Primary-Source Claim Ledger

This ledger holds the atomic factual spine. A source is primary for the state its author can establish: EIA for reported generator inventory, a regulator for an order, an owner for its project state, an OEM for its products and backlog, and a test organization for its own demonstration. Vendor benefits remain vendor-reported.

IDAtomic claim at cutoffGradeDirect primary sourceState / boundary
B-01Developers planned 86 GW of U.S. utility-scale additions in 2026: 51% solar, 28% batteries, 14% wind and 6.3 GW gas.AEIAPlan from a preliminary inventory; not guaranteed completion.
B-02Planned 2026 gas additions comprised 3.3 GW combined cycle and 2.8 GW combustion turbine.AEIAPlanned operating-capacity clock, not order-book size.
B-03GE Vernova reported 116 GW of gas equipment backlog plus slot reservations at Q2 2026 and targeted at least 125 GW by year-end.BGE VernovaGlobal mixed commercial state; backlog and reservation are not collapsed.
B-04GE reported 130 HA units commissioned and another 195 under contract in July 2026.BGE VernovaFrame-family global installed and contract counts.
B-05Siemens reported 12 GW booked in Q2 FY2026 and 87 GW total gas commitments, including 24 GW data-center related.BSiemens Energy analyst presentationGlobal commitments; not all U.S. and not all operating.
B-06MHI booked 35 large-frame gas turbines in FY2025 and reported GTCC backlog above ¥5 trillion.BMHI FY2025 presentationGlobal unit/order measure; country allocation incomplete.
B-07NRG placed 415 MW of new T.H. Wharton capacity into commercial operation on May 26, 2026.A/BNRG Q2 2026 resultsOwner's explicit COD record.
B-08NRG's Cedar Bayou 5 and Greens Bayou 6 projects remained in construction, with mid-2028 targets.BNRG Q2 2026 resultsConstruction and target clocks only.
B-09Plant Yates is building three M501JAC simple-cycle units totaling 1.3 GW; Units 8 and 9 had received major equipment by December 2025.A/BGeorgia PowerOwner project record; all units targeted by end-2027.
B-10Duke had begun site work at Cayuga; its two new units are targeted for 2029 and 2030.A/BDuke EnergyConstruction, not operation.
B-11Project Kilby has a 20-year PPA to serve a Microsoft data center.BKilby project ownerOfftake/development state; not FID or completed capacity.
B-12Berkeley Lab counted 253 GW of gas in active interconnection queues at year-end 2025, but only 18% had a draft or executed IA.ADOE/LBNLQueue capacity is a developer-activity signal, not buildable or operating capacity.
B-13Historically, 13% of capacity entering queues in 2000–2020 was operating by end-2025; median request-to-operation exceeded five years.ADOE/LBNLHistorical conversion constraint, not a deterministic project forecast.
B-14Pin Oak Creek Energy Center reached commercial operation on April 30, 2026.A/BConstellation Q1 2026 resultsOwner's explicit COD record.
B-15Homer City's seven GE 7HA.02 turbines were converted to firm order, while Pennsylvania DEP records later permitting/site activity.A/BGE Vernova, Pennsylvania DEPFirm order and site activity; not operating capacity.
T-01GE says its generation M&D service monitors 1,000+ plants and processes tens of billions of data points per day.CGE Vernova APMVendor-reported scale; proves commercial offering, not independent benefits.
T-02Siemens says 800+ power units use its monitoring/optimization expertise and 260+ plants use performance monitoring.CSiemens EnergyVendor-reported service scale.
T-03MHI reported 144 TOMONI-connected thermal units by August 2023, operating anomaly detection and specialist review.R/CMHI Technical ReviewNamed internal system record; specialists remained in the judgment loop.
T-04EPRI describes fault-inference digital twins as implemented at several gas and nuclear plants, with typical implementation of six to twelve months.REPRI Plant Modernization ToolboxBroad-use readiness with recorded model and sensor failure modes; not a universal twin.
T-05GE Autonomous Tuning changes LM2500/LM6000 combustion targets every two seconds within existing safety-critical control logic.CGE product page, launch recordReal bounded closed loop; not authority over trips, life extension or return to service.
T-06MHI identifies autonomous combustion-dynamics and cooling-air optimization at T-Point 2.R/CMitsubishi Power TOMONISelected process functions, not general autonomous plant operation.
T-07Siemens and Volkswagen completed a certified 72-hour unattended gas-and-steam plant test in October 2025.RSiemens Energy referencePlant-specific hazard analysis and retained protection; exceptional reference case.
T-08GE reports an ANYmal robot collecting inspection data from 15+ assets at a named Irish thermal plant and feeding APM.CGE Vernova case studyNamed commercial deployment; outcome remains vendor-reported.
T-09GE says more than 9,000 wind blades had received Digital Blade Certificates after robotic and AI-assisted inspection by April 2026.CGE Vernova reviewManufacturing QA scale; humans review flagged areas.
T-10IBM launched Condition Insight in December 2025 and Maximo 9.2 agentic workflows in June 2026.CIBM Condition Insight, IBM Maximo 9.2Product availability, not proof of owner adoption or safety authority.
T-11DOE CESER released Stormbreaker in July 2026 to test LLM and agent failure modes in dynamic power and OT environments.RDOE CESEREvaluation need is evidence against assuming generic-agent readiness.
W-01Vestas reports more than 128 GW and 55,000 turbines on its Scipher platform.CVestas ScipherVendor-reported platform scale; multi-function fleet software is commercial.
W-02RWE says TPA Next Evolution has been implemented across its full OPEA wind fleet and assists analysts across multiple condition-data modules.CRWE digital energy productionOperator-reported deployment; assists rather than replaces analysts.
W-03An autonomous drone inspection of an operating, rotating offshore turbine was demonstrated at Rødsand 2 in January 2026.RRWE AQUADA-GOCompleted demonstration; not broad fleet deployment.
W-04NREL's wtDigiTwin estimates turbine loads, motion and environment from SCADA plus a turbine model.RNREL wtDigiTwinPurpose-specific research software, not a universal lifecycle twin.
W-05DOE/NREL's 2024 offshore O&M roadmap places fully autonomous inspection/intervention in its long-term 2032–2036 horizon.RDOE/NREL roadmapR&D roadmap, not deterministic market forecast.

Claims not supported by this record

Sources

Full saved reading

View cited sources (30)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details
About the dates and filing language
Evidence date
When this document or named claim was checked. A newer collection, export or website date does not update it.
Current, private, Workbench or promotion
These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
Master data and projection
The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
Provenance and source join
Where a record came from, and the exact reference connecting a claim to its source.
Gate, receipt and operating evidence
A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

title: "Primary-Source Claim Ledger — Turbine Asset Management and Buildout"

status: current Workbench control

artifact_role: atomic claim ledger

evidence_cutoff: 2026-08-09 ET

---