.md · 1 sections · 6910 characters
workbench: Research Packages/Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_TRANSACTION_TRIGGER_CLAIM_AUDIT_2026-08-19.md
Canonical source SHA-256: 52cc196c31a1a824cb75b39af32e0cf2d21f15571b6b5d5fc9333376fcfd1149
Served copy SHA-256: 52cc196c31a1a824cb75b39af32e0cf2d21f15571b6b5d5fc9333376fcfd1149
Owner evidence cutoffs: {"nssts-technology-company-map": "2026-08-19", "nssts-program-acceptance-economy": "2026-08-19"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: nssts-technology-company-map, nssts-program-acceptance-economy
Section 1 of 1
# NSSTS Transaction Trigger Claim Audit and Manual Return Board
Evidence cutoff: 2026-08-19
Status: current Workbench research
Automatic monitoring: false
| Unsafe compression | Current ruling | Promotion object |
|---|---|---|
| ASU Research Park is the final PPF site | The location is planned; the public record still exposes only a nonbinding LOI | Executed lease, sublease, development or facility-use agreement |
| ASU owns and controls every project asset | ABOR controls university land; the Research Park nonprofit is a legally separate component unit/master lessee; improvement ownership varies | Parcel record and target agreement |
| Sunbelt Holdings is the PPF developer | Sunbelt is the park asset manager; no PPF instrument is public | Exact target agreement and legal signatory |
| Park utilities are PPF suppliers | Park-wide presence proves neither capacity nor a target order | Service/capacity agreement and acceptance |
| JE Dunn, Diamondback or Applied Materials won the PPF | Each has a real same-campus comparator, not a public PPF award | Target solicitation, contract or NTP |
| Genesis has selected a Center team | The active object is a sources-sought notice, not a solicitation or award | Post-close procurement or partnership instrument |
| Oracle/NVIDIA GPU announcements establish IOC | Argonne describes Solstice and Equinox as early-stage | Installed configuration, ATO, user release and signed transition |
| WWT or SambaNova is the Center incumbent | Their systems operate at ALCF; no Center award is public | Center-specific order and acceptance |
| Existing ComEd service proves Genesis capacity | It proves the physical utility boundary, not new reserved load | Impact study, service agreement and energization record |
| A pre-award vendor name can be carried forward | The SDC case shows acquisition can make it legally stale before award | Award-date recipient, UEI and asset-transfer clock |
| Certificate of insurance proves coverage | It is evidence of a policy, not the policy wording or required endorsements | Bound policy, endorsements and loss-payee/additional-insured terms |
| A forensic expert decides the claim | The expert develops facts; carrier, self-insured owner or tribunal decides | Delegated authority and formal disposition |
| A surety can take over a federal project unilaterally | The contracting officer considers and accepts a remedy in a written agreement | Bond, termination and takeover agreement |
| A NETA or lab pass restarts the asset | It is evidence against a scoped criterion; owner, utility, AHJ and regulator retain their decisions | Witnessed integrated test and signed return authorization |
| Shared parent proves bias or misconduct | It creates a structural independence question, not misconduct | Conflict disclosure, raw-data access and independent review |
| Object | Evidence producer | Initial decision authority | Possible final authority |
|---|---|---|---|
| Site control | Property counsel / recorder / board clerk | Land controller and counterparty | Court if disputed |
| Utility capacity | Utility planning engineer | Utility and owner | Regulator where applicable |
| Permit / occupancy | Designer, inspector, commissioning team | Building official / AHJ | Appeals authority or court |
| System acceptance | Vendor and test team | Owner's authorized technical/contracting official | Contract dispute forum |
| Insurance coverage | Adjuster and experts | Carrier or delegated self-insured authority | Court or arbitration |
| Surety completion | Surety and completion consultant | Owner or federal contracting officer | Board/court under dispute |
| Return to service | Lab, field tester and recommissioning authority | Owner/operator plus utility/AHJ/regulator | Sector-specific regulator or court |
### Immediate — before 2026-08-22
AI-Capability-RFI history and any amendments at close.DE-AC02-06CH11357.### High-value Arizona returns
### High-value failure returns
## Downgrade and falsifier rules
No company in this board should be promoted to a target assignment without the named evidence object. Negative public-record findings are boundaries on what can be claimed, not proof that confidential commercial instruments do not exist.