"schema": "f250.nuclear-case-register/v1",
"compiled": "2026-11-19",
"research_id": "nuclear-infrastructure-buildout",
"scope": "Selected source-backed cases across reactor, fuel, financing and research objects; not a census",
"aggregation_rule": "Objects overlap and have incompatible units/stages. Never sum these rows into national capacity or funding.",
"cases": [
{
"id": "duane-arnold",
"object_type": "restart",
"actors": "NextEra Energy / Duane Arnold",
"recorded_state": "DOE reported financial close September 8, 2026; restart subject to NRC licensing in that source",
"capacity_or_measurement": "615 MW proposed return",
"money_or_contract": "Up to $1.9 billion closed loan",
"next_evidence": "NRC authorization, advances, commissioning and metered output",
"owning_return": "Research Packages/Federal Science Operating System/NUCLEAR_FLEET_FINANCE_AND_LICENSING_RETURN_2026-11-19.md",
"source_review_ids": [
"W1-DUANE-CLOSE"
],
"checked": "2026-11-19"
},
{
"id": "vistra-uprates",
"object_type": "existing-fleet-finance",
"actors": "Vistra; Energy Harbor Nuclear Generation and Vistra Operations retain separate owner/operator roles",
"recorded_state": "DOE October 5 conditional commitment; current Chronicle has later potential-recipient evidence",
"capacity_or_measurement": "Nearly 4 GW preservation distinct from 433 MW uprates",
"money_or_contract": "Up to $4.2 billion conditional; additional Comanche Peak option",
"next_evidence": "Definitive loan, plant allocation, draws and output",
"owning_return": "Research Packages/Federal Science Operating System/NUCLEAR_FLEET_FINANCE_AND_LICENSING_RETURN_2026-11-19.md",
"source_review_ids": [
"W1-VISTRA"
],
"checked": "2026-11-19"
},
{
"id": "constellation-uprates",
"object_type": "existing-fleet-finance",
"actors": "Constellation Energy Generation, LLC / DOE / FFB",
"recorded_state": "October conditional credit; loan agreement still required in September-quarter filing",
"capacity_or_measurement": "Nearly 1.1 GW prospective uprates",
"money_or_contract": "Up to $5 billion conditional guarantee/FFB loan",
"next_evidence": "Loan agreement, advances, named plant approvals and incremental generation",
"owning_return": "Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/NUCLEAR_CUSTOMER_CONTRACTS_FINANCE_AND_COSTS_2026-11-19.md",
"source_review_ids": [
"W1-CONSTELLATION",
"W4-CRANE-Q3"
],
"checked": "2026-11-19"
},
{
"id": "crane",
"object_type": "restart-and-offtake",
"actors": "Constellation Energy Generation, LLC / Microsoft / DOE / FFB",
"recorded_state": "PPA, federal guarantee/loan and transferred CIRs; no borrowings as of Q3 filing date",
"capacity_or_measurement": "Restart output under 20-year PPA; no operating-output finding in return",
"money_or_contract": "Up to $1 billion unsecured FFB loan; Treasury-maturity spread per advance",
"next_evidence": "Draw, licensing/commissioning and delivered power",
"owning_return": "Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/NUCLEAR_CUSTOMER_CONTRACTS_FINANCE_AND_COSTS_2026-11-19.md",
"source_review_ids": [
"W4-CRANE-Q3"
],
"checked": "2026-11-19"
},
{
"id": "susquehanna-aws",
"object_type": "existing-generation-offtake",
"actors": "Talen / AWS / PPL / PJM",
"recorded_state": "June 2025 expanded PPA; 2025 10-K expects full front-of-meter transition spring 2027",
"capacity_or_measurement": "Up to 1,920 MW existing-plant supply, full ramp by 2032 target",
"money_or_contract": "Contracted revenue; public full price/loss clauses not established",
"next_evidence": "Actual service conversion, current load/delivery and contract risk terms",
