Venezuela Oil and Gas Deal Execution Ledger

.md · 2 sections · 17550 characters

Source, owner, and dates

workbench: Research Packages/Global Oil and Gas Movements 2026/VENEZUELA_DEAL_EXECUTION_LEDGER_2026-09-15.md

Canonical source SHA-256: b4589dee045e1287460110a506aca099107707ed6cdedf284827790881274742

Served copy SHA-256: b4589dee045e1287460110a506aca099107707ed6cdedf284827790881274742

Owner evidence cutoffs: {"global-oil-gas-movements": "2026-09-30"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: global-oil-gas-movements

Venezuela Oil and Gas Deal Execution Ledger

Section 1 of 2

# Venezuela Oil and Gas Deal Execution Ledger

Evidence cutoff: 2026-09-15, America/New_York
Status: current factual ledger; underlying agreement/concession texts remain public-source gaps

## Bottom line

The Venezuela story is not one transaction. It is at least four linked but independent systems:

  1. a January U.S.-controlled marketing and proceeds corridor for existing Venezuelan crude and products;
  2. an OFAC permissions architecture covering oil, gas, diluent, services, PDVSA transactions, payments and eligible counterparties;
  3. a late-August NABEP/U.S. governance and future-offtake arrangement tied to claimed 100-year concessions over 17 fields; and
  4. separate September Chevron and Eni operating/investment agreements plus a GE Vernova grid agreement.

There is meaningful movement from rhetoric into signed/authorized structures, but most of the enormous future claims have not yet reached public receipts for capital deployed, field work, added production, lifting, controlled payment, tax/royalty receipt or U.S. offtake.

The phrase “as soon as early next year” does not mean first Venezuelan or first NABEP production. The focused VENEZUELA_EARLY_2027_FLOW_AND_READINESS_TEST_2026-09-15.md establishes that existing Venezuelan crude is already reaching the United States, while the early-2027 statement is a forecast for material deal/offtake-linked U.S. flow. No public cargo record yet joins current NABEP production to State's 20% at-cost right.

## The execution ladder

public announcement
→ controlling agreement / law / concession
→ exact legal entities and governance rights
→ sanctions and payment permission
→ financing commitment / FID / capital deployed
→ rigs, power, diluent and field rehabilitation
→ measured incremental production
→ nomination and terminal lifting
→ bill of lading / vessel / buyer / discharge
→ payment into the required controlled account
→ royalty, tax, dividend or sale-proceeds allocation
→ U.S. offtake exercise / SPR or other government receipt
→ sustained production and receipts

