Actual Construction-Use Evidence Audit — Six Deep Dives

.md · 1 sections · 4859 characters

Source, owner, and dates

workbench: Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/ACTUAL_SPEND_EVIDENCE_AUDIT.md

Canonical source SHA-256: 29889744e047f4e6fd0bca973ac53f773f617769f3ff58d63694aaf96350c9ab

Served copy SHA-256: 29889744e047f4e6fd0bca973ac53f773f617769f3ff58d63694aaf96350c9ab

Owner evidence cutoffs: {"us-inbound-investment-industrial-capex": "2026-07-31", "ai-infrastructure-capital-stack-risk-transfer": "2026-08-10", "industrial-project-finance-digital-rails": "2026-07-31"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: us-inbound-investment-industrial-capex, ai-infrastructure-capital-stack-risk-transfer, industrial-project-finance-digital-rails

Opening section

Section 1 of 1

# Actual Construction-Use Evidence Audit — Six Deep Dives

## Rule

A lender or DOE advance proves borrower receipt, not necessarily contractor payment or capitalized construction. A capitalized-cost/CIP figure is strong deployment evidence, but still does not identify which financing source paid each dollar. Do not derive a residual by subtracting draws from CIP.

Project Actual receipt Actual construction-use evidence What cannot be claimed Evidence grade
CP2 LNG July 2025 equity bridge of $2.809B fully drawn to make indirect equity contributions; Phase-1 construction facilities not fully drawn at 2025 year-end. $9.9B of CP2 Phases 1 and 2 total project cost paid at 2025-12-31. That $9.9B is not Phase-1-only, not a use-of-proceeds match to the $15.1B close, and not operating revenue. Partial combined-project spend
Rio Grande LNG Train 5 $150M first installment of $500M notes issued December 2025; $3.6B Train-5 bank facility had zero drawn at 2026-03-31. Q1 2026 $1.176674B PP&E cash acquisition and $11.659040B facility-under-construction asset are consolidated across Phase 1, Trains 4 and 5. No Train-5-only CIP, paid-to-date cost, restricted cash, EPC payable or equity cash received. Project receipt; no project-specific spend
Thacker Pass Phase 1 $867M DOE ATVM advances through 2026-02-24, retained in restricted borrower accounts. $1.277B cumulative capitalized construction/project cost at 2026-03-31; $1.138B within $2.93B Phase-1 construction-capex estimate. CIP is not a source-by-source reconciliation: do not describe the difference from DOE advances as an unfunded gap. Strong project-specific actual-use evidence
BlueOval SK $7.835540B DOE/FFB advances to BOSK before May 2026 restructuring. KY Facility 1 certificate of occupancy; KY Facility 2 building constructed. No audited BOSK CIP, contractor-payments, restricted-cash or plant-by-plant advance schedule located; advance is not spend. Strong borrower receipt; physical progress, no cost figure
TSMC Arizona $8.0B Arizona notes outstanding at 2025 year-end; no published CHIPS/loan draw or paid-in amount under $20B capital authorization. Fab 1 volume production at end-2024; Fab 2 and Fab 3 construction state public. No Arizona CIP/PP&E-at-cost, construction cash paid, project restricted cash, CHIPS cash received, loan draw, or fab revenue figure. Operational/build evidence, no dollar deployment
Abilene DC1 Gross equity contributions of $926.846823M at 2025-12-31; construction-facility draw unavailable. Two buildings delivered in 2025; $146.738356M interest/loan-acquisition cost capitalized; $35M one-time land/power reservation payment; rent began March and July 2025. Gross equity is not net cost because $303.608587M distributions occurred. ASC 946 fair-value accounting does not supply historical construction-cost/CIP roll-forward or loan utilization. Partial financial/use markers; no total cost

## Ranking for an eventual deployed-capital numerator

  1. Thacker Pass — usable project-specific capitalized cost and advance clocks.
  2. CP2 — real paid-cost evidence, only for the combined Phases 1–2 project family.
  3. Abilene DC1 — partial capitalized-finance and physical-delivery evidence, no historical-cost total.
  4. Rio Grande Train 5 — actual note issuance, but spend is broader-facility and the bank loan was undrawn.
  5. BlueOval SK — large actual advances and physical milestones, no cost/spend disclosure.
  6. TSMC Arizona — actual operating/build status, no public dollar deployment record in reviewed sources.

The ranking is an evidence-quality ranking, not a ranking of project importance, likely cost, or commercial viability.