"owning_return": "Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/NUCLEAR_CUSTOMER_CONTRACTS_FINANCE_AND_COSTS_2026-11-19.md",
"source_review_ids": [
"W4-TALEN-PPA",
"W4-TALEN-10K"
],
"checked": "2026-11-19"
},
{
"id": "long-mott",
"object_type": "new-reactor-industrial-heat",
"actors": "Long Mott Energy, LLC / Dow / Union Carbide / X-energy",
"recorded_state": "CPAR-3 issued November 9, 2026; Dow investment decision ahead",
"capacity_or_measurement": "Four Xe-100; 320 MWe design maximum and industrial-steam needs not additive outputs",
"money_or_contract": "ARDP relationship; full project finance not reconstructed",
"next_evidence": "Board decision, design, construction, fuel, operating license",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-LONG-MOTT-FR",
"W2-DOW",
"W2-DOE-LONG-MOTT"
],
"checked": "2026-11-19"
},
{
"id": "clinch-river",
"object_type": "new-reactor-utility",
"actors": "Tennessee Valley Authority / GE Vernova Hitachi",
"recorded_state": "CPAR-2 issued September 28, 2026; announced September 29",
"capacity_or_measurement": "BWRX-300 project; permit is not metered output",
"money_or_contract": "Project investment/financing not recertified",
"next_evidence": "Project commitment, construction, operating approval and generation",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-CLINCH"
],
"checked": "2026-11-19"
},
{
"id": "natrium-kemmerer",
"object_type": "new-reactor-utility",
"actors": "TerraPower / Bechtel / DOE",
"recorded_state": "Construction permit and April 23 owner-reported plant construction",
"capacity_or_measurement": "345 MWe reactor; storage-supported 500 MW boost is not additive continuous capacity",
"money_or_contract": "First-project cost scope includes development/test/fuel capabilities",
"next_evidence": "Operating application expected 2028, fuel, build and commissioning",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-NATRIUM-DOE",
"W2-NATRIUM-BUILD",
"W2-NATRIUM-FAQ"
],
"checked": "2026-11-19"
},
{
"id": "hermes-1",
"object_type": "demonstration-reactor",
"actors": "Kairos Power / DOE / LANL",
"recorded_state": "Nuclear construction and January 20 finalized HALEU-material contract",
"capacity_or_measurement": "Low-power demonstration; not commercial Google fleet capacity",
"money_or_contract": "Performance-based ARDP relationship; fuel contract distinct from delivery",
"next_evidence": "Fuel fabrication/acceptance, operating permission and test result",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-KAIROS-FUEL"
],
"checked": "2026-11-19"
},
{
"id": "hermes-2",
"object_type": "new-reactor-offtake",
"actors": "Kairos Power / TVA / Google",
"recorded_state": "April 17 groundbreaking; company describes binding TVA PPA",
"capacity_or_measurement": "Up to 50 MWe first plant, nested within up-to-500-MWe 2035 fleet target",
"money_or_contract": "Samsung term sheet includes direct/in-kind support subject to approval",
"next_evidence": "Construction/operating milestones and power delivery targeted 2030",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-KAIROS-BUILD",
"W2-KAIROS-GOOGLE",
"W2-KAIROS-SAMSUNG"
],
"checked": "2026-11-19"
},
{
"id": "aco-enrichment",
"object_type": "fuel-capacity-contract",
"actors": "American Centrifuge Operating, LLC / DOE Idaho",
"recorded_state": "June30/July1 signed capacity order; Q3 company reports production/new centrifuge shipments",
"capacity_or_measurement": "Installed annual capacity distinct from 1 MTU base product and optional volumes",
"money_or_contract": "$900m fully funded CLIN1; two $85m optional CLINs",
"next_evidence": "Site rights, accepted milestones, operating capacity and product by contractual dates",
