Tribal data centers — separate entity timelines
Updated: 2026-07-11
Status: first factual spine; entities remain separate
Scope: dated actions by Tribal Nations, tribal enterprises, private developers, and Indigenous opposition movements connected to U.S. data-center and AI-compute development.
Reading rule
These timelines are intentionally not merged. A federal approval on one date, a developer announcement on another, and a tribal political action on a third remain actions of different entities until a source connects them.
B. Cachil Dehe Band / Colusa Indian Community → Colusa Indian Energy
Circa 2003 — Colusa tribal microgrid begins long-running island-mode operations
Status: Occurred; approximate year
Entities: Cachil Dehe Band of Wintun Indians; Colusa Indian Community; tribal utility and later Colusa Indian Energy
Clock: Power / operating capacity
Project stage: Energy infrastructure operating
In February and March 2026 presentations, Colusa Indian Energy described the Community's microgrid as operating for approximately 22–23 years and supplying all reservation loads. The exact commissioning date and original entity instruments remain to be obtained; the circa-2003 date is an estimate, not a locked event date.
Sources: DOE — Webinar transcript; Colusa Indian Energy — Partnership announcement
2026-02-12 — Colusa Indian Energy presents powered-land model through DOE
Status: Occurred
Entities: Colusa Indian Energy; DOE Office of Indian Energy; Tribal Nations
Clock: Public position / market development
Project stage: Model promoted; later named partnership not yet announced
COO Ken Ahmann described data-center demand as a “gold rush” for powered land. He argued that direct onsite power sales can yield substantially more value than passive land leases, stated that large developers seek long leases, and identified HEARTH certification as important for the long terms hyperscale capital may require.
Time/place: 3:00–4:00 p.m. EST; online.
Source: DOE — Webinar transcript
2026-03-25 — Colusa Indian Energy and Strata Expanse announce AI-and-energy partnership
Status: Announced
Entities: Colusa Indian Energy; Strata Expanse; Cachil Dehe Band of Wintun Indians; DDN; Supermicro; NVIDIA; Intel; AMD
Clock: Developer / tribal enterprise / power
Project stage: Announced partnership
The parties announced planned energy and digital infrastructure on land of the Cachil Dehe Band. The initial component is an Amphix Center of Excellence for proof-of-concept AI workloads connected to the existing microgrid. The announcement states an intention to expand onsite generation above 100 MW over 18 months. It does not disclose a parcel, lease, financing close, construction start, tenant, or operating date for the larger campus.
Place: Announcement issued from Colusa, California, and The Woodlands, Texas; presented in connection with RES 2026 in Las Vegas.
Source: Colusa Indian Energy — Partnership announcement
2026-06-22 — Interior approves Cachil Dehe HEARTH regulations
Status: Occurred
Entities: Cachil Dehe Band of Wintun Indians; Department of the Interior; BIA
Clock: Land / legal capacity
Project stage: Announced partnership; specific lease unverified
Interior approved agriculture, business, and residential leasing regulations under the HEARTH Act. The approval can support covered tribal surface leasing without later deal-by-deal Interior approval. The BIA registry does not identify the AI campus as the reason for the regulations.
Source: BIA — Approved HEARTH Act Regulations
Approximately 2027-09 — company target for generation above 100 MW
Status: Company target; not a guaranteed deadline
Entities: Colusa Indian Energy; Strata Expanse
Clock: Power / construction
Project stage: Future target
The March 25 announcement states an 18-month plan to expand onsite generation above 100 MW. A dated construction schedule, permits, equipment contracts, financing, and interconnection record have not yet been located.
Source: Colusa Indian Energy — Partnership announcement
Current state
Confirmed announced partnership attached to an existing tribal power asset. The Center of Excellence proof-of-concept and the proposed 100-MW expansion must be tracked as separate project phases.
