View the saved source references. This record has no direct external citation in its source-link list.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Nuclear research coverage and next evidence
Compiled November 19, 2026. This is the first bounded research cycle, following the existing-library orientation and the planned six substantive waves. It is a connected study with selected case follow-through, not an exhaustive U.S./world project census or complete reconstruction of every package.
Actual reading
The orientation record identifies earlier owner passages and route-only threads. The source review identifies each current primary object, native date, read scope and access result. Each dated wave return describes the passage-level findings and limitations. Short releases were generally read in full; long rules, filings, technical guidance and programme reports received the bounded sections disclosed in those returns.
| Planned wave | Substantive result | Coverage boundary |
|---|---|---|
| Existing fleet and authority | Finance/loan states, UPRISE/EIA baselines and NRC final/direct-final changes | No November unit-level national census or all-rule finality review; EIA baseline is March 2026 |
| New reactors | Seven named project paths including industrial steam, grid customers and military implementation | No every-project docket, full technical safety review or private agreement audit |
| Fuel and manufacturing | Enrichment/centrifuge movement, phased General Matter application, ACO contract and TRISO-X order | No complete heavy-component factory census, qualified-tonnage balance or final remedial closure |
| Customers and costs | Crane federal-credit/draw state, Talen/Meta/Kairos routes, Vogtle recovery and CFPP cancellation | No undisclosed PPA price, uniform cost ranking or realized national household savings estimate |
| Operations and longer horizon | Selected cooling/outage/storage duties, exploratory campuses and bounded fusion updates | No site-by-site water/security/decommissioning audit or replicated fusion/AI result |
| Connected account | Linked narrative, selected case register, existing-owner returns and filing | Library integration and delivery checks are recorded in the campaign closeout, separately from source truth |
Important unresolved evidence
- New reactor investment decisions, financing/advances, full nuclear construction milestones, operating approvals, fuel and measured output remain project-specific.
- PPA prices, cancellation/shortfall provisions, complete loss allocation and actual billed costs are often undisclosed. Do not substitute a generic modeled value.
- The INL/DOE UPRISE source pages display different goal years. Categories and rounding also prevent treating the visible dashboard as an exact new-capacity ledger.
- The ACO task order's property/access prerequisites and later performance-based payments need actual instruments/receipts. The scanned contract's extracted fields were read; the reader exposed image placeholders rather than a usable visual rendering.
- Direct NRC pages/accessions frequently returned 403. Readable official bulletins, Federal Register notices and selected other original records support the bounded claims. The unread ACRS letters and underlying technical findings remain separate gaps.
- The published TRISO-X order's notice/initial attachment were read, but remaining remedy-body access was limited. No final corrective-action closure or shutdown was inferred.
- Direct reads of PJM's surfaced November 16 ER27-522 filing timed out. The current proposal clauses and any subsequent order remain for return, without treating an index/title as adopted terms.
- NRC's fusion status page was inaccessible. Saved proposal/statutory clocks were not converted into a claim that no later rule exists.
- March 2027 Prometheus deployment, claimed productivity/staffing improvements and company fusion/grid targets remain future or performance questions. They are not accepted operation today.
New owner and scope
The durable question is how nuclear supply, government authority, industrial capability, customers and cost meet at actual delivery. That connected answer is different from the earlier turbine technology study, broad federal-science package or fusion-only study. The new owner therefore adds one connected entrance while keeping dated findings in their original owners. Relationship and story placement do not transfer evidence clocks or create a second vote for the same claim.
Construction accounting extension on November 19
The construction guide adds bounded issuer policy reads, FERC capitalization guidance and informal staff Q&A, selected 2025 codified utility instructions, AP1000 scope/schedule illustrations and laboratory economic definitions/equations. It supplies a work breakdown and reconciled hypothetical cost example, not company project ledgers or a new event chronology. Live FASB Codification was not retrieved; detailed eCFR paragraph rereads were blocked after the current heading opened. The cited detailed utility instructions are explicitly the 2025 published edition.