National security technology Wave 2 — Claim Audit and Forward Watchboard

NSSTS Wave 2 — Claim Audit and Forward Watchboard

Evidence cutoff: 2026-08-18
Status: active workbench control record
Scope: energy systems, advanced manufacturing and critical-materials company edges

Claim rulings

Unsafe compressionRuling
A named company on an AI-campus announcement supplies the turbines or cooling system.Not supported. The current federal project releases do not name those OEMs.
A 48C allocation means the factory is operating.False. Allocation, construction, production start and accepted delivery are separate.
A FITT or GRIP selection is an accepted grid deployment.False. Preserve selected, awarded, installed, commissioned and accepted.
A Transmission Facilitation Program selection means the HVDC line will be built.False. Contract, permit, financing, NTP and energization remain open.
An advanced-reactor construction permit means the plant may operate.False. Operating license, fuel, commissioning and generation remain separate.
A selected SMR project is a reactor order.False. Selection does not establish final award, permit or procurement.
A fusion Milestone participant is building a commercial power plant.False. Preserve design, component, device, site, license and electricity states.
A federal loan means project funds have all been drawn.False. Closing, disbursement, construction and repayment are distinct.
Announced magnet nameplate equals qualified production.False. Customer qualification and recurring delivery control.
U.S. magnet manufacture proves fully domestic feed.False. Oxide, metal/alloy and other origin seams remain material.
A DLA magnet order proves delivery.False. It confirms acquisition; completion and acceptance remain later objects.
A gallium or germanium award proves new output.False. Equipment installation, commissioning, purity and customer acceptance remain gates.
A demo-scale separation award can be added to commercial supply.False. Demonstration and production must not share a capacity total.
Major construction at Thacker Pass means lithium production.False. Mechanical completion, commissioning and battery-grade qualification are open.
Demonstration HALEU output equals commercial-scale supply.False. Expanded licensed cascades and fuel-chain delivery are still required.
An IDIQ ceiling is contractor revenue.False. Task orders and obligations control.
An America Makes winner is already a qualified supplier.False. Selection begins a process-control and qualification path.
Named GOTHAAM team membership proves the partner’s functional workshare.Not yet. Membership is public; role allocation remains inferred.
HiCAM or ARM membership proves a company-specific award.False. Require a funded task, contract, accepted article or transition object.
SMART USA remains a live path.False. The federal award was terminated and funding withdrawn.

Near-term return gates

WatchCurrent stateReturn object that upgrades the mapDowngrade or disconfirm
America Makes INSITEaward notice scheduled for 2026-08-30named teams for in-situ sensing, NDE and defect correlationdelayed/canceled notice or no company role
America Makes MIAMIanticipated decision date passednamed metal-interchangeability award teamscall canceled or scope removed
Delta Qual 2.0anticipated decision date passedmachine calibration and installation-qualification winnersno award or program closure
GRIP / Switched Sourceselected in DOE status tableexecuted award and accepted Fort Bliss/utility deploymentrescission or failed demo
Siemens Energy Charlottefactory under constructionproduction start, qualification and first orderschedule/certification failure
FITT transformer projectsselected development pathsinstalled public-utility demonstration with performance recordcancellation or failed test
Southern Spirit HVDCcapacity-contract selectionexecuted contract, permits, finance and named supplierswithdrawal, denial or redesign
TerraPower Natriumconstruction permit issuedoperating-license progress, fuel and major nuclear build milestonessuspension, fuel or license failure
X-energy / TRISO-Xfactory build and ARDP pathlicensed qualified fuel output and Seadrift permitHALEU, license or customer failure
Kairos Hermesconstructionoperating authorization, fuel loading and criticalityconstruction halt or license failure
Holtec SMR-300selectedfinal award, NRC authorization and site workrescission or review failure
TVA / BWRX-300application docketedconstruction permit and long-lead ordersTVA withdrawal or adverse review
BWXT SMR componentsselected capacity projectinstalled nuclear-QA line and customer orderqualification or demand failure
DLA magnet ordersorders issueddelivery acceptance and optionslate/rejected delivery
MP Independence / 10Xstartup / planned buildqualified recurring magnet sales; installed 10X equipmentqualification or scale failure
USA Rare Earthcommissioned/planned multi-site platformnamed shipment and verified run rate; Blacksburg constructionramp or finance failure
Energy Fuels HREEunder constructioncommissioned Dy/Tb line and customer-qualified shipmentpurity, schedule or customer failure
ReElement expansionfundedinstalled line with measured output and named buyerscale economics or feed failure
Syrah Vidaliaoperating / qualifyingrecurring accepted commercial volumesqualification or Mozambique disruption
Thacker Passmajor constructionmechanical completion and battery-grade qualificationcost/schedule/market scope failure
Project Cruciblefinal award / preconstructionEPC mobilization and first commissioned product linefinance, permit or schedule failure
American Centrifugedemo output + expansion contractnew cascade installation and NRC authorizationcentrifuge, license or schedule failure
General Mattertask order + site preparationaccepted NRC application and construction noticetechnology or license failure
GOTHAAMGA-ASI selected primeworkshare, process-control plan and validated allowablesfailure to reproduce properties
JAQS-SQwinners selectedapproved supplier processes and transition ordersaudit or transition failure
AFRL active contractsdated 2025 portfolionewer modification, accepted milestone or transition usertermination or stale state
Sedaro IDIQvehicle awardedmaterial task-order flow and named program useno task orders or cancellation
QTIMEleads selectedvalidated rapid NDI in DoD/FAA/NASA productionperformance or transition failure
SMART USAterminatedno promotion trigger; historical onlyany use as live PATH evidence

Leading indicators by sector

Energy and grid

High-value signals are executed capacity contracts, utility acceptance, energization, NRC permits and operating authorizations, fuel loading, long-lead equipment orders and named project suppliers. Load forecasts, queue positions, job postings and generic factory expansion are discovery signals only.

Critical materials

High-value signals are direct orders, milestone disbursements, commissioned processing lines, certificates of analysis, origin records, named customer qualification and recurring deliveries. Nameplate announcements and planned tonnes decay quickly without these objects.

Advanced manufacturing

High-value signals are contract modifications, process-control plans, statistical allowables, NDE acceptance, approved supplier status, flight or production articles, and a named transition user. Institute membership and printer ownership do not substitute for qualification.

Required source surfaces

Recheck cadence

Sources

Full saved reading

View the saved source references. This record has no direct external citation in its source-link list.

Document details and formats
Optional file downloads
For AI readers: complete text and record details
About the dates and filing language
Evidence date
When this document or named claim was checked. A newer collection, export or website date does not update it.
Current, private, Workbench or promotion
These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
Master data and projection
The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
Provenance and source join
Where a record came from, and the exact reference connecting a claim to its source.
Gate, receipt and operating evidence
A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.