Permanent-magnet transition timeline

Cutoff: 2026-07-22
Clock rule: announcement, legal instrument, financing close, construction, commissioning, qualification, commercial shipment and sustained output are separate events.

Factual spine

DateClockEventControlled status / limitSource
2023operatingNoveon reports commercial sales from San Marcosestablishes pre-2025 U.S. production; does not establish 2,000-tpa outputNoveon-hosted report
2024operatingMP Independence begins commercial rare-earth metal productionmetal, not yet finished-magnet commercial supplyMP 10X release
2024operatingEnergy Fuels begins commercial separated NdPr production at White Mesamidstream oxide output, not magnetsEnergy Fuels 10-K
2025-02-03contractNidec and Noveon announce five-year binding offtake with potential for more than 1,000 total tonnes, deliveries beginning 2025contract ceiling is not delivered volumeagreement
2025-03-20legal/policyEO 14241 treats permanent magnets as derivative mineral products and activates DPA/financing/permitting posturepolicy authority; project execution remains separateFederal Register
2025-04-04export-control legalChina imposes licenses on seven medium/heavy rare-earth families and specified related materialsactive licensing; not a blanket banMOFCOM No. 18
2025-04-15investigationWhite House orders Section 232 investigation of processed critical minerals and derivative productsinvestigation opened; no tariff automatically imposedorder
2025-07shipmentNoveon begins GM magnet deliveriesnamed commercial shipmentGM/Noveon
2025-07transactionMP and DoD execute public-private packageequity/warrant, price floor, HREE finance and 10X outlet support have separate conditionsMP/DoD
2025-07contractApple and MP announce $500m recycled-magnet partnership$200m prepayment and 2027 supply target; no 2025 Apple magnet deliveries impliedApple/MP
2025-08shipmentNoveon begins monthly ABB deliveriesnamed commercial supply; end-2026 ramp remains futureABB/Noveon
2025-09-19facility openingNeo opens Narva, Estonia magnet plantopening/sample state; 2026 mass-production output needs verificationNeo Estonia
2025-10-09export-control announcementChina announces broader rare-earth and technology controlslater suspended; keep separate from April rulesSCIO explanation
2025-11-03preliminary financeCommerce announces proposed $50m Vulcan support; OSC announces conditional $620m Vulcan and $80m ReElement loans later in Novemberconditional/preliminary, not cash receivedNIST; OSC
2025-11-10export-control suspensionbroader October controls suspended until 2026-11-10April 2025 controls remainSCIO
2025-12-12shipmenteVAC ships first Sumter commercial magnetsfirst shipment; not proof of Q1 2026 2,000-tpa run rateeVAC
2025-12operatingMP produces first NdFeB magnets on commercial equipmentcommercial-scale equipment milestone; 2026 GM ramp is separateMP results
2026-01-14Section 232 remedyProclamation 11001 finds PCMDP imports threaten national security and directs negotiations, including price-floor concepts180-day negotiating milestone ran to mid-July; no later public remedy was located by cutoffproclamation
2026-01-19private financeNoveon closes $215m Series Cfinancing, not productionNoveon
2026-02-02reserve financeEXIM approves Project Vault loan authorization of up to $10bn, alongside approximately $2bn described private capitalpublic loan + private capital; do not call the entire $12bn a federal reserve appropriationEXIM
2026-02-26site/capacityMP selects Northlake for 10Xplanned; commissioning targeted 2028MP
2026-03-26commissioningUSAR commissions Stillwater Phase 1acommissioning; customer shipment and year-end run rate remain openUSAR
2026-04-19merger agreementUSAR signs agreement to acquire Serra Verdeproposed/signed; expected Q3 close subject to conditionsSEC 8-K
2026-05diplomacyU.S.–China fact sheet says China will address shortages/restrictions in several critical-mineral lanescommitment, not proof that every license or shipment issue clearedWhite House
2026-06-03final finance agreementCommerce finalizes up to $277m incentives and up to $1.3bn loan for USARfinal agreement; milestone disbursement and build remain separateNIST
2026-06-18conditional financeOSC signs $725m conditional Energy Fuels loan commitmentno final disbursement impliedOSC
2026-07-20sourcing/qualification legalWhite House orders defense critical-material supply-chain mapping, qualification acceleration and waiver restrictionactive order; Jan. 1, 2027 and rulemaking clocks aheadWhite House

Forward clocks

TargetObservableWhat it would proveWhat it would not prove
2026 Q3USAR–Serra Verde transaction closelegal consolidationprojected 2027 output or successful integration
2026 Q4USAR 600-tpa Stillwater run-rate claimramp progress if supported by tonnes and shipments10,000-tpa future platform
2026-11-10scheduled end of China October-control suspensionwhether broader controls reactivate, extend or changestatus of April controls, which already operate separately
2027-01-01defense waiver restriction beginschange in contractor sourcing/mitigation practiceinstant availability of qualified domestic parts
2027 Q1USAR Phase 1b 1,200-tpa targetexpanded Stillwater line if verifiedfeedstock security or customer acceptance
2027Apple–MP supply start; Iluka commissioning; Noveon/Kangwon targetindividual contract/project progressaggregate Western independence
2028MP 10X commissioning; Round Top commercial targetphysical transition into new capacitystable yield/nameplate/customer-qualified output
2029–2030multiple 10,000-tpa projectswhether announced Western nameplate becomes realprofitable operation without state support

Sources

Full saved reading

View cited sources (26)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.