Program and Project Registry

Status: current bounded registry; not an exhaustive site census Cutoff: 2026-09-30 ET

Program/projectOwner/operator modelPublic stateLoad/duration boundaryNext decisive receipt
FORTRESS Americacentral Department program; office directed under USW(A&S)establishedevery major installation; “independent power” undefinedoffice, charter, site list, technical standard and budget
10 U.S.C. §2920 implementationDepartment/services/agenciesstatutory_requirementeach installation's critical-mission energy; 99.9% minimum availability by FY2030issued standards, site baselines and compliance evidence
Installation Energy Plansservices/installationsplanning_systeminstallation-specific mission/load/riskcurrent plan tied to financed projects and tests
ERCIPOSD/services; appropriated Defense-wide MILCONoperating_funding_programproject-specific mission assuranceproject list, award, completion and test
Army SCI energyprivate developer on Army land; emergency priority by agreementsix_conditional_selectionssolicitation says island within qualifying outage and support installation ≥14 daysexecuted EUL/PPA, financing close, interconnection and test
Army Januscontractor-owned/operated reactorsfive_vendor_site_pairings_selectedsite requirements not equal to full-base load by announcement alonedesign/authorization, construction, criticality and power delivery
NWS Crane MMRplanned commercial owner/operator; Navy host with Army Janus and department partnersdeployment_announced_for_2028critical operations; announcement does not establish full-installation loadexecuted agreement, authorization, design, construction, criticality and accepted delivery
Eielson microreactorproposed private vendor under long-term service arrangementnotice_of_intent_negotiationup to 5 MW to critical infrastructurefinal award, NRC licence, construction and operation
Project Pelegovernment prototype/test at INLprototype_demonstration_pathtechnology demonstration, not base servicefueled criticality, output and published test result
MCAS Yuma microgridutility partnershipoperational_publicly_describedbackup capacity for 100% current/projected base requirementscurrent exercise and readiness result
MCAS Miramar microgridmixed sources and third-party/system partnersoperational_and_exerciseddesign description up to 21 days; observed exercise covered mission-critical operationscurrent endurance/recovery exercise report
SUBASE New London microgridNavy plant plus first-right access to utility/private fuel-cell parkoperationalessential functions; 10.75 MW CHP plus 7.4 MW fuel cellscurrent black-start/endurance result
Fort McCoy Main Gate microgridArmy/Xcel partnershipoperational_scope_limitedgate and nearby mission-essential facilities; stated ≥14 daysobserved 14-day or recurring exercise result
DLA Distribution SigonellaDLA/NAVFAC tenant-facility systemactivated_scope_limitedDLA facilities; stated up to 14 days on one fuel loadobserved endurance and recovery result
Next Great American Basefuture model-base initiativeannounced_design_objectivecompletely off commercial grid by announcementsite, authority, plan, budget, construction and operation

Portfolio finding

The current estate already contains full-load, critical-load, campus, gate and tenant-facility microgrids plus emerging nuclear and private-generation models. FORTRESS cannot use a single project count as its readiness denominator. The portfolio needs common load, duration and test fields before unlike projects can be compared.

Sources

Full saved reading

View the saved source references. This record has no direct external citation in its source-link list.