EO 14302 — Reinvigorating the Nuclear Industrial Base

The order directs the Secretary of Energy to report within 240 days on a national spent-fuel and fuel-cycle policy, plan within 120 days to expand uranium conversion and enrichment, halt the surplus plutonium dilute-and-dispose program in favor of making plutonium available for fuel, update excess-uranium policy within 90 days, seek Defense Production Act section 708 voluntary agreements within 30 days, prioritize Loan Programs Office support toward 5 GW of uprates and 10 large reactors under construction by 2030, and prioritize funding for advanced nuclear; it also directs Labor, Education and other grant agencies to prioritize the nuclear workforce within 120 days.

Signed 2025-05-23 · published 2025-05-29

Sec. 2 Sets the policy of expediting and promoting nuclear energy production and operation, advanced reactors and their supply chains, and fuel recycling and reprocessing. No separate result assessment recorded

Sets the policy of expediting and promoting nuclear energy production and operation, advanced reactors and their supply chains, and fuel recycling and reprocessing.

Addressed to

  • not stated (policy of the United States)
Order text
It is the policy of the United States to expedite and promote to the fullest possible extent the production and operation of nuclear energy
Sec. 3(a) DOE is to report to the President, through the NEDC Chair and the OSTP Director, with a recommended national policy on spent fuel and high-level waste, statutory review, reprocessing and recycling evaluations, disposal, isotope recovery, facility reevaluation and a fuel transport program. Not found in the notes

DOE is to report to the President, through the NEDC Chair and the OSTP Director, with a recommended national policy on spent fuel and high-level waste, statutory review, reprocessing and recycling evaluations, disposal, isotope recovery, facility reevaluation and a fuel transport program.

Addressed to

  • the Secretary of Energy (in coordination with the Secretary of Defense, the Secretary of Transportation and the OMB Director)

Deadline

Words
Within 240 days of the date of this order
Date
2026-01-18

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2026-01-18
Kind of date
deadline on an officer or body
Order text
Within 240 days of the date of this order, the Secretary of Energy, in coordination with the Secretary of Defense, the Secretary of Transportation, and the Director of the Office of Management and Budget (OMB), shall prepare and submit to the President, through the Chair of the National Energy Dominance Council and the Director of the Office of Science and Technology Policy, a report that includes:
Sec. 3(b) DOE is to plan expanded domestic uranium conversion and enrichment (LEU, HEU, HALEU) for civilian and defense needs, to be implemented on the plan's timeframes. Not found in the notes

DOE is to plan expanded domestic uranium conversion and enrichment (LEU, HEU, HALEU) for civilian and defense needs, to be implemented on the plan's timeframes.

Addressed to

  • the Secretary of Energy (in consultation with the Chair of the Nuclear Regulatory Commission and the OMB Director)

Deadline

Words
Within 120 days of the date of this order
Date
2025-09-20

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-09-20
Kind of date
deadline on an officer or body
Order text
Within 120 days of the date of this order, the Secretary of Energy, in consultation with the Chair of the Nuclear Regulatory Commission and the Director of OMB, shall develop a plan to expand domestic uranium conversion capacity and expand enrichment capabilities sufficient to meet projected civilian and defense reactor needs
Sec. 3(c) DOE is to halt the surplus plutonium dilute-and-dispose program (except obligations to South Carolina) and instead establish a program making surplus plutonium available to industry for advanced reactor fuel. Not found in the notes

DOE is to halt the surplus plutonium dilute-and-dispose program (except obligations to South Carolina) and instead establish a program making surplus plutonium available to industry for advanced reactor fuel.

Addressed to

  • the Secretary of Energy

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
The Secretary of Energy shall halt the surplus plutonium dilute and dispose program except with respect to the Department of Energy's legal obligations to the State of South Carolina.
Sec. 3(d) DOE is to update its excess uranium management policy in line with the order and the Nuclear Fuel Security Act, and prioritize contracts for fuel fabrication facilities able to supply test or pilot reactors within 3 years. Not found in the notes

DOE is to update its excess uranium management policy in line with the order and the Nuclear Fuel Security Act, and prioritize contracts for fuel fabrication facilities able to supply test or pilot reactors within 3 years.

