Forward Watchboard
This board is a research radar, not a vault watch calendar. It keeps the next observable state changes and the evidence that would weaken the package's current thesis.
1. Physical buildout
| Lane | Primary surface | Trigger to record | Falsifier / caution |
|---|---|---|---|
| National operating fleet | EIA-860M monthly releases | Unit status changes from planned/construction to operating; revised COD; cancellation or retirement | Never call gross “actual additions” all greenfield without checking uprates and corrections. |
| GE Vernova supply clock | Quarterly results, 10-Q/10-K, investor transcripts | Reservation-to-order conversions, backlog MW, shipments, factory throughput, service backlog | Reservations stall, cancellations rise, or deliveries move later. |
| Siemens Energy supply clock | Quarterly results and analyst presentation | Commitment MW, bookings, Charlotte/Tampa/Winston-Salem factory milestones, Gas Services backlog | Commitment measure changes definition or U.S. share is not disclosed. |
| MHI supply clock | Quarterly/fiscal results | Large-frame unit bookings, North American share, Takasago/Savannah capacity and delivery state | Global unit count cannot be allocated to U.S. projects. |
| NRG Texas Energy Fund | NRG results and PUCT records | Cedar Bayou 5 / Greens Bayou 6 construction milestones and COD; Wharton performance-grant test | “On time” changes; operating capacity differs from nameplate or schedule. |
| Georgia Power | Georgia PSC dockets and owner construction updates | Yates unit CODs; Wansley mechanical completion and COD | Equipment delivery is mistaken for operation. |
| Duke Cayuga | IURC records and Duke updates | Construction milestones; 2029/2030 unit CODs | Coal-unit disposition and gas-unit construction are collapsed. |
| Entergy Louisiana / Meta | LPSC dockets U-37882 and related construction filings | Each approval, notice to proceed, turbine delivery and individual COD | Contract funding claim is confused with cash already spent or every facility already approved. |
| Kilby | TCEQ permit docket, Chevron/Microsoft/GE filings | Final investment decision, final permits, notice to proceed, first turbine delivery, first power | PPA or air-permit draft is promoted to construction or 2.67 GW operation. |
2. Digital adoption
Promote a technology state only when a primary record identifies the owner, asset or fleet, use case, operating state and authority boundary.
| Technology lane | Confirmation trigger | Falsifier / unresolved question |
|---|---|---|
| APM / remote monitoring | Named project contract or owner deployment; units and functions stated | OEM capability page is the only source; owner adoption remains unknown. |
| EAM / CMMS agent | Named operator says the feature is in production and identifies whether it drafts, recommends, approves or executes | Product release alone; no controlled-work or audit evidence. |
| Digital twin | Represented asset, purpose, configuration, validation period, error criteria and operational decision named | “Digital twin” used as an unbounded label. |
| Predictive maintenance | Prospective validation against as-found condition; false-positive/negative rates; changed work or outage state | Only retrospective success case or avoided-cost estimate. |
| Robotic inspection | Named site/fleet deployment; sensor modality; human review and work-order handoff stated | Demonstration or manufacturing QA generalized to field repair. |
| Closed-loop optimization | Exact manipulated variable, control period, safety envelope and fallback stated | Marketing says “autonomous” without control-authority detail. |
| Unattended plant operation | Regulator/inspection authority record, hazard analysis, abnormal-condition evidence and sustained operating history | One bounded test generalized to the fleet. |
| General agent in OT | Independent or government evaluation under dynamic fault and adversarial conditions; role-based authority and kill path | Lab benchmark or natural-language fluency treated as operating competence. |
3. Questions worth following
- How many of the newly contracted U.S. gas turbines include long-term service, remote monitoring, APM or digital-twin scope at delivery?
- Are owners building an owner-controlled data layer, or does operating history remain fragmented across OEM portals and EAM systems?
- Does the data-center buildout favor dedicated single-customer plants with different availability, cycling and cyber requirements from grid plants?
- Which operators publish prospective performance for anomaly detection, remaining life and inspection deferral rather than vendor-estimated savings?
- Do new plants preserve high-resolution commissioning baselines and configuration history in forms usable across the full asset life?
- Where does AI enter the warranty and LTSA decision chain, and who retains authority when the owner model and OEM recommendation disagree?
- Does agentic workflow automation reduce planning time without increasing duplicate, low-quality or unauditable work orders?
- Which automated controls receive regulatory or insurer recognition, and which remain OEM functions inside the certified turbine controller?
4. Promotion gates
This package is ready for selective vault promotion only after human review. The strongest candidate landing is a concise factual spine linking:
- data-center and industrial load growth;
- turbine reservation, order, manufacturing, construction and COD clocks;
- the remote-monitoring/APM/EAM technology stack;
- the boundary between decision support and safety-critical authority; and
- dated project and quarterly-results triggers.
Do not promote vendor benefit figures, speculative project capacity, a new watch date or a master narrative without a separate source check and explicit human choice.
Sources
Full saved reading
View cited sources (1)
These are the sources cited by this reading. Each source keeps its own date and scope.
Document details and formats
About the dates and filing language
- Evidence date
- When this document or named claim was checked. A newer collection, export or website date does not update it.
- Current, private, Workbench or promotion
- These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
- Master data and projection
- The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
- Provenance and source join
- Where a record came from, and the exact reference connecting a claim to its source.
- Gate, receipt and operating evidence
- A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Forward Watchboard — Turbine Buildout and AI Asset Management"
status: current Workbench control
artifact_role: dated trigger and falsifier board
evidence_cutoff: 2026-08-09 ET
---