NSCC's Continuous Net Settlement (CNS) application modernization and its go-live date

Through member notices from November 2025 to October 2026, NSCC set and moved the testing and go-live dates for its modernized CNS application; A9841 (October 28, 2026) moved go-live from November 16, 2026 to February to March 2027.

Where it sits: Finance › Tokenization, clearing and custody › DTCC, exchanges & tokenized trading · Storylines: The Digital-Rails Transition

How it entered the Observatory

The saved starting points
Earliest thread file
Date
2026-08-21
File
Monetary Cross-Cuts/DTCC Notice and Testing Clock Map 2026-08-21/DTCC_NOTICE_AND_TESTING_CLOCK_MAP_2026-08-21.md
Requests
  • When
    2026-08-21 17:23 UTC
    Id
    K04-007
    Subject
    DTCC important notices and testing updates
    Her words
    Can we go through the DTCC and check in on their important notices and updates on the testing they've been going through?
  • When
    2026-09-06 03:09 UTC
    Id
    K05-021
    Subject
    DTCC/NSCC important notices, modernization updates, rule filings, rules and procedures, policy and compliance
    Her words
    Anything of interest in here? I think a lot of these might be interesting to add to the observatory.
    Files
    • Fed, Clearing and Treasury/DTCC_MODERNIZATION_LEGAL_AND_POLICY_REVIEW_2026-09-05.md
Request source
Obsidian vault: 00 - Index/Operation Inch by Inch/Katie's Words 2026-11-13/ORIGINS_BY_PACKAGE.json

The dated steps

2025-11-17In Important Notice A9678, NSCC announced distributed connectivity and updated input and output formats for its modernized Continuous Net Settlement (CNS) application, with a fourth-quarter 2026 target.

In Important Notice A9678, NSCC announced distributed connectivity and updated input and output formats for its modernized Continuous Net Settlement (CNS) application, with a fourth-quarter 2026 target.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: announced

NSCC announced distributed connectivity and updated input and output formats.

DTCC Notice and Testing Clock Map — Source Document.md

2026-01-28In A9717, NSCC set November 16 (2026) as go-live, kept existing client connections and fixed-width machine-readable reports at launch, and planned to retire print-image reports on launch day.

In A9717, NSCC set November 16 (2026) as go-live, kept existing client connections and fixed-width machine-readable reports at launch, and planned to retire print-image reports on launch day.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: scheduled

retained existing client connections and fixed-width machine-readable reports at launch

DTCC Notice and Testing Clock Map — Source Document.md

2026-03-31In A9742, NSCC scheduled client testing to start July 13 and called for signoff before October 9.

In A9742, NSCC scheduled client testing to start July 13 and called for signoff before October 9.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: scheduled

NSCC scheduled client testing to start July 13 and called for signoff before October 9.

DTCC Notice and Testing Clock Map — Source Document.md

2026-07-13In A9795, NSCC placed day-cycle CSV and CNS machine-readable output testing in a July 27 to October 9 window and kept print-image reports in production beyond the November 16 go-live.

In A9795, NSCC placed day-cycle CSV and CNS machine-readable output testing in a July 27 to October 9 window and kept print-image reports in production beyond the November 16 go-live.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: amended

extended print images in production beyond its stated November 16 go-live

DTCC Notice and Testing Clock Map — Source Document.md

2026-07-23In A9799, NSCC moved the start of modernized CNS testing from July 27 to August 24 and used November 14 as the go-live date.

In A9799, NSCC moved the start of modernized CNS testing from July 27 to August 24 and used November 14 as the go-live date.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: amended

Where the files differ: A9799 gave November 14. A9795 and the August client roadmap gave November 16. A9841 later identified November 16 as the date being moved.

Moved modernized CNS testing from July 27 to August 24; used November 14 as the go-live date.

DTCC Notice and Testing Clock Map — Source Document.md

2026-08-06In A9805, NSCC set the August 24 to October 9 output test to receipt, record layout and file structure.

In A9805, NSCC set the August 24 to October 9 output test to receipt, record layout and file structure. It excluded economic values, cash and the Buy-In, Miscellaneous Night and Miscellaneous Day reports, and deferred print-image and CSV attestations.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: scheduled

Fixed the controlling August 24–October 9 output-test scope and explicit exclusions.

DTCC Notice and Testing Clock Map — Source Document.md

2026-08DTCC's August 2026 client roadmap showed the application live for client use on November 16 with legacy interfaces kept, interface migration starting in the second quarter of 2027 and a production migration deadline in the third quarter of 2028.

DTCC's August 2026 client roadmap showed the application live for client use on November 16 with legacy interfaces kept, interface migration starting in the second quarter of 2027 and a production migration deadline in the third quarter of 2028.

Who acted: The Depository Trust & Clearing Corporation (DTCC)

Stage: scheduled

places interface migration in Q2 2027 with the production migration deadline in Q3 2028

DTCC Notice and Testing Clock Map — Source Document.md

2026-10-28 Turning pointIn A9841, NSCC moved the November 16 CNS application go-live to February to March 2027 to extend production parallel testing through year-end, said the exact date would be announced in November, and asked members with outstanding output attestations under A9795 to submit them.

In A9841, NSCC moved the November 16 CNS application go-live to February to March 2027 to extend production parallel testing through year-end, said the exact date would be announced in November, and asked members with outstanding output attestations under A9795 to submit them.

Who acted: National Securities Clearing Corporation (NSCC), a DTCC subsidiary

Stage: amended

It moved the November 16 CNS application go-live to **February–March 2027** to extend production parallel testing through year-end.

DTCC Notice and Testing Clock Map — Source Document.md

Where it stands

As of 15 November 2026: NSCC's notice A9841 (October 28, 2026) moved the modernized CNS application go-live from November 16, 2026 to February to March 2027, extended production parallel testing through year-end and said the exact date would be announced in November. DTCC's August roadmap places the separate interface migration from the second quarter of 2027 to a production deadline in the third quarter of 2028. The notes record no new go-live date, no published test results and no SEC rule filing or SEC action on the CNS schedule as of 15 November 2026.