---
C. Caddo Nation of Oklahoma
2017 — Caddo casino reportedly closes
Status: Research lead; primary record requested
Entities: Caddo Nation of Oklahoma; tribal gaming enterprise
Clock: Revenue background
Current reporting describes the Nation's casino as having closed in 2017 and frames later data-center interest against that economic background. This first pass has not located the Nation's closure record, audited revenue history, or a tribal statement connecting the closure to a data-center plan.
2026-06-22 — Interior approves Caddo Nation HEARTH regulations
Status: Occurred
Entities: Caddo Nation of Oklahoma; Department of the Interior; BIA
Clock: Land / legal capacity
Project stage: No verified data-center project
Interior approved Caddo regulations covering agriculture, business, and residential leasing. The approval establishes a leasing route under tribal regulations. It does not establish that a data-center developer has a lease or site.
Source: BIA — Approved HEARTH Act Regulations
2026-07 — national reporting identifies Caddo data-center interest
Status: Reported lead; official instrument not located
Entities: Caddo Nation leaders; unnamed or unverified developers
Clock: Approach / political debate
Project stage: Unverified
Public reporting says some Caddo leaders view data centers as an economic opportunity. No official Nation resolution, request for proposals, named project company, parcel, lease, power agreement, or construction record has been located in this pass. This remains a lead rather than a confirmed project.
Current state
Legal leasing capacity is verified. A data-center transaction is not.
---
D. Cherokee Nation
2026-02-24 / 2026-02-26 — Principal Chief creates data-center task force
Status: Occurred
Entities: Cherokee Nation; Principal Chief Chuck Hoskin Jr.; Secretary of Natural Resources; Cherokee Nation Businesses; Environmental Protection Commission; Attorney General; CIO
Clock: Tribal government / study / citizen input
Project stage: Policy study
The executive order creates a task force to identify existing and planned data centers within the reservation, study economic and environmental effects, examine alignment with Cherokee business interests, solicit citizen input, and consider tribal, state, and federal policy. The Cherokee website lists the document as created February 24; the signed order states an effective date of February 26. Both dates are retained pending clarification.
Source: Cherokee Nation — Executive Order 2026-02-CTH
2026-06-30 — task-force completion deadline
Status: Scheduled date passed; completion not located
Entities: Cherokee Nation Data Center Task Force
Clock: Tribal government / report
The order required completion and a final report by June 30 unless the Principal Chief extended the deadline in writing.
Source: Cherokee Nation — Executive Order
2026-08-14 — outside public-distribution date if report completed June 30
Status: Derived watch date; not a stated calendar date
Entities: Cherokee Nation
Clock: Transparency / report
The order requires public distribution within 45 days of completion. August 14 is the outside date only if the report was completed June 30 and no extension changes the clock.
Current state
Government study confirmed. No final report, extension, or Cherokee-approved data-center project was located as of July 11.
---
E. Seminole Nation of Oklahoma
Before 2026-03-07 — developer approach prompts internal consideration
Status: Reported; developer identity unverified
Entities: Seminole Nation of Oklahoma; unnamed technology startup
Clock: Approach / tribal government
Indigenous news reporting states that a technology company approached tribal leaders about data-center development. The company's identity and proposal are not established by a primary record in this pass.
2026-03-07 — Tribal Council unanimously adopts data-center moratorium
Status: Reported occurred; primary resolution requested
Entities: Seminole Nation Tribal Council; Mekusukey Band Representative Glen Chebon Kernell
Clock: Tribal government / resistance
Project stage: Moratorium
Native News Online reports a 24–0 vote for a moratorium on generative AI and hyperscale data-center development within the Nation and tribal lands and territories. It reports that the measure bars inquiries, discussions, and developments concerning data centers of any size during the moratorium. The enacted resolution is needed to fix its definitions, duration, exemptions, and territorial reach.
Source: Native News Online — Seminole Nation Moratorium
Current state
Moratorium strongly reported; primary legislative text remains the next document.
