Construction cost example

Download the original JSON document

{
  "schema": "f250.construction-cost-example/v1",
  "date": "2026-11-19",
  "status": "hypothetical teaching example; not an issuer estimate or PPA",
  "currency": "USD",
  "balance_sheet_units": "millions",
  "source_document": "Research Packages/Nuclear Infrastructure Buildout 2025-2026/NUCLEAR_CONSTRUCTION_COSTS_AND_CARRYING_COSTS_2026-11-19.md",
  "assumptions": {
    "plant_cost_paid": 7100,
    "plant_cost_accrued_unpaid": 200,
    "eligible_interest_paid": 700,
    "initial_fuel_paid": 120,
    "restricted_cash_funded": 80,
    "preopening_expense_paid": 40,
    "debt_proceeds": 6000,
    "equity_proceeds": 2040,
    "unspent_unbooked_contingency": 500,
    "depreciable_years": 40,
    "salvage": 0,
    "net_capacity_MW": 1000,
    "capacity_factor": 0.9,
    "hours_per_year": 8760,
    "nominal_recovery_rate": 0.08,
    "recovery_years": 40,
    "fixed_OM_annual": 100,
    "other_net_lifecycle_annual": 20,
    "variable_and_fuel_USD_per_MWh": 5,
    "delay_eligible_average_expenditure": 5000,
    "delay_rate": 0.06,
    "delay_years": 1,
    "delay_extra_site_cost": 90
  },
  "boundaries": [
    "No AFUDC equity, grants, tax adjustments, retirement-cost entry or test-power credits in balance-sheet illustration.",
    "All plant costs and stated interest assumed to qualify for capitalization. Interest eligibility is an input, not derived from this table.",
    "No income tax, credit, inflation or detailed financing waterfall in simplified level nominal recovery.",
    "Initial fuel, working capital, restricted cash, preopening losses and their replenishment/release require a separate full investment-model reconciliation; price illustration recovers only plant capital and stated recurring costs.",
    "Single depreciable pool is a teaching assumption; actual land and asset group lives differ.",
    "Delay price sensitivity assumes stated additional amounts qualify as economic plant capital; capitalization is separately assessed."
  ],
  "formulas": {
    "CWIP": "plant paid + plant accrued unpaid + eligible interest paid",
    "cash_uses": "plant paid + interest paid + initial fuel paid + restricted cash funded + preopening expense paid",
    "capital_recovery_factor": "r / (1 - (1+r)^(-n))",
    "generation_MWh": "net MW * hours/year * capacity factor",
    "price_USD_per_MWh": "(plant dollars * CRF + fixed OM dollars + other net lifecycle dollars) / MWh + variable/fuel dollars per MWh",
    "delay_added_price": "(eligible average expenditures * delay rate * delay years + extra site cost) * 1e6 * CRF / MWh"
  },
  "outputs": {
    "CWIP": 8000,
    "cash_uses": 8040,
    "other_assets": 200,
    "total_assets": 8200,
    "total_liabilities": 6200,
    "net_equity": 2000,
    "unpaid_construction_cash_remaining": 200,
    "annual_depreciation": 200,
    "capital_recovery_factor": 0.08386016150058534,
    "annual_capital_recovery": 670.8812920046827,
    "annual_MWh": 7884000.0,
    "capital_USD_per_MWh": 85.09402486107086,
    "fixed_OM_USD_per_MWh": 12.683916793505835,
    "other_lifecycle_USD_per_MWh": 2.536783358701167,
    "illustrative_price_USD_per_MWh": 105.31472501327787,
    "delay_extra_capital": 390,
    "delay_extra_price_USD_per_MWh": 4.148333711977204
  }
}

Sources

Document details and formats

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.