SR 400 Express Lanes federal transportation loan (TIFIA), up to $3.89 billion

The U.S. Department of Transportation's Council on Credit and Finance recommended the SR 400 Express Lanes TIFIA loan request on May 21, 2025; the Secretary approved the application on June 3, 2025 (approval letter dated June 12; notification June 13); DOT executed a credit agreement for up to $3.89 billion on August 5, 2025, with SR 400 Peach Partners, LLC as borrower. The notes record no draw on the loan as of 2026-11-15.

Where it sits: Remaking the Institutions › The physical country: lands, environment and transport › Roads, rail & water

How it entered the Observatory

The saved starting points
Earliest thread file
Date
2026-09-28
File
Government Hidden Control Surfaces 2026/PUBLIC_CONTACT_AND_PROGRAM_BOARD_SWEEP_2025_2026.md
Note
All six thread files and the related files that hold SR 400 steps carry an evidence cutoff of 2026-09-28, except the October 30 credit-board file.
Katie requests
  • Date
    2026-09-28 17:04 UTC
    Request
    K08-023
    Package
    Government Hidden Control Surfaces 2026
    Her words
    I just keep having this feeling that we're missing some GREAT information somewhere just because it's hidden under entity layers and committees and we don't know where specifically to go.
    Why
    Kind of like we only discovered the IAC meetings last week
  • Date
    2026-09-28 17:30 UTC
    Request
    K08-024
    Package
    Government Hidden Control Surfaces 2026
    Her words
    I'm wondering if we should work through doing a FULL sweep of these committees/agencies/think tanks from the beginning of 2025 until now.
    Why
    I think we should add these to our entity chart too just so we can see how they're organized, legally.
  • Date
    2026-09-25 02:43 UTC
    Request
    K07-085
    Package
    Institutional Signals and Thesis Test 2025-2026
    Her words
    Ok so how is our research doing at 'proving' this thesis?
    Why
    not stated; the request record matches it to this package by subject only (match marked 'guess')
  • Date
    2026-09-29 01:36 UTC
    Request
    K08-026
    Package
    Institutional Signals and Thesis Test 2025-2026
    Her words
    So I think we should look into what these committees have done recently, not just what went through the full cycle - let's see if we can map what's being built currently
    Why
    not stated; the request record matches it to this package (match marked 'guess'); the active buildout files that hold steps 5 and 6 are in this package
Note
None of her requests names SR 400, TIFIA or the Council on Credit and Finance. The loan came in through the committee and council sweeps.

The dated steps

2025-05-21 Turning pointThe Council on Credit and Finance recommended the SR 400 Express Lanes TIFIA loan request to the Secretary of Transportation for final approval.

The Council on Credit and Finance recommended the SR 400 Express Lanes TIFIA loan request to the Secretary of Transportation for final approval. Its post-vote agenda records the action.

Who acted: Council on Credit and Finance (U.S. Department of Transportation)

Stage: recommended by an advisory body

The post-vote agenda records that CCF recommended the SR 400 Express Lanes TIFIA request to the Secretary for final approval

TRADE_LOGISTICS_INFRASTRUCTURE_FULL_SWEEP_SIGNAL_LEDGER_2025-2026.json

2025-06-03 Turning pointThe Secretary of Transportation approved the SR 400 Express Lanes TIFIA application.

The Secretary of Transportation approved the SR 400 Express Lanes TIFIA application. DOT's approval letter, dated June 12, 2025, records the approval date.

Who acted: Secretary of Transportation (U.S. Department of Transportation). The files do not name the official who signed the approval letter.

Stage: approved or adopted

DOT’s approval letter, dated June 12, 2025, records that the Secretary approved the application June 3.

TRADE_LOGISTICS_INFRASTRUCTURE_FULL_SWEEP_FINDINGS_2026-09-28.md

2025-06-13 Turning pointDOT's FY2025 TIFIA report to Congress lists June 13, 2025 as the notification date for the SR 400 approval.

DOT's FY2025 TIFIA report to Congress lists June 13, 2025 as the notification date for the SR 400 approval. DOT's approval letter is dated June 12, 2025.

Who acted: Secretary of Transportation (office), U.S. Department of Transportation. The files call this 'Secretarial approval' and an 'approval notice'; they do not name the official who signed the notice.