## State ledger

Object Public state at cutoff What the source establishes What it does not establish Next receipt
January U.S.–Venezuela energy deal B-OFFICIAL-REPORTING; execution claimed DOE said the U.S. began marketing Venezuelan crude/products, engaged commodity marketers and banks, expected an initial 30–50 million barrels, and required proceeds first to settle in U.S.-controlled accounts. Named cargoes, marketers, banks, contracts, prices, account statements, distributions or full performance of 30–50 million barrels. Cargo/B/L/export record joined to marketer, buyer, controlled-account credit and distribution.
EO 14373 / Foreign Government Deposit Funds A-OPERATIVE legal/payment framework OFAC FAQ 1247 requires covered payments to blocked Venezuelan persons into the Foreign Government Deposit Funds or another Treasury-instructed account, subject to the relevant license. A particular payment, account balance, allocation or final beneficiary. Treasury account instruction plus transaction credit and disbursement record.
OFAC GL 46D A-OPERATIVE authorization Defined oil/petrochemical lifting, sale, storage, purchase, delivery, transport and related conduct may proceed subject to conditions. A particular lifting or buyer; blanket unblocking of PDVSA or Venezuela. Contract + nomination + B/L + payment for one covered cargo.
OFAC GL 47B A-OPERATIVE authorization Defined U.S.-origin diluent sales and related conduct may proceed subject to conditions. A shipment, volume, supplier, Venezuelan receiver or use in a particular blend. Export/B/L/customs record joined to supplier, receiver, discharge and field/blend use.
OFAC GL 48C A-OPERATIVE authorization Defined items and services for Venezuelan operations may proceed subject to conditions. Equipment delivery, installation, field restoration or added production. Purchase order/award, customs/import receipt, installation and operating record.
OFAC GL 50C A-OPERATIVE authorization Listed entities may conduct defined oil/gas operations, investment and payment activity. That every oil company or field is covered; contract performance; production growth. Annex/entity match plus executed field transaction and operating receipt.
OFAC GL 52C A-OPERATIVE authorization; effective September 14 and superseding 52B Established U.S. entities may conduct defined transactions involving PDVSA/PdVSA Entities, including covered oil movement, supplies/diluent, investment/JV and due-diligence activity described by FAQ 1245, subject to contract, payment, counterparty, vessel and other exclusions. PDVSA unblocked generally; covered debt/equity or CITGO-governance action; a completed payment/trade. Covered transaction joined to PDVSA entity, contract, cargo/service, State/DOE report and controlled payment.
NABEP/U.S. arrangement D-ENTITY-CLAIM; signed arrangement described, underlying instruments not located White House says Venezuela granted NABEP 100-year concessions for 17 fields with about 65 billion barrels of proven reserves; OSC received rights to 35% of NABEP's parent; State received 20% at-cost offtake and first refusal on the rest; U.S. board controls apply; up to $100 billion investment is planned. Exact signatories/capacities, parent entity, issued equity, consideration, field schedule, concession texts, reserve auditor/effective date, capital commitment, production, lifting or offtake. Signed binational and company instruments; cap table; 17-field annex; concessions; reserve reports; financing and first operational receipts.
NABEP current-production claim D-ENTITY-CLAIM; 250,000 b/d current production asserted September 2 White House says the private company already produces 250,000 b/d. This is a dated government claim about the company, not a field ledger or regulator measurement. Which fields/JVs and equity basis are included; gross versus net production; grade; terminal; liftings; buyer; payment; whether the 17 new concessions contribute. NABEP legal-entity disclosure, field/operator production reports, entitlement schedule and cargo reconciliation.
NABEP at-cost flow by year-end forecast; no volume or route specified White House says at-cost oil will be flowing to the market by the end of 2026. Whether State exercised its option; volume, field, price formula, buyer, terminal, vessel, market destination, payment or receipt. Option exercise plus contract, nomination, B/L, discharge, invoice and controlled-account credit.
NABEP material U.S. flow forecast; early 2027 timing White House says material production will come to the United States as soon as early 2027 because of the offtake rights. “Material” volume; incremental production; option exercise; U.S. refinery; discharge; SPR or other government receipt. Field production, offtake exercise, U.S. customs/refinery receipt and any SPR procurement/acceptance record.
Chevron agreements D-ENTITY-CLAIM; signed agreements described with stronger operating detail Chevron says updated joint-venture terms and added Orinoco acreage underpin more than $7 billion of five-year investment and a target near 600,000 b/d; its subsidiary holds 49% of Petroindependencia. Agreement text, committed-versus-contingent capital schedule, FID by project, spend to date or achieved future production. SEC filing/contract exhibit, project sanction, capital spend, rig/well and production receipts.
Eni Junín 5 CPPH D-ENTITY-CLAIM; signed contract described, contract text not public Eni says it and PDVSA signed a 25-year CPPH; Eni becomes exclusive technical, financial and commercial operator; field currently produces about 12,000 b/d; the structure follows January 2026 hydrocarbons-law reform. Full fiscal terms, capex schedule, reserves-versus-oil-in-place reconciliation, added production, lifting or payment. CPPH text or official filing; FID/capex; well/production report; terminal and sale records.
GeoPark Bare Block CPP D-ENTITY-CLAIM furnished to SEC; executed contract described but not yet effective GeoPark's September 6-K says Beta Resources (V), indirectly controlled through Energy Assets International, executed a 25-year CPP with PDVSA Petróleo. GeoPark would fund approved work programs, hold a 65% net working interest and operate/commercialize under the CPP. Contract text, present effectiveness, approvals, sanctions clearance, a closed GeoPark share transaction or deployed field capital. The filing expressly says effectiveness remains subject to approvals, authorizations, regulatory and sanctions-compliance requirements, with an estimated maximum 120-day period. Effective-date/approval notice; CPP text; transaction closing; approved work program; capex and field-operating receipts.
Bare current production D-ENTITY-CLAIM; dated field-level operating claim The same 6-K reports about 11,000 b/d current gross production, about 1,100 existing wells and installed infrastructure. Regulator confirmation, GeoPark entitlement, field uptime, terminal route, cargo, buyer or payment. Forecast peak and plateau values are not current production. Monthly regulator/operator production; entitlement; terminal lifting; discharge and payment.
Nabors Venezuela rig contract D-ENTITY-CLAIM furnished to SEC; signed service contract and awarded rig described Nabors' September 4 investor materials say a multi-year rig contract was signed to recommence drilling and one Venezuelan rig is expected to start in early Q1 2027. Customer, field, rig identifier, contract value, mobilization, import, installation, spud or accepted operations. Customer/field disclosure, rig and customs record, mobilization, spud and operating report.
GE Vernova/CORPOELEC D-ENTITY-CLAIM; government and entity agreement description DOE says the agreement targets 1 GW within 24 months and another 5 GW over four years, following a June cooperation framework. Financing, equipment order, construction, energization or reliable delivered power to oil operations. Award, financed project list, equipment delivery, construction and grid-acceptance records.

