States the policy that both finished military equipment and the critical materials and components to make, maintain and repair it are sourced domestically or from allied nations. No separate result assessment recorded
States the policy that both finished military equipment and the critical materials and components to make, maintain and repair it are sourced domestically or from allied nations.
Addressed to
- The President
Order text
It is the policy of the United States that not only the finished equipment deployed by our military, but also the critical materials and components necessary to manufacture, maintain, sustain, and repair that equipment, are sourced domestically or from allied nations.
From January 1, 2027 the Secretaries must stop issuing 10 U.S.C. 4872(c)(1) waivers for covered materials, except under Sec. 2(b). Not found in the notes
From January 1, 2027 the Secretaries must stop issuing 10 U.S.C. 4872(c)(1) waivers for covered materials, except under Sec. 2(b).
Addressed to
- the Secretary of War (Secretary)
- the Secretaries of the military departments
Deadline
- Words
- On January 1, 2027
- Date
- 2027-01-01
- How
- date stated in the order
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Date
- 2027-01-01
- Kind of date
- date the order sets for its own effect (not a deadline on an officer)
- Deadline passed
- False
Order text
On January 1, 2027, the Secretary of War (Secretary) and the Secretaries of the military departments shall cease to issue waivers under 10 U.S.C. 4872(c)(1) for the acquisition of covered materials under 10 U.S.C. 4872, except as provided in subsection (b) of this section.
10 U.S.C. 4872(e) waivers may issue only under Sec. 2(b) or after a request by the Secretary or military department Secretary to the APNSA. No separate result assessment recorded
10 U.S.C. 4872(e) waivers may issue only under Sec. 2(b) or after a request by the Secretary or military department Secretary to the APNSA.
Addressed to
- the Secretary
- the Secretary of the military department
Order text
Waivers issued under 10 U.S.C. 4872(e) will only be issued as provided in subsection (b) of this section or following a request from the Secretary or the Secretary of the military department to the Assistant to the President for National Security Affairs.
The Secretary may still issue such waivers if the contractor submits, and the Secretary accepts, a mitigation plan identifying the noncompliant source, showing exhaustive efforts or non-availability, describing removal steps and setting a strict timeline. Not found in the notes
The Secretary may still issue such waivers if the contractor submits, and the Secretary accepts, a mitigation plan identifying the noncompliant source, showing exhaustive efforts or non-availability, describing removal steps and setting a strict timeline.
Addressed to
- the Secretary of War (Secretary)
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Deadline passed
- False
Order text
The Secretary may continue to issue waivers under 10 U.S.C. 4872(c)(1) or (e) that would otherwise be prohibited under subsection (a) of this section for the acquisition of covered materials under 10 U.S.C. 4872, provided that the prime contractor or subcontractor submits to the Secretary or his designee a formal mitigation plan, accepted by the Secretary or his designee, that clearly:
States that a contractor's failure to qualify a domestic source is not non-availability for a 4872(c)(1) waiver unless it shows active, funded, ongoing qualification efforts. No separate result assessment recorded
States that a contractor's failure to qualify a domestic source is not non-availability for a 4872(c)(1) waiver unless it shows active, funded, ongoing qualification efforts.
Addressed to
- The President
Order text
A prime contractor's or subcontractor's failure to qualify a domestic source of covered material shall not constitute non-availability for purposes of a waiver under 10 U.S.C. 4872(c)(1),
If a contractor committed fraud, misled the Government or knowingly failed to carry out its plan, the Secretary must take actions and contractual remedies and may refer the matter to the Attorney General. Not found in the notes
If a contractor committed fraud, misled the Government or knowingly failed to carry out its plan, the Secretary must take actions and contractual remedies and may refer the matter to the Attorney General.
Addressed to
- the Secretary of War (Secretary)
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Deadline passed
- False
Order text
the Secretary shall take all actions and exercise all contractual remedies the Secretary deems appropriate, consistent with applicable law.
The Secretary must give the APNSA a list of actions and contractual remedies for knowing or willful contractor noncompliance. Not found in the notes
The Secretary must give the APNSA a list of actions and contractual remedies for knowing or willful contractor noncompliance.
Addressed to
- the Secretary of War (Secretary)
Deadline
- Words
- Within 180 days of the date of this order
- Date
- 2027-01-16
- How
- 180 days counted from signing date 2026-07-20
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Date
- 2027-01-16
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Within 180 days of the date of this order, the Secretary shall provide the Assistant to the President for National Security Affairs a list of generally available actions and contractual remedies that have been taken or may be taken or exercised to address knowing or willful noncompliance by prime contractors and subcontractors.
The Secretary must review the Department's use of the electronic-devices exemption under 10 U.S.C. 4872(c)(3)(B) and ensure it meets current needs. Not found in the notes
The Secretary must review the Department's use of the electronic-devices exemption under 10 U.S.C. 4872(c)(3)(B) and ensure it meets current needs.
Addressed to
- the Secretary of War (Secretary)
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Deadline passed
- False
Order text
The Secretary shall review the Department of War's present application of the exemption for electronic devices under 10 U.S.C. 4872(c)(3)(B) and ensure the continued application of that exemption meets current national security needs.
The Secretary must issue policy and guidance requiring contractors at every tier to map and illuminate critical supply chains for national-security acquisitions from raw materials to end products. Not found in the notes
The Secretary must issue policy and guidance requiring contractors at every tier to map and illuminate critical supply chains for national-security acquisitions from raw materials to end products.
