Rule: A class deviation is the buying rule now. A Companion Guide is not a rule. A proposed FAR is not a final FAR.

Short answer

EO 14275 (Apr. 15, 2025, 90 FR 16447) orders the FAR cut back to what statute requires or what sound procurement still needs. OMB M-25-26 (May 2, 2025) splits the work into two clocks: Phase I class deviations now, Phase II notice-and-comment later under 41 U.S.C. § 1707.

Acquisition.gov issues model deviation text part by part. Agencies adopt it by class deviation. The FAR Companion and buying guides are non-mandatory. They are not the FAR.

FR Doc. 2026-12559, 91 FR 37550 (June 23, 2026), is one of twelve proposed rules (FAR Case 2026-001). Comments closed July 23, 2026. A final rule was not retrieved at cutoff.

EO 14402 pushes fixed-price as the default. EO 14398 writes a DEI-ban clause into contracts and calls compliance material for the False Claims Act. Neither order repeals Title 41. Neither order is the FAR.

This is the buying rulebook under the payment record. Defend the Spend can show a payment. It cannot show whether the award was made under the old FAR, a class deviation, or a rule that has not yet been issued.

1. Entity / control table

Legal personCharter / organic hookWhat it can do to the buying bookCurrent state at cutoffDo not collapse into
OFPP Administrator41 U.S.C. § 1121; EO 14275 § 3(b)Overall direction of procurement policy; may, with OMB concurrence, deny or rescind inconsistent agency procurement rulesLeading the overhaul with the FAR CouncilOFPP is not GSA
FAR Council41 U.S.C. §§ 1302, 1303Jointly issue and maintain the single Government-wide FAR. Members: OFPP, Defense, NASA, GSAIssuing model deviations (Phase I) and proposed rules (Phase II)A Council model text is not an agency deviation until the agency issues it
GSA41 U.S.C. § 1303(a)(1); 40 U.S.C.One of three FAR issuers; hosts Acquisition.govHost of RFO pages, Companion, Practitioner AlbumsHosting is not rulemaking
Civilian agenciesEO 14275 § 5; M-25-26Issue class deviations adopting model text (generally within 30 days)Model text “is not applicable to an agency until the agency has issued a class deviation” (Acquisition.gov FAQ)An unadopted model is not that agency’s FAR
Contracting officerFAR 1.4 / proposed RFO 1.402Awards and administers. Gains discretion where mandates move to the CompanionBound by the FAR or the agency’s class deviation in force on that solicitationDiscretion is not a repeal of CICA
GAO (bid protest)31 U.S.C. §§ 3551–3556, esp. § 3552Decides protests of “an alleged violation of a procurement statute or regulation”Forum still openGAO is not the Court of Federal Claims
U.S. Court of Federal Claims28 U.S.C. § 1491(b)APA-style procurement reviewForum still openA protest forum is not a rule-writer
Offerors / contractorsCICA; Contract Disputes ActMay protest a statute or regulation. EO 14398 makes the DEI clause material under 31 U.S.C. § 3729(b)(4)Bound by the solicitation’s FAR/deviation text, not by the CompanionA buying-guide practice is not a contract clause

2. Binding FAR vs Companion Guide

The FAR is the single Government-wide procurement regulation. 41 U.S.C. § 1303(a)(1); 48 C.F.R. ch. 1. A protest lies for “an alleged violation of a procurement statute or regulation.” 31 U.S.C. § 3552(a). That is the protest hook.

A class deviation is an authorized departure from the FAR for more than one contract action. Once an agency issues the RFO class deviation, that text is the agency’s FAR for new solicitations. Acquisition.gov FAQ: “The model deviation text for a particular FAR part is not applicable to an agency until the agency has issued a class deviation.”

The FAR Companion, buying guides, and Practitioner Albums are the other half of what M-25-26 calls Strategic Acquisition Guidance. Acquisition.gov FAQ, in terms:

A Companion practice is therefore not a procurement regulation under § 3552. Failure to follow a buying-guide tip is not, without more, a protestable violation. Failure to follow a statute, the still-codified FAR, or the agency’s issued class deviation is.

The test for what stays in the FAR (EO 14275 § 4): required by statute, or necessary to simplicity, efficacy, or economic or national-security protection.

Sunset (EO 14275 § 6): non-statutory FAR that remains is to expire four years after the final rule unless the Council renews it. That clock does not start on a proposed rule.

3. The clocks

Do not collapse these four.

