This board is a research radar, not a vault watch calendar. It keeps the next observable state changes and the evidence that would weaken the package's current thesis.

1. Physical buildout

LanePrimary surfaceTrigger to recordFalsifier / caution
National operating fleetEIA-860M monthly releasesUnit status changes from planned/construction to operating; revised COD; cancellation or retirementNever call gross “actual additions” all greenfield without checking uprates and corrections.
GE Vernova supply clockQuarterly results, 10-Q/10-K, investor transcriptsReservation-to-order conversions, backlog MW, shipments, factory throughput, service backlogReservations stall, cancellations rise, or deliveries move later.
Siemens Energy supply clockQuarterly results and analyst presentationCommitment MW, bookings, Charlotte/Tampa/Winston-Salem factory milestones, Gas Services backlogCommitment measure changes definition or U.S. share is not disclosed.
MHI supply clockQuarterly/fiscal resultsLarge-frame unit bookings, North American share, Takasago/Savannah capacity and delivery stateGlobal unit count cannot be allocated to U.S. projects.
NRG Texas Energy FundNRG results and PUCT recordsCedar Bayou 5 / Greens Bayou 6 construction milestones and COD; Wharton performance-grant test“On time” changes; operating capacity differs from nameplate or schedule.
Georgia PowerGeorgia PSC dockets and owner construction updatesYates unit CODs; Wansley mechanical completion and CODEquipment delivery is mistaken for operation.
Duke CayugaIURC records and Duke updatesConstruction milestones; 2029/2030 unit CODsCoal-unit disposition and gas-unit construction are collapsed.
Entergy Louisiana / MetaLPSC dockets U-37882 and related construction filingsEach approval, notice to proceed, turbine delivery and individual CODContract funding claim is confused with cash already spent or every facility already approved.
KilbyTCEQ permit docket, Chevron/Microsoft/GE filingsFinal investment decision, final permits, notice to proceed, first turbine delivery, first powerPPA or air-permit draft is promoted to construction or 2.67 GW operation.

2. Digital adoption

Promote a technology state only when a primary record identifies the owner, asset or fleet, use case, operating state and authority boundary.

Technology laneConfirmation triggerFalsifier / unresolved question
APM / remote monitoringNamed project contract or owner deployment; units and functions statedOEM capability page is the only source; owner adoption remains unknown.
EAM / CMMS agentNamed operator says the feature is in production and identifies whether it drafts, recommends, approves or executesProduct release alone; no controlled-work or audit evidence.
Digital twinRepresented asset, purpose, configuration, validation period, error criteria and operational decision named“Digital twin” used as an unbounded label.
Predictive maintenanceProspective validation against as-found condition; false-positive/negative rates; changed work or outage stateOnly retrospective success case or avoided-cost estimate.
Robotic inspectionNamed site/fleet deployment; sensor modality; human review and work-order handoff statedDemonstration or manufacturing QA generalized to field repair.
Closed-loop optimizationExact manipulated variable, control period, safety envelope and fallback statedMarketing says “autonomous” without control-authority detail.
Unattended plant operationRegulator/inspection authority record, hazard analysis, abnormal-condition evidence and sustained operating historyOne bounded test generalized to the fleet.
General agent in OTIndependent or government evaluation under dynamic fault and adversarial conditions; role-based authority and kill pathLab benchmark or natural-language fluency treated as operating competence.

3. Questions worth following

  1. How many of the newly contracted U.S. gas turbines include long-term service, remote monitoring, APM or digital-twin scope at delivery?
  2. Are owners building an owner-controlled data layer, or does operating history remain fragmented across OEM portals and EAM systems?
  3. Does the data-center buildout favor dedicated single-customer plants with different availability, cycling and cyber requirements from grid plants?
  4. Which operators publish prospective performance for anomaly detection, remaining life and inspection deferral rather than vendor-estimated savings?
  5. Do new plants preserve high-resolution commissioning baselines and configuration history in forms usable across the full asset life?
  6. Where does AI enter the warranty and LTSA decision chain, and who retains authority when the owner model and OEM recommendation disagree?
  7. Does agentic workflow automation reduce planning time without increasing duplicate, low-quality or unauditable work orders?
  8. Which automated controls receive regulatory or insurer recognition, and which remain OEM functions inside the certified turbine controller?

4. Promotion gates

This package is ready for selective vault promotion only after human review. The strongest candidate landing is a concise factual spine linking:

Do not promote vendor benefit figures, speculative project capacity, a new watch date or a master narrative without a separate source check and explicit human choice.

Sources

Full saved reading

Read source: EIA-860M

View cited sources (1)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details
About the dates and filing language
Evidence date
When this document or named claim was checked. A newer collection, export or website date does not update it.
Current, private, Workbench or promotion
These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
Master data and projection
The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
Provenance and source join
Where a record came from, and the exact reference connecting a claim to its source.
Gate, receipt and operating evidence
A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

title: "Forward Watchboard — Turbine Buildout and AI Asset Management"

status: current Workbench control

artifact_role: dated trigger and falsifier board

evidence_cutoff: 2026-08-09 ET

---