Authority, Scope and Definition Map

Status: current Cutoff: 2026-09-30 ET

1. Authority stack

LayerObjectWhat it controlsWhat it does not prove
department programFORTRESS America memorandum/releasefive pillars, central program, office direction, department supportfunding, binding technical standard or site delivery
statutory performance10 U.S.C. §2920each installation's critical-mission energy availability, planning and required informationfull-site load or current compliance
statutory definitions10 U.S.C. §101energy resilience, energy security and military installation resilienceFORTRESS-specific implementation
master planning10 U.S.C. §2864 and UFC 2-100-01major-installation plans and resilience/energy componentspower project award or readiness
construction10 U.S.C. §§2815–2816; §2914 ERCIPresilience construction and life-cycle treatmentoperation or successful testing
energy agreementsPPA, EUL, ESPC, UESC, §2922afinance, site rights, energy service and risk allocationmilitary ownership or automatic wartime access absent terms
engineeringUFC 3-550-04 and facility-control cybersecurity criteriaresilient microgrid and control-system designsite acceptance or endurance
operating proofblack-start/islanding/endurance exerciseobserved start, transfer and load-carrying behavior within test conditionsperformance outside the test envelope

2. Scope terms

TermCurrent public meaningFORTRESS boundary
military installationstatutory base, camp, post, station, yard, center or other covered activitybroader than the announced “major installation” phrase
major military installation§2864 points to the current BSR “large site” definitionlikely reference class, but not expressly adopted in the accessible release
large sitecurrent BSR surface: at least 100,000 acres or at least 4.5 million building square feeta site category; multiple sites may belong to an installation
installation estatemore than 500 installations and more than 5,000 sites on current official surfacesneither number is a FORTRESS covered-site count
critical mission§2920 mission-essential defense functions; excludes housing, MWR, exchanges, commissaries and private facilitiesimportant load denominator unless FORTRESS publishes a broader one

3. Capability terms

TermProper test
on-site generationasset located on or directly serving the installation
distributed energygeneration/storage located near loads; does not itself imply islanding
microgridbounded controllable loads/resources able to operate grid-connected or islanded
islandingsafe electrical separation from external grid while serving defined loads
black startstart without off-installation energy, then transfer and carry defined load
critical-load resiliencedefined mission loads remain available for defined duration
full-load resiliencecomplete installation load served within stated conditions
energy net-zeroannual production/accounting equals or exceeds annual use; not outage endurance
independent powerundefined in the FORTRESS release; must name load, duration, fuel and operating mode
off-gridnormal-operation disconnection from commercial grid; expressly attached to the Next Great American Base, not the current estate

4. Scope ruling

Do not calculate a FORTRESS installation count from the public estate totals or the BSR threshold. First obtain the program's authoritative covered-site list. Do not treat a large site's acreage or building area as an energy-load proxy. Do not assume that installation headquarters, geographically separate sites and tenant facilities share one electrical boundary.

Sources

Full saved reading

View the saved source references. This record has no direct external citation in its source-link list.

Document details and formats
Optional file downloads
For AI readers: complete text and record details
About the dates and filing language
Evidence date
When this document or named claim was checked. A newer collection, export or website date does not update it.
Current, private, Workbench or promotion
These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
Master data and projection
The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
Provenance and source join
Where a record came from, and the exact reference connecting a claim to its source.
Gate, receipt and operating evidence
A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.