Skip to content
Browse the whole research Library · Start page for AI agents ·

GAO 25 106874 AND COST METHOD AUDIT

.json · 1 sections · 8805 characters

Source, owner, and dates

workbench: _Working/federal-budget-2026-2027/goal/terra_human/va/ehr_cost/batch2/GAO_25_106874_AND_COST_METHOD_AUDIT.json

Canonical source SHA-256: 21945c6c672423b74f6b45fe92b7455e7b5b08a67ff68f62b9821984d174d1ba

Served copy SHA-256: 21945c6c672423b74f6b45fe92b7455e7b5b08a67ff68f62b9821984d174d1ba

Owner evidence cutoffs: {"federal-budget-fy2026-fy2027": "2026-09-11T19:55:13-04:00"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: federal-budget-fy2026-fy2027

complete text

Opening section

Section 1 of 1

{ "receipt_id": "va_ehr_cost_batch2_gao25_106874", "status": "bounded_primary_read_complete; IDA_original_unrecovered", "created_date": "2026-09-12", "primary_report": { "title": "Electronic Health Records: VA Making Incremental Improvements in New System but Needs Updated Cost Estimate and Schedule", "identifier": "GAO-25-106874", "official_url": "https://www.gao.gov/assets/gao-25-106874.pdf", "publication_date": "2025-03-12", "recipient": "Congressional Committees; copy list names Senate and House Veterans' Affairs and MilCon-VA Appropriations leadership", "pdf_page_count": 69, "coverage": "physical PDF pages 1-40 (zero-based 0-39), ending in the Agency Comments and Our Evaluation section at printed GAO page 34. A few lines from physical page 41 / printed page 35 were visible at the pagination boundary but are not claimed as sequential coverage.", "next_unread": "physical PDF page 41 / zero-based 40 / printed GAO page 35", "access": "official GAO browser PDF text; direct local curl was access denied and no local copy was treated as read" }, "gao25_methods_and_limits": { "audit_period": "June 2023-March 2025", "scope": "actions after the April 2023 pause at the original five deployment sites; expressly excludes review of the sixth site, Lovell FHCC", "methods": [ "reviewed VA briefing slides, issue assessments, EHR contract performance work statement, service-level agreements, contractor-performance reports, reset-committee materials, and other program documentation", "conducted structured interviews with a judgmental sample supplemented by random selections: 71 users across roles from five sites, October 2023-May 2024; GAO says results cannot be generalized to all EHR users", "reviewed VA survey results and interviewed VA EHRM/VHA officials and five-site leadership", "examined the January 2019 VA estimate and October 2022 independent estimate and discussed cost/schedule status with program officials", "compared improvement and performance-measure work with federal guidance and leading practices; performed under generally accepted government auditing standards" ], "contemporaneous_boundary": "Findings concern the reset/pause through early 2025. They predate the CJ's asserted September 30, 2025 high-level notification and must not be presented as later status." }, "cost_estimate_findings": [ { "locator": "physical PDF 24-26 / printed GAO 19-21", "finding": "GAO found no updated total life-cycle cost estimate or integrated master schedule reflecting the 20-month pause, changes, delays, and updated processes. It says management/oversight then relied on the January 2019 VA $16.1b estimate or October 2022 independent $49.8b estimate.", "boundary": "March 2025 finding, not an assessment of VA's later $37.2b CJ claim." }, { "locator": "physical PDF 24 / printed GAO 19", "finding": "GAO reports the October 2022 IDA independent estimate as $49.8b: $32.7b implementation over 13 years and $17.1b sustainment over 15 years. It characterizes this as more realistic than VA's 10-year 2019 estimate but still not reflecting the later pause and changes.", "boundary": "The two phase durations are not necessarily additive to a single 28-year sequential horizon; the original IDA report is required to establish calendar timing, cost base, overlap, assumptions, and risk treatment." }, { "locator": "physical PDF 39-40 / printed GAO 34; first lines of physical 41 were incidental lookahead only", "finding": "VA concurred in principle with GAO's updated-independent-estimate recommendation but described plans for deployments through May 2028, the then-current Oracle contract endpoint. GAO concluded that plan fell short of a full life-cycle estimate and schedule because future acquisition work was required.", "boundary": "VA's response describes planned action, not achievement of GAO's requested full-life-cycle product." } ], "recommendations": [ {"id":"GAO25_rec1","locator":"physical PDF 38 / printed GAO 33","text":"Direct EHRM Integration Office to obtain an updated and independent total life-cycle cost estimate using GAO Cost Estimating and Assessment Guide best practices.","status_at_report":"VA concurred in principle; GAO regarded planned through-May-2028 work as insufficient."