Addressed to

  • the Secretary of Energy (in consultation with the Secretary of Defense as appropriate)

Deadline

Words
Within 90 days of the date of this order
Date
2025-08-21

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-08-21
Kind of date
deadline on an officer or body
Order text
Within 90 days of the date of this order, the Secretary of Energy, in consultation with the Secretary of Defense as appropriate, shall update the Department of Energy's excess uranium management policy to align with the policy objectives of this order and the Nuclear Fuel Security Act,
Sec. 3(e) DOE is to use its delegated DPA section 708(c)(1) authority to seek voluntary agreements with domestic nuclear energy companies for cooperative procurement of LEU and HALEU, and should prioritize companies meeting objective milestones. Found

DOE is to use its delegated DPA section 708(c)(1) authority to seek voluntary agreements with domestic nuclear energy companies for cooperative procurement of LEU and HALEU, and should prioritize companies meeting objective milestones.

Addressed to

  • the Secretary of Energy (in coordination with the Attorney General and the Chairman of the Federal Trade Commission)

Deadline

Words
Within 30 days of the date of this order
Date
2025-06-22

What the notes record

What it shows
a DPA section 708 Nuclear Fuel Cycle Consortium voluntary agreement exists; three final plans of action signed July 28, publicly filed August 7, scheduled for publication August 10, 2026; the date the agreement itself was made is not recorded (the file says plans were finalized before an April 23 consortium meeting)
Pass
2
Date
2025-06-22
Kind of date
deadline on an officer or body
Deadline passed
True
DOE filed final, Secretary-approved plans of action under the Nuclear Fuel Cycle Consortium voluntary agreement
WAVE_4_PHYSICAL_PRODUCTION.md
Order text
Within 30 days of the date of this order, the Secretary of Energy, in coordination with the Attorney General and the Chairman of the Federal Trade Commission, shall utilize the authority provided to the President in section 708(c)(1) of the Defense Production Act of 1950 (DPA) (50 U.S.C. 4558(c)(1)), which has been delegated to the Secretary of Energy pursuant to Executive Order 13603 of March 16, 2012 (National Defense Resources Preparedness), to seek voluntary agreements pursuant to section 708 of the DPA with domestic nuclear energy companies.
Sec. 3(f) They are to take the steps under DPA section 708(c), (d), (e) and (f)(1)(A) for DOE to form the voluntary agreements. No separate result assessment recorded

They are to take the steps under DPA section 708(c), (d), (e) and (f)(1)(A) for DOE to form the voluntary agreements.

Addressed to

  • the Secretary of Energy
  • the Attorney General
  • the Chairman of the Federal Trade Commission
Order text
The Secretary of Energy, the Attorney General, and the Chairman of the Federal Trade Commission shall take all necessary and appropriate steps under sections 708(c), (d), (e), and (f)(1)(A) of the DPA (50 U.S.C. 4558(c), (d), (e), (f)(1)(A)), for the Secretary of Energy to form agreements pursuant to subsection (e) of this section.
Sec. 3(g) The Attorney General is to consider the DPA section 708(f)(1)(B) finding for any agreement and publish it within 30 days after an agreement is reached. Not found in the notes

The Attorney General is to consider the DPA section 708(f)(1)(B) finding for any agreement and publish it within 30 days after an agreement is reached.

Addressed to

  • the Attorney General (after consultation with the Chairman of the Federal Trade Commission)

Deadline

Words
no later than 30 days after any voluntary agreement is reached (rolling)

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
The Attorney General shall, after consultation with the Chairman of the Federal Trade Commission, consider whether to make the finding described in section 708(f)(1)(B) of the DPA (50 U.S.C. 4558(f)(1)(B)), with respect to any agreement and, no later than 30 days after any voluntary agreement is reached, shall publish such finding as appropriate.
Sec. 3(h) The voluntary agreements are to allow industry consultation on spent fuel and fuel-supply consortia, and DOE is authorized to give such consortia procurement support, forward contracts or guarantees to ensure offtake. Not found in the notes

The voluntary agreements are to allow industry consultation on spent fuel and fuel-supply consortia, and DOE is authorized to give such consortia procurement support, forward contracts or guarantees to ensure offtake.

Addressed to

  • the Secretary of Energy

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
The Secretary of Energy, consistent with applicable law, is authorized to provide procurement support, forward contracts, or guarantees to such consortia as a means to ensure offtake for newly established domestic fuel supply, including conversion, enrichment, reprocessing, or fabrication capacity.
Sec. 4(a) DOE is to work toward 5 GW of power uprates and 10 new large reactors under construction by 2030, and the Loan Programs Office is to prioritize restarts, uprates, completions, new advanced reactors and the fuel supply chain. Found in part

DOE is to work toward 5 GW of power uprates and 10 new large reactors under construction by 2030, and the Loan Programs Office is to prioritize restarts, uprates, completions, new advanced reactors and the fuel supply chain.

