Primary-Source Claim Ledger
This ledger holds the atomic factual spine. A source is primary for the state its author can establish: EIA for reported generator inventory, a regulator for an order, an owner for its project state, an OEM for its products and backlog, and a test organization for its own demonstration. Vendor benefits remain vendor-reported.
| ID | Atomic claim at cutoff | Grade | Direct primary source | State / boundary |
|---|---|---|---|---|
B-01 | Developers planned 86 GW of U.S. utility-scale additions in 2026: 51% solar, 28% batteries, 14% wind and 6.3 GW gas. | A | EIA | Plan from a preliminary inventory; not guaranteed completion. |
B-02 | Planned 2026 gas additions comprised 3.3 GW combined cycle and 2.8 GW combustion turbine. | A | EIA | Planned operating-capacity clock, not order-book size. |
B-03 | GE Vernova reported 116 GW of gas equipment backlog plus slot reservations at Q2 2026 and targeted at least 125 GW by year-end. | B | GE Vernova | Global mixed commercial state; backlog and reservation are not collapsed. |
B-04 | GE reported 130 HA units commissioned and another 195 under contract in July 2026. | B | GE Vernova | Frame-family global installed and contract counts. |
B-05 | Siemens reported 12 GW booked in Q2 FY2026 and 87 GW total gas commitments, including 24 GW data-center related. | B | Siemens Energy analyst presentation | Global commitments; not all U.S. and not all operating. |
B-06 | MHI booked 35 large-frame gas turbines in FY2025 and reported GTCC backlog above ¥5 trillion. | B | MHI FY2025 presentation | Global unit/order measure; country allocation incomplete. |
B-07 | NRG placed 415 MW of new T.H. Wharton capacity into commercial operation on May 26, 2026. | A/B | NRG Q2 2026 results | Owner's explicit COD record. |
B-08 | NRG's Cedar Bayou 5 and Greens Bayou 6 projects remained in construction, with mid-2028 targets. | B | NRG Q2 2026 results | Construction and target clocks only. |
B-09 | Plant Yates is building three M501JAC simple-cycle units totaling 1.3 GW; Units 8 and 9 had received major equipment by December 2025. | A/B | Georgia Power | Owner project record; all units targeted by end-2027. |
B-10 | Duke had begun site work at Cayuga; its two new units are targeted for 2029 and 2030. | A/B | Duke Energy | Construction, not operation. |
B-11 | Project Kilby has a 20-year PPA to serve a Microsoft data center. | B | Kilby project owner | Offtake/development state; not FID or completed capacity. |
B-12 | Berkeley Lab counted 253 GW of gas in active interconnection queues at year-end 2025, but only 18% had a draft or executed IA. | A | DOE/LBNL | Queue capacity is a developer-activity signal, not buildable or operating capacity. |
B-13 | Historically, 13% of capacity entering queues in 2000–2020 was operating by end-2025; median request-to-operation exceeded five years. | A | DOE/LBNL | Historical conversion constraint, not a deterministic project forecast. |
B-14 | Pin Oak Creek Energy Center reached commercial operation on April 30, 2026. | A/B | Constellation Q1 2026 results | Owner's explicit COD record. |
B-15 | Homer City's seven GE 7HA.02 turbines were converted to firm order, while Pennsylvania DEP records later permitting/site activity. | A/B | GE Vernova, Pennsylvania DEP | Firm order and site activity; not operating capacity. |
T-01 | GE says its generation M&D service monitors 1,000+ plants and processes tens of billions of data points per day. | C | GE Vernova APM | Vendor-reported scale; proves commercial offering, not independent benefits. |
T-02 | Siemens says 800+ power units use its monitoring/optimization expertise and 260+ plants use performance monitoring. | C | Siemens Energy | Vendor-reported service scale. |
T-03 | MHI reported 144 TOMONI-connected thermal units by August 2023, operating anomaly detection and specialist review. | R/C | MHI Technical Review | Named internal system record; specialists remained in the judgment loop. |
T-04 | EPRI describes fault-inference digital twins as implemented at several gas and nuclear plants, with typical implementation of six to twelve months. | R | EPRI Plant Modernization Toolbox | Broad-use readiness with recorded model and sensor failure modes; not a universal twin. |
T-05 | GE Autonomous Tuning changes LM2500/LM6000 combustion targets every two seconds within existing safety-critical control logic. | C | GE product page, launch record | Real bounded closed loop; not authority over trips, life extension or return to service. |
