Corporate Umbrella Crosswalk — Parent Programs to Child Assets
Rule
The graph is umbrella → child site/SPV, not umbrella + child = two investments. A relationship may instead be customer/offtake, supplier, public support, actual corporate capex, or a non-additive multiplier. Each edge carries included in parent: yes / no / unknown.
| Parent / claim | Child assets or relationships | What is included | Edge and dedupe ruling | Source |
|---|---|---|---|---|
| Stargate $500B / 4 years | Abilene, Texas; five later sites; Oracle arrangement; ongoing CoreWeave projects | "New U.S. AI infrastructure"; later statements cite nearly 7GW / >$400B over three years and Oracle's >$300B/5-year agreement. | Later $400B and $300B statements are progress/constituent claims inside the original $500B program; never add. Abilene is a child with separate SPV financing. | Launch; site update; Oracle |
| TSMC $165B planned U.S. investment | Phoenix/Fab 21, six-fab/packaging/R&D plan; Apple Fab 21 silicon commitment | $100B additional stated intention plus existing $65B Phoenix plan. | Public CHIPS support is a layer inside, not $11.6B to add. Apple's unnamed multibillion-dollar Fab 21 commitment is a customer/supplier edge, not construction cost. | TSMC 6-K; Commerce award |
| Apple $600B / 4 years | Houston server facility, data-center expansion, Manufacturing Fund, Michigan academy, TSMC Fab 21 purchase commitment | Suppliers, direct employment, R&D, data centers, facilities and productions. | $600B supersedes >$500B. Every named asset/fund is presumed contained unless issuer says otherwise; TSMC relationship remains a non-additive supplier edge. | Apple release |
| Micron >$250B through 2035 | Two Idaho fabs, up to four NY fabs, Virginia expansion, U.S. HBM packaging/R&D | Revised nationwide plan. Earlier 2025 figure was about $200B ($150B manufacturing + $50B R&D). | Treat >$250B as revised outer plan, not $200B + $250B. CHIPS awards tag funding; $3B supply-chain ecosystem relationship unresolved until source says inside/outside. | 2025 plan; 2026 update |
| Google: PJM >$25B / 2 years; Texas $40B through 2027 | PJM data-center/AI sites; Texas Armstrong/Haskell campuses; Brookfield hydro modernization | Separate state/regional umbrellas; Alphabet also reports global actual capex. | PJM $25B, Texas $40B and $91.4B global 2025 capex are non-additive until scope is reconciled. $3B/20-year hydro agreement is contracted power support, not DC construction capex. | PJM; Texas; Alphabet earnings |
| Blackstone/QTS Pennsylvania >$25B + $60B "catalyzed" | QTS northeast-PA land sites; Blackstone/PPL generation JV | Funds managed by Blackstone Infrastructure and Real Estate; no disclosed fund checks or debt facility. | $25B is sponsor/fund program claim. $60B is an external multiplier, not Blackstone spend; never add. Child locations/costs/financing not disclosed. | Blackstone release |
High-value overlap already identified
Apple's unnamed multibillion-dollar commitment to buy advanced silicon from TSMC Fab 21 Arizona is the clearest live example: it is a customer relationship supporting a fab's economics, while the Fab belongs in TSMC's project family. Treating Apple, TSMC and Fab 21 as three investments would triple-count one commercial relationship.
Sources
Full saved reading
View cited sources (12)
These are the sources cited by this reading. Each source keeps its own date and scope.
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Corporate Umbrella Crosswalk — Parent Programs to Child Assets"
status: current
artifact_role: non-addition and relationship map
evidence_cutoff: 2026-07-31
---