# Source ledger — Federal Reserve Non-Core Initiative Governance **Research ID:** `federal-reserve-noncore-initiative-governance-2026` **Cutoff:** 2026-09-30 EDT This ledger records what each source can prove. It does not promote an announcement, recommendation or accounting aggregate into a later operating state. ## Primary sources ### 1. Federal Reserve OIG Report 2026-FMIC-B-016 - **Source:** [*Evaluation of the Eccles-1951 Renovation Project Management and Construction Costs*, September 29, 2026](https://oig.federalreserve.gov/reports/board-eccles-1951-renovation-construction-costs-sep2026.pdf) - **Controls:** project chronology; budget and package evidence; CMAR/GMP execution; governance and reporting findings; seven recommendations; Chairman Warsh's attached response; the Board-as-nonexpert-owner diagnosis; planned IT modernization as a future relevance point. - **Does not prove:** final cost reasonableness; amount of avoidable loss; signed GMP; completed independent audit; recovered amount; issued agency policy; successful IT-modernization application; durable closure. ### 2. Board of Governors 2025 and 2024 financial statements - **Source:** [OIG Report 2026-FMIC-B-003, March 12, 2026](https://oig.federalreserve.gov/reports/board-financial-statement-audit-mar2026.pdf) - **Controls:** Board entity and U.S. GAAP boundary; year-end 2025 and 2024 aggregate construction-in-process balances; capital expenditures; property accounting policy; financial-statement audit opinion and internal-control reporting. - **Does not prove:** Eccles-1951-only cost; vendor, trade, package or cost-code detail; value for money; contract compliance; paid-but-unreceived services; exact placed-in-service classification. ### 3. Board of Governors 2023 and 2022 financial statements - **Source:** [OIG Report 2024-FMIC-B-002, March 11, 2024](https://oig.federalreserve.gov/reports/board-financial-statement-audit-mar2024.pdf) - **Controls:** earlier aggregate construction-in-process balances used to build the 2022–2025 accounting trend. - **Does not prove:** project-level or vendor-level lineage. ### 4. Board Acquisition Policy - **Source:** [Board of Governors Acquisition Policy](https://www.federalreserve.gov/aboutthefed/procurement/aquisition-policy.htm) - **Controls:** the Board's published procurement posture and current public acquisition-policy surface. - **Does not prove:** the specific Eccles-1951 contract, an operative post-OIG framework or application to IT modernization. ## Current evidence-state ledger | Proposition | State | Controlling source | |---|---|---| | The Board failed to execute the Eccles-1951 CMAR contract effectively | observed finding | OIG Report 2026-FMIC-B-016 | | The Board should treat itself as a nonexpert owner for certain non-core initiatives | observed OIG institutional diagnosis | OIG Report 2026-FMIC-B-016 | | Seven corrective recommendations were issued | observed | OIG Report 2026-FMIC-B-016 | | Warsh concurred and directed GSA, audit, GMP, metrics and remedies | directed | Management response attached to OIG Report 2026-FMIC-B-016 | | GSA holds an operative delegated Project Executive mandate | not yet established separately | Return gate | | An independent auditor has been selected and engaged | not established | Return gate | | Awarded costs have been independently validated | not established | Return gate | | A project-level GMP or enforceable substitute has been signed | not established | Return gate | | The Board has recovered cash or obtained a project credit | not established | Return gate | | The Board has issued the agency-wide framework | not established | Return gate | | The framework governs planned IT modernization | not established | Return gate | | The recommendations are closed and the capability is durable | not established | Return gate | ## Required source types for the next update Prefer, in order: 1. OIG recommendation-follow-up or closure evidence; 2. signed Board/GSA authority, governance or interagency instrument; 3. procurement award or audit engagement record; 4. independent audit report and management response; 5. executed contract modification, GMP or fee cap; 6. Board policy, committee charter, RACI, KPI or dashboard; 7. contract demand, modification, credit, settlement or payment record; 8. audited financial statements and notes; 9. project-ledger, CIP or placed-in-service reconciliation; and 10. IT-modernization budget, charter, procurement or assurance record showing actual reuse of the framework. ## Source-handling rules - Keep Board, GSA, contractor, auditor and OIG statements attributed to the issuing actor. - Preserve original and current budget and schedule measures together. - Keep award, invoice, accrual, cash payment, CIP, placed-in-service transfer and depreciation on separate clocks. - Keep questioned, unsupported, disallowed, credited, reimbursed, settled and recovered amounts separate. - Do not treat an OIG closure entry as durable capability without later-project operating evidence.