Funds Drawn and Risk-Holder Matrix — Six Deep Dives
Reading rule
For each project, preserve these three non-additive measures:
- facility commitment — maximum credit or stated equity commitment;
- actual advance / funded signal — cash advance, loan availability reduction or other hard funding evidence; and
- actual construction spend — capitalized project cost or other observed deployment.
The holder of an economic claim can change through syndication, refinancing, restructuring, a guarantee, or sale of the asset. A named arranger is not necessarily the final risk holder.
| Project | Legal borrower and facility | Commitment | Actual advance / funded signal | Restricted use and spend evidence | Presently identified risk holder / residual claimant | Crucial gap |
|---|---|---|---|---|---|---|
| CP2 LNG Phase 1 | CP2 LNG LLC; guarantors CP2 Procurement and CP Express. $11.3B construction term loan + $850M working-capital/LC; CP2 Holdings separately has $2.8B equity bridge + $191M interest reserve. | $15.1B disclosed Phase-1 financial-close stack. | At 2025 year-end, $9.39B construction and $740M WC/LC capacity available, implying roughly $1.91B and $110M used/outstanding/LC—but not a separately stated cash-draw series. | Facility use: finance/develop/construct/place in service. $9.9B total CP2 Phases 1–2 project cost paid at year-end is not attributable solely to Phase 1/new facilities. | Project assets/guarantors and secured lenders; 10-K says project debt has no parent recourse/guarantee. | Facility-exhibit extraction for originating lender list; Phase-1-only draw and spend. |
| Rio Grande LNG Train 5 | Rio Grande LNG Train 5, LLC. $3.59B senior-secured non-recourse term loan + $500M senior-secured private-placement notes; equity through Train 5 JVCo. | $4.09B project debt; $2.58B committed equity. | Close established, but no public aggregate cash-draw balance. Notes fund in tranches December 2025–October 2026. | Project construction and collateral/security use; full NTP, but no numeric spend. | Secured lenders/noteholders, then JV equity; sponsor has upstream borrowing to fund its contribution. | Draw balance, lender/noteholder schedule and construction spend. |
| Thacker Pass Phase 1 | Lithium Nevada LLC, owned by Lithium Nevada Ventures LLC LAC–GM JV. DOE ATVM facility; Citibank collateral/depositary accounts. | Expected maximum $2.23B after amendment ($1.97B principal). | $867M: $435M 2025-10-20 + $432M 2026-02-24. | Restricted accounts; advances typically quarterly, spent monthly. $611.6M 2025 capitalized construction/project cost; later Q1 record reports $1.277B cumulative capitalized project costs at 2026-03-31. | DOE secured lender; LAC completion/debt guarantor; GM/LAC residual equity; GM offtake supports revenue. All LN assets/equity and tax-credit-monetization proceeds are secured. | Advance-to-vendor/use-of-proceeds schedule. |
| BlueOval SK | Original borrower BOSK; successor structure after May 2026: Ford Energy Battery holds Kentucky plants/assumed note for one advanced KY plant; SK Battery America controls BOSK/Tennessee. | Up to $9.63304B DOE/FFB multi-draw facility. | $7.83554B actual BOSK advances reported before restructure. | Construction use for KY/TN battery plants. KY Facility 1 certificate of occupancy and Facility 2 building complete; advance is not spend. | Post-restructure: Ford Energy Battery assumed $3.80504B DOE note associated with a Kentucky plant; SKBA/BOSK Tennessee exposure requires successor schedule. Ford's former $6.6B support obligation ended. | Allocation of remaining advances/notes and post-restructure spend/operations. |
| TSMC Arizona | TSMC Arizona Corporation, wholly owned by TSMC; Fab 21. CHIPS direct-funding agreement and government-loan agreements; existing Arizona notes. | Up to $6.6B direct funding + up to $5B government loans; $4.5B 2021 parent-guaranteed notes; up to $20B parent capital increase authorized. | No public direct-funding disbursement, government-loan draw, or paid-in parent-capital amount identified. | Award/loan funds subject to milestones and conditions. Fab 1 HVM; Fabs 2/3 construction milestones demonstrate build but not cost/draw. | Parent gives Commerce unconditional guarantee; parent guarantees Arizona notes; award/loan availability conditional. | Paid-in parent equity, award disbursement, loan draw and fab-specific spend. |
| Abilene DC 1 | Abilene DC 1 LLC, wholly owned by Longhorn JV (92.3% BOREC/Blue Owl; 7.7% Crusoe). | $2.288B construction loan; $926.847M equity contributions as of 2025-12-31. | Construction-loan proceeds are restricted for development; lender and numeric draw not public. | Two buildings/eight halls delivered; Oracle rent began March/July 2025; power station under development; no numeric spend. | Construction lender, then BOREC/Crusoe equity. Oracle is 100% tenant and reimburses specified construction costs under build-to-suit lease. | Lender, actual loan balance/draw and project spend. |
First conclusion
Only Thacker Pass has a clean public chain from facility to stated advances to a numeric capitalized-cost figure. BlueOval has a large advance figure, but a post-advance ownership/borrower restructuring. CP2 has an availability-based funding signal and combined-phases spend. The other three demonstrate financing architecture or construction, not published draw-to-spend cash paths.
This is why the eventual numerator must retain separate columns for committed, advanced, spent and operating—not collapse them into a single "investment" amount.
Sources
- Venture Global 2025 10-K
- NextDecade Train 5 closing release; Train 5 financing 8-K
- Lithium Americas 2025 10-K; Q1 2026 10-Q
- Ford May 2026 8-K
- TSMC 2025 20-F
- Abilene DC1 audited statements; Blue Owl tenant filing
Sources
Full saved reading
View cited sources (9)
These are the sources cited by this reading. Each source keeps its own date and scope.
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Funds Drawn and Risk-Holder Matrix — Six Deep Dives"
status: current
artifact_role: cash-path and economic-risk ledger
evidence_cutoff: 2026-07-31
---