"owning_return": "Research Packages/Federal Science Operating System/NUCLEAR_FUEL_CAPACITY_CONTRACTS_AND_QUALITY_RETURN_2026-11-19.md",
"source_review_ids": [
"W3-ACO-CONTRACT",
"W3-CENTRUS-Q3"
],
"checked": "2026-11-19"
},
{
"id": "general-matter",
"object_type": "fuel-facility",
"actors": "General Matter, Inc. / NRC / DOE",
"recorded_state": "Company filed core Part70 application September28; higher-assay amendment intended next year",
"capacity_or_measurement": "Future LEU/LEU+/HALEU supply goal 2030; no new production finding",
"money_or_contract": "$900m DOE HALEU task-order programme position",
"next_evidence": "Accepted/issued permissions, HALEU amendment, plant and qualified production",
"owning_return": "Research Packages/Federal Science Operating System/NUCLEAR_FUEL_CAPACITY_CONTRACTS_AND_QUALITY_RETURN_2026-11-19.md",
"source_review_ids": [
"W3-GENERAL-MATTER",
"W3-HALEU-DOE"
],
"checked": "2026-11-19"
},
{
"id": "triso-x",
"object_type": "fuel-fabrication-quality",
"actors": "TRISO-X, LLC / NRC",
"recorded_state": "License February13; quality order October21, published November17",
"capacity_or_measurement": "Licensed/build milestone distinct from accepted fabricated fuel",
"money_or_contract": "Construction corrective commitments legally binding",
"next_evidence": "Verified remedy closure and qualified fuel delivery",
"owning_return": "Research Packages/Federal Science Operating System/NUCLEAR_FUEL_CAPACITY_CONTRACTS_AND_QUALITY_RETURN_2026-11-19.md",
"source_review_ids": [
"W3-TRISO-ORDER",
"W2-DOE-LONG-MOTT"
],
"checked": "2026-11-19"
},
{
"id": "janus-benning",
"object_type": "military-resilience",
"actors": "Army / Radiant Industries, Inc. / Fort Benning",
"recorded_state": "October16 site survey; preferred location awaiting cultural/environmental work",
"capacity_or_measurement": "Three proposed systems for selected mission-critical loads",
"money_or_contract": "Milestone-based programme, contractor owned/operated",
"next_evidence": "Final site, agreements, authorization and sustained-load acceptance",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-JANUS",
"W2-BENNING"
],
"checked": "2026-11-19"
},
{
"id": "pele",
"object_type": "military-demonstration",
"actors": "BWXT / DoW Strategic Capabilities Office / INL",
"recorded_state": "September2026 fabrication milestone reported; shipment/fueling/test ahead",
"capacity_or_measurement": "1.5MWe integrated design; future service goal",
"money_or_contract": "Prototype contract; not a base-service PPA",
"next_evidence": "Shipment, fueled integrated demonstration and sustained output",
"owning_return": "Research Packages/Federal Science Operating System/ADVANCED_NUCLEAR_PROJECT_PATHS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-PELE",
"W2-PELE-OLD"
],
"checked": "2026-11-19"
},
{
"id": "vogtle",
"object_type": "operating-cost-comparison",
"actors": "Georgia Power / Southern Nuclear / co-owners / Georgia PSC",
"recorded_state": "Units3/4 in service; 2025 annual final cost/recovery account",
"capacity_or_measurement": "Georgia Power 45.7% share distinct from whole station",
"money_or_contract": "$10.670bn final net investment excludes approx $440m capitalized financing; recoverable cost differs",
"next_evidence": "Actual ongoing recovery/performance evidence; no universal construction-cost extrapolation",
"owning_return": "Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/NUCLEAR_CUSTOMER_CONTRACTS_FINANCE_AND_COSTS_2026-11-19.md",
"source_review_ids": [
"W4-VOGTLE-ANNUAL",
"W4-VOGTLE-PSC"
],
"checked": "2026-11-19"
},
{
"id": "cfpp",