---
F. Muscogee (Creek) Nation / Looped Square Ranch lead
2025-08 — citizens reportedly learn of proposed AI data center
Status: Reported lead
Entities: Muscogee (Creek) Nation; tribal citizens; unidentified developer or project proponents
Clock: Approach / citizen opposition
Project stage: Unverified proposal
Reporting says citizens learned of a possible project at Looped Square Ranch, a 5,570-acre site used for a tribal food-sovereignty initiative. The report documents citizen opposition but does not, in the material reviewed here, establish an executed lease, council approval, or current construction state.
Source: ICT / Mother Jones — Muscogee proposal and opposition
Current state
Research lead. Obtain Muscogee council records, land status, project entity, developer correspondence, and present disposition before promoting it into the confirmed-project registry.
---
G. Shoshone-Bannock Tribes / Pocatello ceded-land opposition
2026-06-15 — Tribes receive project records
Status: Occurred according to official tribal statement
Entities: Shoshone-Bannock Tribes; Pocatello public bodies; unidentified or separately identified project developer
Clock: Records / administrative review
Project stage: Non-tribal project under local review
The Tribes state that they received records through a public-records request and reviewed project materials and testimony concerning a proposed AI data center at the former Hoku site.
Source: Shoshone-Bannock Office of Public Affairs statement via ICT
2026-07-07 — Tribes reaffirm opposition
Status: Occurred
Entities: Shoshone-Bannock Tribes; City of Pocatello; project developer
Clock: Tribal government / environmental and utility opposition
Project stage: Administrative dispute
The Tribes oppose the project within their ceded lands and historical homelands. They cite insufficient project information, likely electricity-rate effects, water impacts, and environmental effects. The statement supports the hearing examiner's determination that the developer had not supplied enough information for meaningful review.
Source: Shoshone-Bannock statement
2026-07-16 — Pocatello appeal hearing
Status: Scheduled
Entities: Pocatello City Council; project developer; Shoshone-Bannock Tribes and other interested parties
Clock: Administrative review
The tribal statement identifies July 16 as the City Council appeal hearing date.
Source: Shoshone-Bannock statement
Current state
This is an Indigenous-rights and ceded-land timeline, not a tribal-land development timeline. It is included to preserve the opposition pole without corrupting the land-status field.
---
H. Yakama Nation / Goldendale energy-and-data-center linkage
2026-05-08 — Yakama members and allies protest at Pushpum
Status: Occurred according to reporting
Entities: Yakama Nation members and leaders; Goldendale Energy Storage Project proponents; environmental organizations
Clock: Cultural landscape / energy / resistance
Project stage: Energy project contested; data-center linkage prospective
Participants protested a proposed pumped-storage project at a site sacred to Columbia River tribes. Reporting connects prospective storage output and nearby land discussions to possible STACK Infrastructure data-center demand, but STACK did not confirm the account in the cited report.
Source: ICT / Oregon Capital Chronicle — Goldendale protest
Current state
Confirmed Indigenous opposition to the energy project; reported but not finally verified data-center/offtake linkage. Do not label the prospective data center a Yakama project.
---
I. UnityCloud
Website observed 2026-07-11 — UnityCloud markets tribal sovereign-land AI network
Status: Current public marketing; original launch date not established
Entities: UnityCloud; unnamed Tribal Nations; listed technology partners
Clock: Developer marketing / approach
Project stage: Marketed; no named site verified
UnityCloud's website says it partners with sovereign Tribal Nations to build AI-native data centers on tribal land. It markets faster deployment outside state permitting delays, absence of sales and local property tax, 15–20 percent lower total cost, onsite renewables and microgrids, and sovereign-data protections. The site does not name a Tribal Nation, parcel, executed agreement, operating facility, or construction milestone.
Source: UnityCloud
Current state
Developer thesis confirmed; transaction pipeline unverified. Every tax, jurisdiction, privacy, and permitting statement requires project-specific legal verification.