Addressed to

  • the Department of Energy
  • the Secretary of Energy, through the Department of Energy Loan Programs Office

Deadline

Words
by 2030 (target)

What the notes record

What it shows
DOE loan of up to $1.9 billion for the Duane Arnold restart financially closed September 8, 2026 (the file does not name the order or the Loan Programs Office); the 2030 uprate and new-reactor targets are not dated as reached
Pass
2
Evidence kind
formal step toward the result
Deadline passed
False
DOE financially closed a loan of up to $1.9 billion to restart Duane Arnold
WAVE_1C_OPERATIONS_INDUSTRY_DELIVERY.md
Order text
To maximize the speed and scale of new nuclear capacity, the Department of Energy shall prioritize work with the nuclear energy industry to facilitate 5 gigawatt of power uprates to existing nuclear reactors and have 10 new large reactors with complete designs under construction by 2030.
Sec. 4(b) DOE is to assess with DoD restarting or repurposing closed nuclear plants as energy hubs for military microgrids. Not found in the notes

DOE is to assess with DoD restarting or repurposing closed nuclear plants as energy hubs for military microgrids.

Addressed to

  • the Secretary of Energy (coordinating with the Secretary of Defense)

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
The Secretary of Energy shall also coordinate with the Secretary of Defense to assess the feasibility of restarting or repurposing closed nuclear power plants as energy hubs for military microgrid support,
Sec. 4(c) DOE is to prioritize grants, loans, investment capital and other support for qualified advanced nuclear technologies with the most mature designs and financing. Not found in the notes

DOE is to prioritize grants, loans, investment capital and other support for qualified advanced nuclear technologies with the most mature designs and financing.

Addressed to

  • the Secretary of Energy (in coordination with the Administrator of the Small Business Administration)

Deadline

Words
Within 180 days of the date of this order
Date
2025-11-19

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-11-19
Kind of date
deadline on an officer or body
Order text
Within 180 days of the date of this order, the Secretary of Energy, in coordination with the Administrator of the Small Business Administration, shall, subject to the availability of appropriations, prioritize funding for qualified advanced nuclear technologies through grants, loans, investment capital, funding opportunities, and other Federal support.
Sec. 5(a) Declares nuclear engineering and related careers areas of focus and priority under EO 14278. No separate result assessment recorded

Declares nuclear engineering and related careers areas of focus and priority under EO 14278.

Addressed to

  • not stated (passive: nuclear careers 'shall be considered areas of focus and priority' under EO 14278)
Order text
Nuclear engineering and other careers and education pathways that support the nuclear energy industry shall be considered areas of focus and priority pursuant to Executive Order 14278 of April 23, 2025 (Preparing Americans for High-Paying Skilled Trade Jobs of the Future).
Sec. 5(b) Labor and Education are to increase nuclear-related Registered Apprenticeship and CTE participation through intermediary contracts and a gap analysis, guidance encouraging States to use WIOA funds, and grant priorities. Not found in the notes

Labor and Education are to increase nuclear-related Registered Apprenticeship and CTE participation through intermediary contracts and a gap analysis, guidance encouraging States to use WIOA funds, and grant priorities.

Addressed to

  • the Secretary of Labor
  • the Secretary of Education

Deadline

Words
Within 120 days of the date of this order
Date
2025-09-20

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-09-20
Kind of date
deadline on an officer or body
Order text
Within 120 days of the date of this order, the Secretary of Labor and the Secretary of Education shall seek to increase participation in nuclear
Sec. 5(c) Grant-making agencies are to consider nuclear-related careers a priority area for investment. Not found in the notes

Grant-making agencies are to consider nuclear-related careers a priority area for investment.

Addressed to

  • all executive departments and agencies that provide educational grants

Deadline

Words
Within 120 days of the date of this order
Date
2025-09-20

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-09-20
Kind of date
deadline on an officer or body
Order text
Within 120 days of the date of this order, all executive departments and agencies that provide educational grants shall, as appropriate and consistent with applicable law, consider nuclear engineering and other nuclear energy-related careers as a priority area for investment.
Sec. 5(d) DOE is to increase student and DoD nuclear-personnel access to national laboratory infrastructure and expertise. Not found in the notes

DOE is to increase student and DoD nuclear-personnel access to national laboratory infrastructure and expertise.

Addressed to

  • the Secretary of Energy

Deadline

Words
Within 120 days of the date of this order
Date
2025-09-20

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-09-20
Kind of date
deadline on an officer or body
Order text
Within 120 days of the date of this order, the Secretary of Energy shall take steps to increase access to research and development infrastructure, workforce, and expertise at Department of Energy National Laboratories