"object_type": "terminated-project-comparison",
"actors": "UAMPS / NuScale / DOE",
"recorded_state": "Mutual termination November8,2023; insufficient subscription cited",
"capacity_or_measurement": "Proposed capacity excluded from supply total",
"money_or_contract": "Commercial subscription insufficient to proceed",
"next_evidence": "Use as historical commercial-risk comparison",
"owning_return": "Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/NUCLEAR_CUSTOMER_CONTRACTS_FINANCE_AND_COSTS_2026-11-19.md",
"source_review_ids": [
"W4-CFPP"
],
"checked": "2026-11-19"
},
{
"id": "arco-prometheus",
"object_type": "research-infrastructure",
"actors": "INL / DOE Nuclear Science User Facilities / NVIDIA / consortium",
"recorded_state": "Arco launch/userfacility designation November18; Prometheus production target March2027",
"capacity_or_measurement": "Computing/research capability; no electric-generation capacity",
"money_or_contract": "Funding/access and consortium commitments distinct from cash/use",
"next_evidence": "Accepted production platform, validated task results and permitted use",
"owning_return": "Research Packages/Federal Science Operating System/Genesis Mission/NUCLEAR_COMPUTE_ARCO_AND_PROMETHEUS_RETURN_2026-11-19.md",
"source_review_ids": [
"W2-ARCO-DOE",
"W2-ARCO-INL",
"W2-PROMETHEUS"
],
"checked": "2026-11-19"
},
{
"id": "fusion-sparc-helion",
"object_type": "fusion-research-comparison",
"actors": "CFS / Helion / DOE",
"recorded_state": "November CFS assembly account; Helion FAQ defines narrower electricity demonstration",
"capacity_or_measurement": "Q/process energy, recovered electrical energy and net grid export differ",
"money_or_contract": "Research selection/private support not operating grid revenue",
"next_evidence": "Architecture-specific measured energy balance, repetition and grid delivery",
"owning_return": "Research Packages/Federal Science Operating System/FUSION_MILESTONES_AND_GENESIS_RETURN_2026-11-19.md",
"source_review_ids": [
"W5-CFS",
"W5-HELION",
"W5-INFUSE"
],
"checked": "2026-11-19"
},
{
"id": "large-ap1000-procurement",
"object_type": "conditional-large-reactor-finance",
"actors": "DOE EDF / Westinghouse / prospective utility or energy-company SPVs",
"recorded_state": "June23 conditional procurement programme; later issuer SPV/equity description; no full named-close census",
"capacity_or_measurement": "Up to ten two-unit-project reactors; not construction or operating output",
"money_or_contract": "US$17.5bn conditional programme, separate Commerce/Korea frameworks; no addition",
"next_evidence": "Named SPV/site, definitive agreement, equity funding, equipment/title, advance and FID",
"owning_return": "Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/LARGE_REACTOR_SUPPLY_CHAIN_FINANCE_RETURN_2026-11-19.md",
"source_review_ids": [
"W6-LARGE-DOE",
"W6-CAMECO",
"W6-KOREA"
],
"checked": "2026-11-19"
},
{
"id": "palisades-restart",
"object_type": "restart-readiness",
"actors": "Holtec and NRC-authorized operator; ITC switchyard",
"recorded_state": "September loading pause/switchyard work; October21 company-reported assembly recovery",
"capacity_or_measurement": "Readiness and grid connection distinct from generation; separate new SMR projects",
"money_or_contract": "No whole-cost or loss-allocation finding added",
"next_evidence": "Validated readiness, operating permissions, commercial restart and output",
"owning_return": "Research Packages/Federal Science Operating System/PALISADES_RESTART_AND_FUEL_RECOVERY_RETURN_2026-11-19.md",
"source_review_ids": [
"W6-PALISADES-SEP",
"W6-PALISADES-OCT"
],
"checked": "2026-11-19"
}
]
}