidence
HTS/REBCO supply chain company and Genesis projects active conductor capacity, repeatable cable/coil fabrication, joints, quench protection, irradiation performance and QA
Remote maintenance / hot cells roadmap and Genesis project lane radiation-compatible robotics, component exchange, recovery demonstration and RAMI record
DIII-D / NSTX-U operating/recovery assets with FY2027 requested reductions actual availability, weeks of operation, NSTX-U commissioning and experiment results

Material event and publication clocks

Section 4 of 4

## Material event and publication clocks

These clocks preserve primary-source precision for later astrology. A publication timestamp is not substituted for the underlying agreement, experiment, filing or legal act. A dateline is not proof of web-publication location. The D.C. chart convention and chart selection remain in the separate fusion date/time/place ledger.

Clock ID Object Source clock Locus / precision ruling
FUS-MILESTONE-SELECT-20230531 eight Milestone recipients selected 2023-05-31; time not stated DOE selection; date-only
FUS-MILESTONE-TIA-20240603-05 eight TIAs signed 2024-06-03 through 2024-06-05 signature window; exact recipient/signature times and places unretrieved; not a point chart
FUS-MILESTONE-PUB-20240606 DOE announces all eight agreements 2024-06-06; time not stated online publication; date-only
FUS-REALTA-WHAM-20240715 WHAM first plasma 2024-07-15; time not stated physical event, Stoughton, Wisconsin; date-only
FUS-CFS-LIC-20241024 SPARC radioactive-materials license reported granted 2024-10-24; time not stated Massachusetts regulatory object; exact issuance clock/place not in checked release
FUS-MILESTONE-UPDATE-20250116 DOE identifies five completed early milestones 2025-01-16; time not stated DOE publication; date-only; underlying verification clocks unresolved
FUS-ZAP-CENTURY-20250225 Zap reports DOE certification of Century milestone 2025-02-25; time not stated company publication; underlying DOE verification time unresolved
FUS-TYPEONE-IDR-PUB-20250527 Type One initial design review release 2025-05-27T20:14:26Z / 4:14:26 p.m. EDT exact publication second; Knoxville dateline only, not publication location
FUS-CFS-GOOGLE-20250630 Google 200 MW PPA announced 2025-06-30; time not stated contract/publication date; signature clock/place unresolved
FUS-TYPEONE-PSS-PUB-20250722 first TVA PSS contracts released 2025-07-22T20:13:40Z / 4:13:40 p.m. EDT exact publication second; execution time unresolved
FUS-TYPEONE-LOI-PUB-20250919 TVA/Type One LOI released 2025-09-20T00:36:27Z / 2025-09-19 8:36:27 p.m. EDT exact publication second; LOI issuance/signature time unresolved
FUS-CFS-ENI-20250922 Eni PPA announced 2025-09-22; time not stated contract/publication date; signature clock/place unresolved
FUS-CFS-MAGNET-20250930 CFS reports DOE magnet validation and $8M payment 2025-09-30; time not stated company publication; validation/payment clocks unresolved
FUS-THEA-DESIGN-20260113 Thea reports DOE certification of Helios preconceptual design 2026-01-13; time not stated company publication; DOE decision clock unresolved
FUS-TYPEONE-APP-PUB-20260129 Type One initial-application announcement 2026-01-29T14:36:00Z / 9:36 a.m. EST exact publication minute; filing time/place unresolved
FUS-TN-RULE-FILE-20260311 rule filing received by Tennessee Secretary of State 2026-03-11 10:37 a.m.; timezone unstated stamped minute; Nashville administrative form locus, delivery mode unresolved
FUS-REALTA-CFS-PUB-20260402 Realta/CFS magnet partnership publication 2026-04-02 5:00 a.m. ET / 09:00Z exact publication minute; not contract-signature clock
FUS-CFS-PJM-20260428 CFS announces PJM interconnection application 2026-04-28; time not stated application/announcement date; PJM receipt/queue-validation clock unresolved
FUS-THEA-COIL-20260513 Thea full-scale shaping-coil operation announced 2026-05-13; test time not stated hardware result; Kearny, New Jersey; date-only
FUS-ZAP-DESIGN-20260519 Zap reports DOE approval of pilot design 2026-05-19; time not stated company publication; DOE decision clock unresolved
FUS-FOCUSED-SERIESA-20260527 Focused announces $240M Series A 2026-05-27; time not stated transaction/publication date; close/signature clock unresolved
FUS-XCIMER-PHOENIX-20260603 Xcimer announces Phoenix operations 2026-06-03; operating-start time not stated Denver physical platform; date-only publication, not proof of fusion shot
FUS-THEA-TWIN-20260608 Helios digital-twin collaboration announced 2026-06-08; time not stated distributed design/model program; date-only
FUS-XCIMER-DESIGN-20260610 Xcimer reports DOE approval of Athena design/roadmap 2026-06-10; time not stated company publication; DOE decision clock unresolved
FUS-REALTA-DEC-20260619 WHAM direct-energy-conversion experiment 2026-06-19; time not stated physical event, Stoughton, Wisconsin; date-only
FUS-REALTA-DEC-PUB-20260630 Realta DEC release publication 2026-06-30 7:00 a.m. ET / 11:00Z exact publication minute; not experiment time
FUS-THEA-SCALEUP-20260709 ARPA-E selects Thea for up to $20M 2026-07-09; time not stated federal selection date; not obligation/payment
FUS-CFS-OBL-20260713 USAspending positive obligation revision 2026-07-13; transaction time not supplied federal award-accounting date; technical milestone not identified
FUS-REALTA-FORGE-PUB-20260715 Forge/Hammir site and incentives announced 2026-07-15 8:00 a.m. ET / 12:00Z exact publication minute; project site Madison, publication origin unresolved
GEN-FUSION-SELECT-20260722 Genesis project selections announced 2026-07-22; time not stated selection for negotiation, not award or platform access
FUS-FOCUSED-BIBLIS-20260729 Biblis selected as German laser-fusion hub 2026-07-29; time not stated Biblis, Germany; date-only