ClockInstrumentWhat it doesStatus at cutoff
1. Policy orderEO 14275, Apr. 15, 2025, 90 FR 16447FAR should contain only statutory or essential text. 180 days to amend. Deviation and interim guidance until final rules publishSigned. Charter of the overhaul, not the FAR itself
2. Implementation memoOMB M-25-26, May 2, 2025Phase I = model deviation text, agencies generally adopt within 30 days. Phase II = formal rulemaking under 41 U.S.C. § 1707 after all parts have model textBinding as OMB direction. Not notice-and-comment
3. Class deviation (now)FAR subpart 1.4; Council model text; agency class deviationsOperative buying rule for an agency after that agency issues its deviationLive. This is the rulebook in use. It is not 48 C.F.R. as last codified
4. Notice-and-comment (later)41 U.S.C. § 1707; FR 2026-12559 and eleven sibling proposed rulesA procurement regulation with significant effect may not take effect until 60 days after FR publication for comment2026-12559 proposed June 23, 2026. Comments closed July 23. Final rule not retrieved. The other eleven proposed rules were not extracted

§ 1707 is why Phase I deviations and Phase II rules are different legal objects. A deviation can run a procurement tomorrow. A proposed rule cannot.

Sister orders (same buying book, different clauses):

4. Bind to the payment record

The payment record and the buying rulebook are adjacent machines. They are not the same machine.

The FAR sits on obligation. It is the rule for how the United States chooses a vendor and writes the contract that creates the obligation. Defend the Spend publishes a bounded set of *payments*. It does not publish which FAR part, which class deviation, or which protest clock governed the award.

A clean payment line can sit on a dirty procurement. Moving “how-to” out of the FAR into the Companion moves it off the protestable regulation and off the public rule text that a later payment record could cite.

If the chronicle ever joins a payment to its award terms, the join key is the solicitation/contract, the deviation number, and the FAR part then in force — not the Companion PDF.

Pointer: Federal Transaction Record — Open Accounting, Audit Limits, and the State-NGO Gap.

5. Claim audit

Claim heardOfficial objectAdjudication
“The FAR has been repealed / replaced”41 U.S.C. § 1303 still requires a single FAR. Phase I is deviation. Phase II is proposed. No final rule retrievedNot established. Deviation ≠ repeal
“The Companion is the new FAR”Acquisition.gov FAQ: buying guides are “non-mandatory” and “will remain outside the FAR”Different object
“You can protest a Companion violation”31 U.S.C. § 3552(a): protest of a procurement statute or regulationNot established as to the Companion itself
“Model text binds an agency the day the Council posts it”FAQ: not applicable “until the agency has issued a class deviation”Not established
“Notice-and-comment already finished the rewrite”2026-12559 is a proposed rule. Final not retrievedNot established. Proposed ≠ final
“Fixed-price is now the only legal contract type”EO 14402 makes it the default “to the maximum extent consistent with law,” with written exceptionsNot established as a statutory ban
“RFO eliminates all non-statutory rules”EO 14275 § 4 keeps non-statutory text that is “necessary to support simplicity and usability, strengthen the efficacy of the procurement system, or protect economic or national security”Not established as a total purge

6. Entity Theory read

The United States buys through a consolidated group. The FAR is the group’s purchasing manual — one book, three issuers, one OFPP editor. The overhaul is a function transfer inside the same legal person. The statutory FAR duty in § 1303 does not move. What moves is content: mandates leave 48 C.F.R. and land in a guide the Council says is not a regulation. That is how a consolidated group changes how a subsidiary must buy without amending the organic act.

Four clocks: statutory existence (Title 41 still there) · personnel (CO discretion grows where the mandate leaves) · function (“how-to” leaves the regulation; protest jurisdiction follows the regulation, not the guide) · obligation (the same appropriated dollar; the rule that shaped it may now be a class deviation). A press release that “the FAR is gone” is not a repeal.

7. Open clocks

8. Sources

Sources

Full saved reading

View cited sources (4)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

title: "Revolutionary FAR Overhaul — Procurement Control Map"

type: research

subtype: legal-map

status: active

created: 2026-08-15

updated: 2026-08-15

evidence_cutoff: 2026-08-15

source: "EO 14275, EO 14402, EO 14398, OMB M-25-26, 41 U.S.C. §§ 1121, 1302–1303, 1707, 31 U.S.C. § 3552, FR 2026-12559, Acquisition.gov RFO instruments."

---