Portfolio Evidence and Readiness Matrix
Status: current bounded comparison; not a scorecard
Cutoff: 2026-09-30 ET
Rule: record the highest publicly supported state and the exact load/test boundary; do not turn missing evidence into a zero or failure
Evidence ladder
| Code | State | Minimum receipt |
|---|---|---|
| P0 | direction | signed direction or official program announcement |
| P1 | scope fixed | named site, electrical boundary, mission loads, duration and performance standard |
| P2 | authority and money fixed | appropriation/obligation or executed agreement with accountable owner/operator |
| P3 | design and permission fixed | accepted architecture, interconnection, cyber controls and required license/authorization |
| P4 | built | physical completion with material deficiencies identified or closed |
| P5 | commissioned | integrated system accepted for service and delivering power |
| P6 | island tested | observed no-grid start, transfer and carriage of a defined load |
| P7 | endurance and recovery tested | defined load carried for the required duration and safely resynchronized/recovered |
| P8 | recurring readiness | repeated exercise, maintenance, fuel, staffing and exception evidence |
These are evidence states, not a single maturity score. A prototype can reach advanced technical testing without becoming a base-power service; a commissioned site can still lack public endurance evidence.
Publicly supportable positions
| Object | Public state at cutoff | Load boundary | Highest supportable installation-power state | Missing receipt that matters most |
|---|---|---|---|---|
| FORTRESS America | department program established | every major installation; “independent power” undefined | P0 direction | implementation constitution and covered-site list |
| Army SCI energy portfolio | six conditional developer/site pairings | solicitation says installation support for at least 14 days after qualifying outage | before P2 | executed lease/PPA, finance close and site design |
| Army Janus | five vendor/site pairings | site requirements not equivalent to full-base load | before P2/P3 | task award, authorization, accepted design and construction |
| NWS Crane MMR | planned joint Navy/Army Janus deployment by September 2028 | critical operations; commercial ownership/operation described | P0/P1 planning direction | final commercial agreement, authorization, design, construction and accepted delivery |
| Eielson microreactor | notice of intent to negotiate with Oklo | up to 5 MW for critical infrastructure | P1 proposal | final award, NRC license, construction and commissioning |
| Project Pele | prototype construction/test path at INL | transportable reactor demonstration, not installation service | project-specific build/test lane | fueled criticality and published output/test result; then a separate base-service agreement |
| MCAS Yuma | operational public description | backup capacity described for 100% of current and projected base requirements | P5 publicly described | current black-start, load, duration and recovery receipt |
| MCAS Miramar | completed and exercised | public exercise supports mission-critical islanding; design description says up to 21 days | P6 | observed endurance/recovery evidence at the claimed load boundary |
| SUBASE New London | operational microgrid | essential functions; 10.75 MW CHP plus first-right 7.4 MW fuel-cell access | P5 | current black-start/endurance result |
| Fort McCoy Main Gate | operational scope-limited microgrid | gate and nearby mission-essential facilities; stated at least 14 days | P5 | observed 14-day and recovery result |
| DLA Distribution Sigonella | activated tenant-facility microgrid | DLA facilities; stated up to 14 days on one fuel load | P5 | observed endurance and recovery result |
Required portfolio fields
Every future FORTRESS site row should contain:
- installation and electrical boundary;
- covered mission and excluded loads;
- normal, peak and critical load;
- generation, storage, fuel and switching architecture;
- outage duration and replenishment assumption;
- legal authority and financing instrument;
- asset owner, emergency operator and site-access rights;
- utility interconnection and island permission;
- cyber/physical control standard;
- construction and commissioning state;
- black-start, transfer, island-load and recovery results;
- exception list, maintenance clock and next recurring exercise.
Comparison ruling
The portfolio is heterogeneous by design. Full-load, critical-load, campus, gate and tenant-facility systems cannot be counted as interchangeable “independent bases.” The valid denominator is not project count; it is the number of covered installations whose defined required load has passed the required test for the required duration and remains in recurring readiness.
Sources
Full saved reading
View the saved source references. This record has no direct external citation in its source-link list.
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.