Partial future dates remain non-point-chartable: Infinity Two construction as early as 2028, Infinity One commissioning/startup 2029, Xcimer Anvil 2028, Eos by 2030, and the various mid-2030s plant targets.

## Source defects and unresolved seams

  1. NRC's current Agreement-State activities page says CFS is not funded under the Milestone Program. DOE's award list, roadmap, CFS agreement and reported payment contradict that sentence. Preserve it as an apparent NRC page error pending correction.
  2. Thea, Xcimer and Zap describe DOE-certified/approved designs in detailed company releases; no matching standalone DOE action record was located.
  3. Type One's 350/400 MWe version conflict lacks a public change-control record.
  4. The January Bull Run application itself, receipt, scope, docket, fee, completeness finding and review status remain nonpublic or unretrieved.
  5. CFS's current USAspending amount includes a July 2026 revision despite a displayed 2025 award end. Retrieve the amendment and period extension.
  6. FIRE headline totals, current-year tranches and contingent outyears cannot be reconciled to executed instruments from public announcements alone.
  7. The FY2026 PPP execution split and Fusion BRIDGE solicitation/award objects were not located.
  8. A named Office of Fusion successor, separately enacted operating account, staffing plan and public reporting cadence were not located after JP Allain's departure.
  9. No public artifact was located for the February 22 FES strategy briefing or the July 22 directed helium-3/tritium report. Record not publicly located, not noncompliance.
  10. Exact physical-event times are absent for nearly every private-machine result. Publication clocks must not be substituted silently.

## Promotion queue

### Event candidates for canonical Energy review

  1. CFS PJM interconnection application — 2026-04-28. Strongest new grid object; application, not study/agreement/connection.
  2. Realta WHAM direct-energy conversion — 2026-06-19. Physical electricity conversion result with explicit input/net/fusion-born boundary.
  3. Thea Helios design certification — 2026-01-13. Company-reported DOE design milestone; not an operating device.
  4. Zap pilot-design approval — 2026-05-19. Company-reported DOE design milestone; not 50 MWe generated.
  5. Xcimer Athena design approval — 2026-06-10. Keep separate from Phoenix operations.
  6. CFS transaction chain. License, local permit, Google/Eni PPAs and PJM application should remain separate atoms if promoted.
  7. Realta Forge/Hammir site/incentives — 2026-07-15. Site selected and incentives announced; construction not begun.

### Standing research watches

## Interpretation firewall