Stage: approved or adopted

The FY2025 TIFIA report records a 2025-06-13 SR 400 approval notice

WAVE_12_EXISTING_ACTION_EVIDENCE_NORMALIZATION_2025_2026.json

2025-08-05 Turning pointDOT executed a TIFIA direct-loan (credit) agreement for up to $3.89 billion with the SR 400 public-private partnership.

DOT executed a TIFIA direct-loan (credit) agreement for up to $3.89 billion with the SR 400 public-private partnership. DOT's announcement is titled as Secretary Duffy announcing a $3.89 billion loan to a public-private partnership in Georgia. The Build America Bureau identifies SR 400 Peach Partners, LLC as the borrower and toll revenues as the primary revenue pledge. The signed public project agreement describes 35-year and 45-year TIFIA alternatives for financial close.

Who acted: U.S. Department of Transportation (the files write 'DOT'); announced under the name of Transportation Secretary Sean P. Duffy

Stage: signed

Where the files differ: The files agree on the date and the amount. They name the instrument in four ways: a 'TIFIA direct loan' agreement (signal ledger), 'executed TIFIA agreement' (Trade, Logistics and Infrastructure findings, summary), a 'credit agreement' (Wave 12 data file) and a 'TIFIA loan' executed (Public Contact and Program Board sweep); the findings file's section 2 (changed 2026-11-15) says DOT 'announced the up-to-$3.89 billion loan'. The Build America Bureau names SR 400 Peach Partners, LLC as borrower (findings file and Wave 12 file, both changed 2026-11-15); the signal ledger lists Georgia Department of Transportation, State Road and Tollway Authority and SR 400 Peach Partners, LLC as the operating parties.

DOT executed a TIFIA direct-loan agreement for up to $3.89 billion with the SR 400 public-private partnership

TRADE_LOGISTICS_INFRASTRUCTURE_FULL_SWEEP_SIGNAL_LEDGER_2025-2026.json

not given (stated in a file with evidence cutoff 2026-09-28)The SR 400 Express Lanes project holds a $3.4 billion private-activity-bond allocation.

The SR 400 Express Lanes project holds a $3.4 billion private-activity-bond allocation. The files do not give the date or the body that made the allocation.

Who acted: Not named in the files

Stage: other

a $3.89 billion TIFIA agreement and a $3.4 billion private-activity-bond allocation

ACTIVE_BUILDOUT_DELIVERY_TRADE_INPUT_FINDINGS_2026-09-28.md

2026-04-01A Georgia Department of Transportation fact sheet gives a construction start in 2026 and service commencement in 2031 for the SR 400 Express Lanes.

A Georgia Department of Transportation fact sheet gives a construction start in 2026 and service commencement in 2031 for the SR 400 Express Lanes.

Who acted: Georgia Department of Transportation

Stage: stated by the body

Where the files differ: The Georgia fact sheet (April 1, 2026) gives a 2026 construction start. DOT's Build America Bureau project page, as read on September 28, 2026, places the project in design (step 7).

Georgia identifies a 2026 construction start and 2031 service commencement

ACTIVE_BUILDOUT_REGISTER_2026-09-28.json

2026-09-28DOT's Build America Bureau project page for the SR 400 Express Lanes places the project in design.

DOT's Build America Bureau project page for the SR 400 Express Lanes places the project in design. The page also gives the agreement date.

Who acted: Build America Bureau (U.S. Department of Transportation)

Stage: stated by the body

Where the files differ: See step 6: the Georgia fact sheet of April 1, 2026 gives a 2026 construction start.

DOT's project page still placed the project in design.

TRADE_LOGISTICS_INFRASTRUCTURE_FULL_SWEEP_FINDINGS_2026-09-28.md

Where it stands

As of 2026-11-15 (latest change to a file on the thread): DOT has executed a TIFIA credit agreement of up to $3.89 billion for the SR 400 Express Lanes (August 5, 2025), after the Council on Credit and Finance's recommendation (May 21, 2025) and the Secretary's approval of the application (June 3, 2025; approval letter dated June 12; notification June 13). The Build America Bureau identifies SR 400 Peach Partners, LLC as the borrower and toll revenues as the primary revenue pledge. The project also holds a $3.4 billion private-activity-bond allocation (no date given). DOT's project page, read September 28, 2026, places the project in design; Georgia's April 1, 2026 fact sheet gives a 2026 construction start and 2031 service commencement. The notes record no draw on the loan, no bond issuance and no construction milestone as of 2026-11-15.

What comes next

What the notes do not record

What it touches