Addressed to
- the Secretary of War (Secretary)
Deadline
- Words
- Within 180 days of the date of this order
- Date
- 2027-01-16
- How
- 180 days counted from signing date 2026-07-20
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Date
- 2027-01-16
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Within 180 days of the date of this order, the Secretary shall develop policy and implementation guidance to require all prime contractors and subcontractors at any tier to map and illuminate, as further described in subsection (b) of this section, critical supply chains
Within 90 days after the guidance, the Secretary must issue regulations requiring indentured Bills of Materials, supplier vetting for financial, foreign-ownership and supply risks, a ban on covered material from unreliable foreign suppliers, and mitigation, notice (15 days), corrective-action (45 days) and closeout duties, without unduly burdening small and new firms. Not found in the notes
Within 90 days after the guidance, the Secretary must issue regulations requiring indentured Bills of Materials, supplier vetting for financial, foreign-ownership and supply risks, a ban on covered material from unreliable foreign suppliers, and mitigation, notice (15 days), corrective-action (45 days) and closeout duties, without unduly burdening small and new firms.
Addressed to
- the Secretary of War (Secretary)
Deadline
- Words
- Within 90 days of completion (of the Sec. 3(a) guidance; no fixed date)
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Deadline passed
- False
Order text
Within 90 days of completion, the Secretary shall promulgate implementing regulations,
The Department must map national-security vulnerabilities in raw-material sourcing and other supply-chain links from contractor information, using tools including AI. Not found in the notes
The Department must map national-security vulnerabilities in raw-material sourcing and other supply-chain links from contractor information, using tools including AI.
Addressed to
- The Department of War
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Deadline passed
- False
Order text
The Department of War shall, in response to the vulnerabilities, bottlenecks, and single points of failure identified by contractor acquisition information, map national security vulnerabilities as they relate to the sourcing of key raw materials or other links in the supply chain,
The Secretary must account for identified vulnerabilities before issuing any 4872(c)(1) or (e) waiver. No separate result assessment recorded
The Secretary must account for identified vulnerabilities before issuing any 4872(c)(1) or (e) waiver.
Addressed to
- the Secretary of War (Secretary)
Order text
The Secretary shall account for identified vulnerabilities, bottlenecks, and single points of failure before issuing any waivers under 10 U.S.C. 4872(c)(1) or (e), consistent with the requirements of section 2 of this order.
The Secretary must start regulatory action to identify national-security acquisitions and require their contractors to qualify and use alternatives to unreliable foreign suppliers as soon as possible. Not found in the notes
The Secretary must start regulatory action to identify national-security acquisitions and require their contractors to qualify and use alternatives to unreliable foreign suppliers as soon as possible.
Addressed to
- the Secretary of War (Secretary)
Deadline
- Words
- Within 180 days of the date of this order
- Date
- 2027-01-16
- How
- 180 days counted from signing date 2026-07-20
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Date
- 2027-01-16
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Within 180 days of the date of this order, the Secretary shall initiate regulatory action to:
States that a contractor's failure to qualify an alternative source is grounds for the Secretary to consider suspending or terminating task orders, declining options and terminating the contract. No separate result assessment recorded
States that a contractor's failure to qualify an alternative source is grounds for the Secretary to consider suspending or terminating task orders, declining options and terminating the contract.
Addressed to
- The President
Order text
A contractor's failure to qualify an alternative source under subsection (a) of this section shall constitute grounds, consistent with law and existing contract terms, for the Secretary to consider suspending or terminating task orders, declining to exercise contract options, and terminating the existing contract.
The Secretary must develop a strategy to accelerate testing and qualification of new sources and materials, and identify and begin rescinding regulations that slow it. Not found in the notes
The Secretary must develop a strategy to accelerate testing and qualification of new sources and materials, and identify and begin rescinding regulations that slow it.
Addressed to
- the Secretary of War (Secretary)
Deadline
- Words
- Within 90 days of the date of this order
- Date
- 2026-10-18
- How
- 90 days counted from signing date 2026-07-20
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Deadline passed
- True
- Pass
- 2
- Date
- 2026-10-18
- Kind of date
- deadline on an officer or body
Order text
Within 90 days of the date of this order, the Secretary shall develop a strategy to accelerate testing and qualification of new sources and materials by prime contractors and subcontractors at any tier.
The Secretary must report to the APNSA every 6 months on waivers, mitigation plans accepted and progress on the Sec. 3 and 4 regulations, with a classified annex if needed. Not found in the notes
The Secretary must report to the APNSA every 6 months on waivers, mitigation plans accepted and progress on the Sec. 3 and 4 regulations, with a classified annex if needed.
Addressed to
- the Secretary of War (Secretary)
Deadline
- Words
- Every 6 months from the date of this order until January 1, 2028
- Date
- 2027-01-20
- How
- first report 6 months from signing date 2026-07-20; then 2027-07-20; ends January 1, 2028
What the notes record
- Searched
- 1. stories (batch 3, batch 4, upgraded) for the order number
- 2. thread register: order number and title words
- 3. research files: grep for EO/Executive Order/E.O. <number>, passages read
- Pass
- 2
- Date
- 2027-01-20
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Every 6 months from the date of this order until January 1, 2028, the Secretary shall submit a report to the Assistant to the President for National Security Affairs describing the actions taken pursuant to this order.
States that Project Vault's sale of critical materials to a contractor is not a credit sale of a defense article or service under 12 U.S.C. 635(b)(6)(A). No separate result assessment recorded
States that Project Vault's sale of critical materials to a contractor is not a credit sale of a defense article or service under 12 U.S.C. 635(b)(6)(A).
Addressed to
- The President
Order text
The sale of critical materials or components by Project Vault to a contractor or subcontractor shall not be construed as a credit sale of a defense article or service for purposes of 12 U.S.C. 635(b)(6)(A).