Authority, Scope and Definition Map
Status: current
Cutoff: 2026-09-30 ET
1. Authority stack
| Layer | Object | What it controls | What it does not prove |
|---|---|---|---|
| department program | FORTRESS America memorandum/release | five pillars, central program, office direction, department support | funding, binding technical standard or site delivery |
| statutory performance | 10 U.S.C. §2920 | each installation's critical-mission energy availability, planning and required information | full-site load or current compliance |
| statutory definitions | 10 U.S.C. §101 | energy resilience, energy security and military installation resilience | FORTRESS-specific implementation |
| master planning | 10 U.S.C. §2864 and UFC 2-100-01 | major-installation plans and resilience/energy components | power project award or readiness |
| construction | 10 U.S.C. §§2815–2816; §2914 ERCIP | resilience construction and life-cycle treatment | operation or successful testing |
| energy agreements | PPA, EUL, ESPC, UESC, §2922a | finance, site rights, energy service and risk allocation | military ownership or automatic wartime access absent terms |
| engineering | UFC 3-550-04 and facility-control cybersecurity criteria | resilient microgrid and control-system design | site acceptance or endurance |
| operating proof | black-start/islanding/endurance exercise | observed start, transfer and load-carrying behavior within test conditions | performance outside the test envelope |
2. Scope terms
| Term | Current public meaning | FORTRESS boundary |
|---|---|---|
| military installation | statutory base, camp, post, station, yard, center or other covered activity | broader than the announced “major installation” phrase |
| major military installation | §2864 points to the current BSR “large site” definition | likely reference class, but not expressly adopted in the accessible release |
| large site | current BSR surface: at least 100,000 acres or at least 4.5 million building square feet | a site category; multiple sites may belong to an installation |
| installation estate | more than 500 installations and more than 5,000 sites on current official surfaces | neither number is a FORTRESS covered-site count |
| critical mission | §2920 mission-essential defense functions; excludes housing, MWR, exchanges, commissaries and private facilities | important load denominator unless FORTRESS publishes a broader one |
3. Capability terms
| Term | Proper test |
|---|---|
| on-site generation | asset located on or directly serving the installation |
| distributed energy | generation/storage located near loads; does not itself imply islanding |
| microgrid | bounded controllable loads/resources able to operate grid-connected or islanded |
| islanding | safe electrical separation from external grid while serving defined loads |
| black start | start without off-installation energy, then transfer and carry defined load |
| critical-load resilience | defined mission loads remain available for defined duration |
| full-load resilience | complete installation load served within stated conditions |
| energy net-zero | annual production/accounting equals or exceeds annual use; not outage endurance |
| independent power | undefined in the FORTRESS release; must name load, duration, fuel and operating mode |
| off-grid | normal-operation disconnection from commercial grid; expressly attached to the Next Great American Base, not the current estate |
4. Scope ruling
Do not calculate a FORTRESS installation count from the public estate totals or the BSR threshold. First obtain the program's authoritative covered-site list. Do not treat a large site's acreage or building area as an energy-load proxy. Do not assume that installation headquarters, geographically separate sites and tenant facilities share one electrical boundary.
Sources
Full saved reading
View the saved source references. This record has no direct external citation in its source-link list.
Document details and formats
About the dates and filing language
- Evidence date
- When this document or named claim was checked. A newer collection, export or website date does not update it.
- Current, private, Workbench or promotion
- These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
- Master data and projection
- The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
- Provenance and source join
- Where a record came from, and the exact reference connecting a claim to its source.
- Gate, receipt and operating evidence
- A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.