Claim Funding-State Dashboard — 28 Frozen Families
Codes
| Code | Meaning | What it is not |
|---|---|---|
U | Unresolved umbrella or heterogeneous aggregate | Funding evidence |
F | Sovereign/framework arrangement | Paid-in fund, project draw or construction spend |
P | Purchase, offtake or revenue-support commitment | Inbound construction equity/debt |
A | Announced corporate program | Project-level finance or capex spent |
I | Issuer-reported broad spending | Pure construction capex |
C | Identified project, finance not evidenced in claim book | Financial close/draw |
X | Identified close, draw or cash-deployment evidence | A political claim alone |
Count at the claim-family level
| State | Families | Interpretation |
|---|---|---|
U | 3 | No usable funding inference yet. |
F | 8 | Political/framework commitments, not deployed capital. |
P | 2 | Customer/revenue support, not capital. |
A | 13 | Corporate umbrellas that require site/SPV decomposition. |
I | 1 | Broad issuer-reported spending, definition not pure capex. |
C | 1 | Named project with unresolved capital stack. |
X | 0 | No claim-family line itself yet establishes close/draw/deployment. |
Family-level state map
| State | Claim IDs |
|---|---|
U | WH-01, WH-02, WH-10 |
F | WH-03 through WH-08; W2-01, W2-02 |
P | WH-09, W2-03 |
A | WH-11 through WH-14; W2-05 through W2-13 |
I | WH-15 |
C | W2-04 |
X | — |
Why X = 0 is a feature, not a failure
The claim book tracks political and corporate claims, not the separate project ledger. A specific project can have X-quality evidence—Thacker Pass, BlueOval, CP2, Train 5, or Abilene—while its umbrella claim remains A, F or U. Promoting an umbrella because one child has finance evidence would reintroduce double counting.
First proof queue
- W2-04 America First Refining — recover SPV, ownership, actual cost, Reliance legal commitment, permits, financing and first draw. It is the fastest test of a very large project headline.
- WH-03 / WH-05 / WH-06 / WH-08 — obtain Saudi, UAE, Japan and ROK governing instruments, allocation schedules, obligors, currency/funding mechanics, call/draw records and project recipients.
- WH-13 Stargate, W2-06 TSMC, W2-07 Micron — map parent to site/SPV, then collect financing agreements, awards, board capex, CIP/PP&E, construction contracts and draw/disbursement records.
- Corporate umbrellas — split capex, R&D, payroll/compensation, supplier spending, procurement and named construction into independent accounting objects.
- Offtake/purchase claims — link a contract to a facility only if the debt/equity case identifies it as revenue support; never turn it into capital.
Sources
Full saved reading
View the saved source references. This record has no direct external citation in its source-link list.
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Claim Funding-State Dashboard — 28 Frozen Families"
status: current
artifact_role: claim-state classifier and proof-priority queue
evidence_cutoff: 2026-07-31
---