Skip to content

Download the original MD document

---


title: Navajo broadband completes federal permitting while two minerals projects enter FAST-41 transparency research_id: government-hidden-control-surfaces-2026 status: current artifact_role: answer evidence_cutoff: 2026-11-16


---

FAST-41 permitting follow-through

The Federal Permitting Dashboard records all nine federal environmental review and permitting processes complete on November 9, 2026 for the Navajo Nation Department of Education E-Rate Funded Broadband Project. The Permitting Council announced the result November 12. The Navajo Nation Broadband Office sponsored the project and Interior’s Bureau of Indian Affairs (BIA) was the lead permitting agency. The Council coordinated the FAST-41 timetable. The announced $37 million project scope is approximately 323 miles of middle-mile fiber, with intended service to 17 Head Start sites and 33 libraries. The dashboard separately organizes the construction into two phases. Project status and scope · November 12 announcement.

ComponentWhat the underlying record says
BIA right-of-way, Phase IIDashboard marks the final agency action complete October 16. The approximately 101.81-mile authorization concerns specified Navajo trust, allotted and BIA lands. That mileage is a right-of-way segment, while the announced network spans 323 miles. BIA action
BLM right-of-way, Phase IIDashboard marks the action complete. The narrative explains two separate BLM authorizations and says Farmington issued its authorization October 15. Rio Puerco needed revisions and staff time. November 9 appears as the alternative completion date for the action, without an independently verified signed Rio Puerco instrument. BLM action
Bureau of Reclamation use authorization, Phase IIDashboard marks the action complete and labels October 30 as the alternative date for final agency action. Revised construction drawings were part of deeming the application complete. Reclamation action
Tribal and contractor custodyA Navajo Nation Council agenda labels the Phase II E-Rate update as Sacred Wind’s and names BIA, Reclamation and Navajo offices among the presenters. It is earlier committee evidence. Tribal reports of other chapters already connected do not identify acceptance for the exact 50 sites in this federal project. Navajo Nation Council agenda · Tribal President’s August broadband update

USAC financing cross-check. The public FRN table returns 44 original/current rows for Navajo Nation Tribal Consortium and the provider SWC Telesolutions, Inc. The strongest candidate is funding year 2020 FRN 2099078989, Form 471 201042013, BEN 17023688, whose applicant nickname describes 41 New Mexico Head Start and library sites and special construction for lit fiber. The current row says Funded, shows $35,382,028.54 in its funding-commitment-request field, and reports $17,556,046.72 in authorized disbursements. The decision-letter comment lists 1,689,747 route feet (about 320 miles) and adds sites including Church Rock and San Juan, which also appear in the permit description. The 2020 vintage, provider, scope, mileage and overlapping locations make this a strong partial match. The application nickname and the federal announcement use different site counts and speeds. The documents do not reconcile all 50 sites or the full announced $37 million scope to this one funding request. Exact FRN data · FRN field definitions.

The invoice dataset returns eight rows for the same request with line completion dates from August 2021 to August 2023. That is evidence of earlier invoice processing for the funding request. Its authorized total does not establish that all funds settled or that construction and activation followed the November 2026 permitting event. Federal permitting is complete. A site-level roster join, construction acceptance and live service for the full 50-location project remain open. Exact invoice rows · USAC tools and data scope.

Critical minerals

On November 9 the Permitting Council announced two additions to the FAST-41 Transparency Projects category. Both pages showed planned with timetables due on or before November 20 at the cutoff. Transparency posting makes the projects visible on the federal dashboard. Permit decisions have a separate record. Council announcement · Permitting Council eligibility and transparency authority.

- Rochester Rare Earth Separation Facility, Project Freedom Separation. Phoenix Tailings selected Eastman Business Park on October 20. The dashboard names the Department of War as federal lead and describes repurposing an existing industrial facility. The Council quotes $375 million for the Rochester facility within the broader project. The sponsor’s 2027 ramp and 2028 full-production dates are plans. Company site selection · Rochester project dashboard.

- Quinn Fluorspar, Nevada. The dashboard names the U.S. Forest Service lead and describes an exploration project of up to 96 drill pads and about 17,500 meters of drilling. Its plan is evidence of work proposed for exploration, with production outside the reached permit record. Quinn project dashboard.

These are operating records under the existing FAST-41 process. The library’s November 16 Senate permitting return follows a separate bill and floor process.

Sources

Document details and formats

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.