EO 14301 — Reforming Nuclear Reactor Testing at the Department of Energy

The order finds that DOE-controlled advanced reactors not producing commercial power are for research and fall within DOE's jurisdiction, and directs the Secretary of Energy to issue qualified-test-reactor guidance within 60 days, revise DOE procedures within 90 days so such reactors can operate within 2 years of a complete application, create a pilot program approving at least three reactors outside the national laboratories with a goal of criticality by July 4, 2026, and reform DOE's NEPA rules by June 30, 2025.

Signed 2025-05-23 · published 2025-05-29

Sec. 1 Sets the policy of fostering nuclear innovation and bringing advanced nuclear technologies into domestic production as soon as possible. No separate result assessment recorded

Sets the policy of fostering nuclear innovation and bringing advanced nuclear technologies into domestic production as soon as possible.

Addressed to

  • not stated (policy of my Administration)
Order text
It is the policy of my Administration to foster nuclear innovation and bring advanced nuclear technologies into domestic production as soon as possible.
Sec. 3 Finds that DOE-controlled advanced reactors not producing commercial electric power are for research, not commercial demonstration under 42 U.S.C. 5842, and so fall within DOE's jurisdiction for the foreseeable future. No separate result assessment recorded

Finds that DOE-controlled advanced reactors not producing commercial electric power are for research, not commercial demonstration under 42 U.S.C. 5842, and so fall within DOE's jurisdiction for the foreseeable future.

Addressed to

  • the President ('I find')
Order text
I find that design, construction, operation, and disposition of such reactors under the auspices of the Department--and not to produce commercial electric power--would be for research
Sec. 4(a) DOE is to issue guidance on what counts as a qualified test reactor. Not found in the notes

DOE is to issue guidance on what counts as a qualified test reactor.

Addressed to

  • the Secretary of Energy

Deadline

Words
Within 60 days of the date of this order
Date
2025-07-22

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-07-22
Kind of date
deadline on an officer or body
Order text
Within 60 days of the date of this order, the Secretary shall issue guidance regarding what counts as a qualified test reactor for purposes of this order.
Sec. 4(b) DOE is to revise the regulations, guidance and practices of DOE and the national laboratories to expedite advanced reactors, so qualified test reactors can operate within 2 years of a substantially complete application. Not found in the notes

DOE is to revise the regulations, guidance and practices of DOE and the national laboratories to expedite advanced reactors, so qualified test reactors can operate within 2 years of a substantially complete application.

Addressed to

  • the Secretary of Energy

Deadline

Words
Within 90 days of the date of this order
Date
2025-08-21

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-08-21
Kind of date
deadline on an officer or body
Order text
Within 90 days of the date of this order, the Secretary shall take appropriate action to revise the regulations, guidance, and procedures and practices of the Department, the National Laboratories, and any other entity under the Department's jurisdiction to significantly expedite the review, approval, and deployment of advanced reactors under the Department's jurisdiction.
Sec. 4(c) On finding a substantially complete qualified-test-reactor application, DOE is to set up a team (Secretary's office, national labs, General Counsel and approving entities) reporting directly to the Secretary to assist the applicant. Not found in the notes

On finding a substantially complete qualified-test-reactor application, DOE is to set up a team (Secretary's office, national labs, General Counsel and approving entities) reporting directly to the Secretary to assist the applicant.

Addressed to

  • the Secretary of Energy

Deadline

Words
upon each substantially complete application (rolling)

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
Upon finding that an applicant has submitted a substantially complete application for a qualified test reactor, the Secretary shall establish a team consisting of representatives from the Secretary's office, the relevant National Laboratory or Laboratories, the Department's Office of General Counsel, and any other entities within the Department that possess the authority to deconflict, oppose, or approve the application.
Sec. 4(d) DOE is to prioritize qualified test reactor projects. No separate result assessment recorded

DOE is to prioritize qualified test reactor projects.

Addressed to

  • the Secretary of Energy
Order text
The Secretary shall prioritize qualified test reactor projects for processing, as consistent with applicable law.
Sec. 5(a) DOE is to create a pilot program for reactors outside the national laboratories under 42 U.S.C. 2140 and approve at least three, aiming for criticality in each by July 4, 2026. Found

DOE is to create a pilot program for reactors outside the national laboratories under 42 U.S.C. 2140 and approve at least three, aiming for criticality in each by July 4, 2026.

Addressed to

  • the Secretary of Energy

Deadline

Words
goal: criticality by July 4, 2026
Date
2026-07-04

What the notes record

What it shows
DOE Reactor Pilot Program: Unity reached criticality June 30 and Aalo-X July 4, 2026, the third and fourth reported; a fifth (Oklo Groves) reported August 2026; pilot selections announced August 12, 2025
Pass
2
Date
2026-07-04
Kind of date
deadline on an officer or body
Deadline passed
True
These were the third and fourth reported demonstrations in DOE's pilot.
DOMESTIC_SYSTEMS_WAVE_7_PRIMARY_OBJECT_LEDGER.md
Order text
The Secretary shall approve at least three reactors pursuant to this pilot program with the goal of achieving criticality in each of the three reactors by July 4, 2026.
Sec. 5(b) On approving a pilot application, DOE is to assign a Sec. 4(c)-style team to assist the applicant. Not found in the notes

On approving a pilot application, DOE is to assign a Sec. 4(c)-style team to assist the applicant.

Addressed to

  • the Secretary of Energy

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
Upon approval of an application for this pilot program, the Secretary shall assign a team to provide assistance to the applicant as specified in subsection 4(c) of this order.
Sec. 6(a) DOE is to reform its NEPA rules consistent with EO 14154. Not found in the notes

DOE is to reform its NEPA rules consistent with EO 14154.

Addressed to

  • the Secretary of Energy (in consultation with the Chair of the Council on Environmental Quality)

Deadline

Words
no later than June 30, 2025
Date
2025-06-30

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Deadline passed
True
Pass
2
Date
2025-06-30
Kind of date
deadline on an officer or body
Order text
The Secretary shall, in consultation with the Chair of the Council on Environmental Quality, take action to reform the Department's rules governing compliance with the National Environmental Policy Act (NEPA) no later than June 30, 2025,
Sec. 6(b) DOE is to eliminate or expedite its environmental reviews, including deciding which functions are not subject to NEPA and creating or relying on categorical exclusions. Not found in the notes

DOE is to eliminate or expedite its environmental reviews, including deciding which functions are not subject to NEPA and creating or relying on categorical exclusions.

Addressed to

  • the Secretary of Energy

What the notes record

Searched
  • stories
  • thread-register
  • research-files
Pass
2
Deadline passed
False
Order text
The Secretary shall, consistent with applicable law, use all available authorities to eliminate or expedite the Department's environmental reviews for authorizations, permits, approvals, leases, and any other activity requested by an applicant or potential applicant.
Sec. 7 DOE is to implement the order with its DOGE Team Lead, OMB and OSTP. No separate result assessment recorded

DOE is to implement the order with its DOGE Team Lead, OMB and OSTP.

Addressed to

  • the Secretary of Energy (with the DOGE Team Lead at the Department, the OMB Director and the OSTP Director)
Order text
The Secretary shall work with the DOGE Team Lead at the Department, as defined in Executive Order 14158 of January 20, 2025 (Establishing and Implementing the President's ``Department of Government Efficiency''), with the Director of the Office of Management and Budget, and with the Director of the Office of Science and Technology Policy to implement this order.