---
J. Strata Expanse
2026-03-25 — Strata announces first Tribal Nation partnership
Status: Announced
Entities: Strata Expanse; Colusa Indian Energy; Cachil Dehe Band
Clock: Developer / infrastructure
Project stage: Announced partnership
Strata describes its role as developing land and delivering power, cooling, and secure connectivity through an energy-first infrastructure model. The Colusa relationship is identified as its first partnership with a Tribal Nation.
Source: Colusa Indian Energy — Partnership announcement
Current state
One named tribal partnership. Watch for site control, financing, permits, construction, customers, and additional nations.
---
Neutral overlap index — facts only
| Date | Entities that move near one another | Neutral factual seam |
|---|---|---|
| 2026-01-20 | DOE; Tribal Nations; developers | DOE publicly opens the tribal-data-center opportunity frame |
| 2026-02-12 | DOE; Colusa Indian Energy; Data Holdings | Federal convening joins an operating precedent with a proposed powered-land replication model |
| 2026-02-24/26 | Cherokee Nation; regional developers and governments | Cherokee creates its own study process as nearby development grows |
| 2026-03-07 | Seminole Nation; unnamed developer | A tribal government answers the emerging market with a moratorium |
| 2026-03-24/25 | DOE; RES; Colusa; Strata | Federal/industry convening and a named tribal AI-campus announcement occur in the same summit window |
| 2026-06-01 | DOE; developers; Tribal Nations | DOE publicly describes itself as an intermediary and announces work toward a dedicated convening |
| 2026-06-22 | Interior; Cachil Dehe; Caddo Nation | Two Tribes connected publicly to the emerging field receive HEARTH approvals on the same date; project-specific causation is not stated |
| 2026-07 | Cherokee; Shoshone-Bannock; Caddo reporting; UnityCloud marketing | Study, opposition, economic-interest reporting, and developer marketing become visible at the same time |
What would strengthen a coordinated-build reading
- multiple named Tribal Nations announcing projects shortly after DOE matchmaking;
- repeated use of HEARTH, TERA, TEDO, or Section 17 structures in executed project documents;
- the same developers, law firms, financiers, utilities, or federal advisers recurring across projects;
- documents explicitly identifying state/local permitting delay or tax avoidance as a site-selection reason;
- federal grants or technical assistance tied to specific data-center-serving generation or site readiness;
- Defense or national-security customers used to accelerate or protect tribal projects;
- projects migrating from blocked municipal sites to tribal sites with the same operator or tenant.
What would weaken that reading
- few projects proceeding beyond announcements;
- most Tribes adopting moratoria or rejecting offers;
- deals relying on ordinary state/local land rather than trust or restricted land;
- project economics failing without large public subsidies or cost shifting;
- no recurring developer, financier, legal, or federal network;
- HEARTH approvals serving broad existing leasing needs without data-center agreements;
- tribal projects emphasizing small sovereign colocation and tribal data custody rather than hyperscale non-tribal compute.
Immediate document requests and watches
- Seminole Nation moratorium resolution and minutes.
- Cherokee Nation final report or extension; public-release watch through at least 2026-08-14.
- Caddo Nation council agendas, resolutions, economic-development records, and any developer communications.
- Cachil Dehe HEARTH regulations, Colusa/Strata parcel facts, lease authority, and project-phase documents.
- Muscogee Looped Square Ranch council and land records.
- Pocatello July 16 appeal record and written decision.
- DOE Tribal Data Center Convening date, agenda, participants, and outputs.
- UnityCloud named sites, tribal counterparties, financing, and corporate registrations.
- Utility interconnection queues near every confirmed or candidate tribal site.
- Nation-specific gaming, contracting, energy, grant, and enterprise revenue histories before assigning economic motive.