## NABEP claim audit

Claim Ruling at cutoff Reason
The United States now owns 65 billion barrels of Venezuelan oil NOT ESTABLISHED AS TITLE The White House describes governance, equity and offtake rights tied to concessions. Subsurface hydrocarbons, concessions, company equity, reserves and produced barrels are different property objects.
The U.S. received a 35% equity stake at no cost RIGHT DESCRIBED; ISSUANCE/CAP TABLE NOT LOCATED The public fact sheet names an OSC right to a 35% parent-company interest, but the parent entity, issued security, consideration, closing and cap table are not public in the located record.
State owns 20% of all output OFFTAKE RIGHT DESCRIBED, NOT OWNERSHIP OR DELIVERY A purchase right at production cost is not present title to oil in place, produced inventory or a delivered cargo.
The deal will refill the SPR POSSIBLE USE, NOT AN ACQUISITION The White House says the 20% could facilitate SPR refill. DOE's SPR uses statutory procurement/exchange and delivery systems; no NABEP tender, award, quality acceptance, delivery or cavern receipt was located.
$100 billion has been invested FALSE AS PRESENT PERFORMANCE The amount is a plan/up-to figure. Financing, FID, capital calls and spend are separate clocks.
Venezuela will receive $200 billion in taxes and royalties FORECAST The figure is an expected 25-year total, not a current receivable or receipt.
Production will double in under five years TARGET Field-level project, power, diluent, drilling, decline and terminal receipts are required.
NABEP is currently producing 250,000 b/d OFFICIAL CLAIM; FIELD BASIS NOT LOCATED The September 2 White House release states the figure, but the public package still lacks the company/entity perimeter, field list, gross/net basis and regulator production table.
At-cost oil will flow by year-end 2026 FORECAST No option exercise, nominated volume, cargo, price formula, buyer, payment or market receipt is identified.
Material production will reach the United States in early 2027 FORECAST Offtake rights create a possible commercial path; they are not a nomination, lifting, U.S. import or refinery/SPR receipt.

Physical movement model

Section 2 of 2

## Physical movement model

### Existing/near-term barrel

field or JV production
→ gathering / upgrader or diluent blending
→ storage and export terminal
→ established U.S. entity / authorized non-U.S. participant
→ vessel nomination and non-blocked vessel
→ B/L and export
→ refinery or third-country discharge
→ payment into required U.S.-controlled or Treasury-instructed account
→ authorized distribution

### Future NABEP or expanded-major barrel

concession/field right
→ financing and field development
→ power + equipment + diluent + drilling
→ incremental measured production
→ gathering/upgrading/terminal capacity
→ State 20% option or first-refusal decision
→ sale/offtake contract
→ nomination/lifting/discharge
→ payment and fiscal allocation

The second path cannot be drawn as an observed trade flow until it reaches the movement states. On the future globe it belongs in a dashed deal_target layer.

## Known destination and infrastructure questions

## Primary sources

## Highest-value document requests

  1. The signed U.S.–Venezuela agreement announced August 28.
  2. OSC/NABEP equity instrument, parent-company identity, closing record and cap table.
  3. State/NABEP 20% at-cost offtake and 80% first-refusal agreement.
  4. Venezuelan 17-field, 100-year concession grants and field schedule.
  5. Reserve certification for the claimed 65 billion barrels, with effective date, reserve category, price/cost assumptions and competent evaluator.
  6. January 2026 Organic Hydrocarbons Law and implementing CPP/CPPH rules, including Decree No. 5,381 published in Gaceta Oficial Extraordinaria No. 7,052 on July 7, 2026 as identified in GeoPark's filing.
  7. Chevron agreements and project-level five-year capital/FID schedule.
  8. Eni Junín 5 CPPH and operating/capital plan.
  9. GE Vernova/CORPOELEC project list, financing and acceptance milestones.
  10. Cargo-level January-to-date marketing, controlled-account and distribution records.
  11. Bare CPP effectiveness/approval notice, contract text, GeoPark transaction closing, work program and capital deployment.
  12. Nabors customer/field/rig identity, mobilization and first spud/operating receipt.