}, {"id":"GAO25_rec2","locator":"physical PDF 38 / printed GAO 33","text":"Expeditiously and reliably update the integrated master schedule using GAO Schedule Assessment Guide best practices.","status_at_report":"VA concurred; GAO says the planned schedule through May 2028 was not full-program coverage."}, {"id":"GAO25_rec3","locator":"physical PDF 38 / printed GAO 33","text":"Identify baselines and performance targets for all nine program/system metrics.","status_at_report":"VA concurred; one change-request-ticket metric lacked baseline/target at the March 2025 observation point."} ], "ida_2022_source_identity": { "identity": "Institute for Defense Analyses final independent cost estimate for the VA EHRM program, October 2022", "exact_title_url_and_report_number": "not supplied by GAO-25-106874 and not recovered in targeted IDA official search", "source_located_status": "identified through GAO's primary report; original not located/read", "known_through_gao": "$49.8b total life-cycle cost; $32.7b for 13-year implementation; $17.1b for 15-year sustainment", "unresolved": ["cost base year and inflation", "calendar start/end and phase overlap", "work-breakdown structure and cost elements", "schedule assumptions", "data sources", "risk/sensitivity/confidence treatment", "independence/review process"], "limit": "Do not call $49.8b a verified original-IDA finding beyond GAO's faithful summary until the report itself is recovered and read." }, "gao_20_195g_methodology": { "title": "Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Program Costs", "identifier": "GAO-20-195G", "official_url": "https://www.gao.gov/assets/gao-20-195g.pdf", "published": "2020-03-12", "read_scope": "targeted relevant methodology pages, not the 476-page guide in full", "exact_sections": [ {"section":"Chapter 3, Characteristics of Credible Cost Estimates and a Reliable Process","printed_pages":"31-37","role":"defines comprehensive, well-documented, accurate, and credible estimates; includes independence, sensitivity, risk/uncertainty, updating, and documentation."}, {"section":"Chapter 4, Step 1 Define the Estimate's Purpose","printed_pages":"38-40","role":"scope and including all costs in a life-cycle estimate."}, {"section":"Chapter 5, Step 2 Develop the Estimating Plan","printed_pages":"41-46","role":"team, study plan, schedule, and capabilities."}, {"section":"Chapters 6-10, Steps 3-7","printed_pages":"48-127","role":"technical baseline, WBS, ground rules/assumptions, data and inflation, and point estimate/independent comparison."}, {"section":"Chapters 11-16, Steps 8-12 and audit/validation","printed_pages":"130-203","role":"sensitivity, risk and uncertainty, documentation, management presentation, updating with actuals, and validation."} ], "key_standard": "At printed pages 31-36, the Guide says a credible estimate has sensitivity and risk/uncertainty analysis, cross-checks/alternate methods, and comparison with an independent cost estimate; a well-documented estimate identifies sources, data reliability, method, technical baseline, and management review; an accurate estimate is updated for program changes and actual costs.", "application_limit": "These are GAO best-practice criteria, not a conclusion that either the October 2022 IDA estimate or VA's later $37.2b high-level projection satisfies them." }, "relation_to_37_2b_cj_figure": { "cj_record": "FY2027 Volume 5 printed 158 / physical 159 states a September 30, 2025 high-level $37.2b projection, $10.5b obligated actual 2018-24, based on historical costs plus projected 170-site resources through end-2031.", "finding": "GAO-25-106874 predates that statement. It documents the pre-notification baseline and why GAO sought an updated independent full-life-cycle estimate. Its $49.8b IDA figure cannot be substituted for $37.2b, and the later high-level figure cannot be assumed equivalent to an independently validated full-life-cycle estimate." }, "remaining_work": ["Recover and read the original IDA October 2022 report.", "If obtained, compare its scope/horizon/base-year/risk treatment with a recovered VA September 2025 transmittal/model.", "Read GAO-25-106874 physical 41-69 only if broader non-cost evidence review is assigned."] }