T-06 | MHI identifies autonomous combustion-dynamics and cooling-air optimization at T-Point 2. | R/C | Mitsubishi Power TOMONI | Selected process functions, not general autonomous plant operation. |
T-07 | Siemens and Volkswagen completed a certified 72-hour unattended gas-and-steam plant test in October 2025. | R | Siemens Energy reference | Plant-specific hazard analysis and retained protection; exceptional reference case. |
T-08 | GE reports an ANYmal robot collecting inspection data from 15+ assets at a named Irish thermal plant and feeding APM. | C | GE Vernova case study | Named commercial deployment; outcome remains vendor-reported. |
T-09 | GE says more than 9,000 wind blades had received Digital Blade Certificates after robotic and AI-assisted inspection by April 2026. | C | GE Vernova review | Manufacturing QA scale; humans review flagged areas. |
T-10 | IBM launched Condition Insight in December 2025 and Maximo 9.2 agentic workflows in June 2026. | C | IBM Condition Insight, IBM Maximo 9.2 | Product availability, not proof of owner adoption or safety authority. |
T-11 | DOE CESER released Stormbreaker in July 2026 to test LLM and agent failure modes in dynamic power and OT environments. | R | DOE CESER | Evaluation need is evidence against assuming generic-agent readiness. |
W-01 | Vestas reports more than 128 GW and 55,000 turbines on its Scipher platform. | C | Vestas Scipher | Vendor-reported platform scale; multi-function fleet software is commercial. |
W-02 | RWE says TPA Next Evolution has been implemented across its full OPEA wind fleet and assists analysts across multiple condition-data modules. | C | RWE digital energy production | Operator-reported deployment; assists rather than replaces analysts. |
W-03 | An autonomous drone inspection of an operating, rotating offshore turbine was demonstrated at Rødsand 2 in January 2026. | R | RWE AQUADA-GO | Completed demonstration; not broad fleet deployment. |
W-04 | NREL's wtDigiTwin estimates turbine loads, motion and environment from SCADA plus a turbine model. | R | NREL wtDigiTwin | Purpose-specific research software, not a universal lifecycle twin. |
W-05 | DOE/NREL's 2024 offshore O&M roadmap places fully autonomous inspection/intervention in its long-term 2032–2036 horizon. | R | DOE/NREL roadmap | R&D roadmap, not deterministic market forecast. |
Claims not supported by this record
- “AI is now running U.S. turbine fleets autonomously.”
- “The 116 GW, 87 GW and MHI unit totals can be added into one U.S. buildout number.”
- “A reserved manufacturing slot is a plant under construction.”
- “Every new turbine includes an APM platform, digital twin or LTSA.”
- “A digital twin provides one complete, authoritative representation of the asset.”
- “Predictive maintenance eliminates inspections or transfers engineering authority to a model.”
- “A product launch proves adoption, savings or safe control-room use.”
- “Interconnection-queue capacity is a construction or completion forecast.”
Sources
Full saved reading
View cited sources (30)
These are the sources cited by this reading. Each source keeps its own date and scope.
- EIA
- GE Vernova
- Siemens Energy analyst presentation
- MHI FY2025 presentation
- NRG Q2 2026 results
- Georgia Power
- Duke Energy
- Kilby project owner
- DOE/LBNL
- Constellation Q1 2026 results
- GE Vernova
- Pennsylvania DEP
- GE Vernova APM
- Siemens Energy
- MHI Technical Review
- EPRI Plant Modernization Toolbox
- GE product page
- launch record
- Mitsubishi Power TOMONI
- Siemens Energy reference
- GE Vernova case study
- GE Vernova review
- IBM Condition Insight
- IBM Maximo 9.2
- DOE CESER
- Vestas Scipher
- RWE digital energy production
- RWE AQUADA-GO
- NREL wtDigiTwin
- DOE/NREL roadmap
Document details and formats
About the dates and filing language
- Evidence date
- When this document or named claim was checked. A newer collection, export or website date does not update it.
- Current, private, Workbench or promotion
- These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
- Master data and projection
- The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
- Provenance and source join
- Where a record came from, and the exact reference connecting a claim to its source.
- Gate, receipt and operating evidence
- A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Primary-Source Claim Ledger — Turbine Asset Management and Buildout"
status: current Workbench control
artifact_role: atomic claim ledger
evidence_cutoff: 2026-08-09 ET
---