Boundary for the synthesis layer
The first grouped reading should not be written until at least three named contemporary tribal projects have a verified tribal authorization, parcel, counterparty, and power path. Until then, the strongest factual statement is narrower: a federal office is actively cultivating tribal participation; one long-running tribal data center supplies an operating precedent; one contemporary AI-and-energy partnership is publicly named; multiple Tribal Nations are studying, contesting, or reportedly considering the field; and private developers are marketing sovereignty, speed, power, and tax position as a bundled advantage.
Sources
Full saved reading
View cited sources (12)
These are the sources cited by this reading. Each source keeps its own date and scope.
- Data Holdings — company account
- Data Holdings — Tribal Data Sovereignty
- DOE — Beyond Land Leases transcript
- BIA — Approved HEARTH Act Regulations
- Potawatomi Ventures — MKEIX announcement
- Colusa Indian Energy — Partnership announcement
- Cherokee Nation — Executive Order 2026-02-CTH
- Native News Online — Seminole Nation Moratorium
- ICT / Mother Jones — Muscogee proposal and opposition
- Shoshone-Bannock Office of Public Affairs statement via ICT
- ICT / Oregon Capital Chronicle — Goldendale protest
- UnityCloud
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
A. Forest County Potawatomi Community → Potawatomi Ventures → Data Holdings
2012 — Forest County Potawatomi commissions and begins constructing Data Holdings
Status: Occurred
Entities: Forest County Potawatomi Community; Potawatomi business-development entities; Data Holdings
Clock: Capital / construction
Project stage: Under construction
Data Holdings' corporate history states that the Forest County Potawatomi was the sole investor and commissioned and constructed the facility beginning in 2012.
Source: Data Holdings — company account
2013 — Data Holdings opens on Milwaukee trust land
Status: Occurred
Entities: Forest County Potawatomi Community; Data Holdings
Clock: Compute / revenue
Project stage: Operating
Data Holdings opened on Milwaukee's near west side in 2013. The company and DOE describe it as a 100-percent tribally owned enterprise facility located on trust land. It is a 17-MW, approximately 50,000-square-foot colocation facility rather than a hyperscale AI campus.
Sources: Data Holdings — Tribal Data Sovereignty; DOE — Beyond Land Leases transcript
2024-08-06 — Forest County Potawatomi obtains HEARTH-regulation approval
Status: Occurred
Entities: Forest County Potawatomi Community; Department of the Interior; BIA
Clock: Land / legal capacity
Project stage: Existing facility remains operating
Interior approved the Community's agriculture, business, residential, wind and solar, and wind-evaluation leasing regulations. This post-dates the facility's launch by more than a decade and is not treated as its original lease authority.
Source: BIA — Approved HEARTH Act Regulations
2025-09 — Data Holdings becomes the Milwaukee Internet Exchange host
Status: Occurred
Entities: Data Holdings; Milwaukee Internet Exchange; Potawatomi Ventures
Clock: Network / service expansion
Project stage: Operating / expanded role
Data Holdings announced that it would host the Milwaukee Internet Exchange and provide space, power, and network connections. The move extends the facility from ordinary colocation into regional internet infrastructure.
Source: Potawatomi Ventures — MKEIX announcement
2026-02-12 — Data Holdings presents its model through DOE
Status: Occurred
Entities: Data Holdings; DOE Office of Indian Energy; Forest County Potawatomi Community
Clock: Public position / replication
Project stage: Operating / model promoted
General Manager and CTO Ryan Brooks described the trust-land facility, its tax and power-cost position, tribal ownership, closed-loop cooling, small permanent workforce, and long-term recurring revenue. He urged Tribes to treat data centers as businesses rather than passive land transactions and warned about brokers and duplicated deal claims.
Time/place: 3:00–4:00 p.m. EST; online.
Source: DOE — Webinar transcript
Current state
Operating precedent. It proves that a tribally owned data center on trust land is not new. What is new is the effort to replicate or scale the model into AI-native and hyperscale infrastructure.
---