Program and Project Registry
Status: current bounded registry; not an exhaustive site census
Cutoff: 2026-09-30 ET
| Program/project | Owner/operator model | Public state | Load/duration boundary | Next decisive receipt |
|---|---|---|---|---|
| FORTRESS America | central Department program; office directed under USW(A&S) | established | every major installation; “independent power” undefined | office, charter, site list, technical standard and budget |
| 10 U.S.C. §2920 implementation | Department/services/agencies | statutory_requirement | each installation's critical-mission energy; 99.9% minimum availability by FY2030 | issued standards, site baselines and compliance evidence |
| Installation Energy Plans | services/installations | planning_system | installation-specific mission/load/risk | current plan tied to financed projects and tests |
| ERCIP | OSD/services; appropriated Defense-wide MILCON | operating_funding_program | project-specific mission assurance | project list, award, completion and test |
| Army SCI energy | private developer on Army land; emergency priority by agreement | six_conditional_selections | solicitation says island within qualifying outage and support installation ≥14 days | executed EUL/PPA, financing close, interconnection and test |
| Army Janus | contractor-owned/operated reactors | five_vendor_site_pairings_selected | site requirements not equal to full-base load by announcement alone | design/authorization, construction, criticality and power delivery |
| NWS Crane MMR | planned commercial owner/operator; Navy host with Army Janus and department partners | deployment_announced_for_2028 | critical operations; announcement does not establish full-installation load | executed agreement, authorization, design, construction, criticality and accepted delivery |
| Eielson microreactor | proposed private vendor under long-term service arrangement | notice_of_intent_negotiation | up to 5 MW to critical infrastructure | final award, NRC licence, construction and operation |
| Project Pele | government prototype/test at INL | prototype_demonstration_path | technology demonstration, not base service | fueled criticality, output and published test result |
| MCAS Yuma microgrid | utility partnership | operational_publicly_described | backup capacity for 100% current/projected base requirements | current exercise and readiness result |
| MCAS Miramar microgrid | mixed sources and third-party/system partners | operational_and_exercised | design description up to 21 days; observed exercise covered mission-critical operations | current endurance/recovery exercise report |
| SUBASE New London microgrid | Navy plant plus first-right access to utility/private fuel-cell park | operational | essential functions; 10.75 MW CHP plus 7.4 MW fuel cells | current black-start/endurance result |
| Fort McCoy Main Gate microgrid | Army/Xcel partnership | operational_scope_limited | gate and nearby mission-essential facilities; stated ≥14 days | observed 14-day or recurring exercise result |
| DLA Distribution Sigonella | DLA/NAVFAC tenant-facility system | activated_scope_limited | DLA facilities; stated up to 14 days on one fuel load | observed endurance and recovery result |
| Next Great American Base | future model-base initiative | announced_design_objective | completely off commercial grid by announcement | site, authority, plan, budget, construction and operation |
Portfolio finding
The current estate already contains full-load, critical-load, campus, gate and tenant-facility microgrids plus emerging nuclear and private-generation models. FORTRESS cannot use a single project count as its readiness denominator. The portfolio needs common load, duration and test fields before unlike projects can be compared.
Sources
Full saved reading
View the saved source references. This record has no direct external citation in its source-link list.
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.