Portfolio Evidence and Readiness Matrix

Status: current bounded comparison; not a scorecard Cutoff: 2026-09-30 ET Rule: record the highest publicly supported state and the exact load/test boundary; do not turn missing evidence into a zero or failure

Evidence ladder

CodeStateMinimum receipt
P0directionsigned direction or official program announcement
P1scope fixednamed site, electrical boundary, mission loads, duration and performance standard
P2authority and money fixedappropriation/obligation or executed agreement with accountable owner/operator
P3design and permission fixedaccepted architecture, interconnection, cyber controls and required license/authorization
P4builtphysical completion with material deficiencies identified or closed
P5commissionedintegrated system accepted for service and delivering power
P6island testedobserved no-grid start, transfer and carriage of a defined load
P7endurance and recovery testeddefined load carried for the required duration and safely resynchronized/recovered
P8recurring readinessrepeated exercise, maintenance, fuel, staffing and exception evidence

These are evidence states, not a single maturity score. A prototype can reach advanced technical testing without becoming a base-power service; a commissioned site can still lack public endurance evidence.

Publicly supportable positions

ObjectPublic state at cutoffLoad boundaryHighest supportable installation-power stateMissing receipt that matters most
FORTRESS Americadepartment program establishedevery major installation; “independent power” undefinedP0 directionimplementation constitution and covered-site list
Army SCI energy portfoliosix conditional developer/site pairingssolicitation says installation support for at least 14 days after qualifying outagebefore P2executed lease/PPA, finance close and site design
Army Janusfive vendor/site pairingssite requirements not equivalent to full-base loadbefore P2/P3task award, authorization, accepted design and construction
NWS Crane MMRplanned joint Navy/Army Janus deployment by September 2028critical operations; commercial ownership/operation describedP0/P1 planning directionfinal commercial agreement, authorization, design, construction and accepted delivery
Eielson microreactornotice of intent to negotiate with Okloup to 5 MW for critical infrastructureP1 proposalfinal award, NRC license, construction and commissioning
Project Peleprototype construction/test path at INLtransportable reactor demonstration, not installation serviceproject-specific build/test lanefueled criticality and published output/test result; then a separate base-service agreement
MCAS Yumaoperational public descriptionbackup capacity described for 100% of current and projected base requirementsP5 publicly describedcurrent black-start, load, duration and recovery receipt
MCAS Miramarcompleted and exercisedpublic exercise supports mission-critical islanding; design description says up to 21 daysP6observed endurance/recovery evidence at the claimed load boundary
SUBASE New Londonoperational microgridessential functions; 10.75 MW CHP plus first-right 7.4 MW fuel-cell accessP5current black-start/endurance result
Fort McCoy Main Gateoperational scope-limited microgridgate and nearby mission-essential facilities; stated at least 14 daysP5observed 14-day and recovery result
DLA Distribution Sigonellaactivated tenant-facility microgridDLA facilities; stated up to 14 days on one fuel loadP5observed endurance and recovery result

Required portfolio fields

Every future FORTRESS site row should contain:

  1. installation and electrical boundary;
  2. covered mission and excluded loads;
  3. normal, peak and critical load;
  4. generation, storage, fuel and switching architecture;
  5. outage duration and replenishment assumption;
  6. legal authority and financing instrument;
  7. asset owner, emergency operator and site-access rights;
  8. utility interconnection and island permission;
  9. cyber/physical control standard;
  10. construction and commissioning state;
  11. black-start, transfer, island-load and recovery results;
  12. exception list, maintenance clock and next recurring exercise.

Comparison ruling

The portfolio is heterogeneous by design. Full-load, critical-load, campus, gate and tenant-facility systems cannot be counted as interchangeable “independent bases.” The valid denominator is not project count; it is the number of covered installations whose defined required load has passed the required test for the required duration and remains in recurring readiness.

Sources

Full saved reading

View the saved source references. This record has no direct external citation in its source-link list.

Document details and formats
Optional file downloads
For AI readers: complete text and record details

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.