title: "Federal IT modernization savings actually realized and the later VA forecast revision"

research_id: federal-government-website-sweep-2026-07-25

evidence_cutoff: 2026-11-11

status: current

---

Federal IT modernization savings actually realized and the later VA forecast revision

Authority and 2026 call for proposals

Section 1078 of the Modernizing Government Technology Act, enacted in the FY2018 NDAA (Pub. L. 115-91), established the Technology Modernization Fund and Board. Section 2014 of Pub. L. 119-103 extended the statutory cutoff for projects outside the in-progress exception to December 11, 2026. The Board evaluates and recommends investments, GSA administers transfers and receiving agencies report obligations separately. 40 U.S.C. §11301 note, §1078 · Pub. L. 119-103 §2014 · TMF process

The September call documents set October 20, 2026 as the initial-proposal date for eligibility for consideration by December 11. Federal agencies under 5 U.S.C. §551 were eligible. The permitting priority requires projects that advance an agency’s Permitting Technology Action Plan. The AI priority covers preparation, pilots or enterprise deployment to address agency capability or infrastructure gaps. The call page marks the call closed and says later submissions have no guarantee of consideration before December 11. Call status · September permitting call · September AI call

The public portfolio lists four 2026 investment starts through November 15. TMF defines “investment start” as the month and year of notification of the Board vote. The entries do not specify the solicitation that produced the projects. A public applicant roster, Board selection, transfer or obligation expressly tied to the September–October intake was not located. TMF public portfolio

Agency and projectInvestment startPublic investment amount
State, agentic AIJuly 2026$17.3 million
USDA, environmental review platformAugust 2026$10 million
DOT, airline complaint AISeptember 2026$3,784,596
USDA, payroll modernizationSeptember 2026$52,324,826

The July accountability evidence ledger located the GAO audit. Its July 23, 2026 release reports on the June 2025 portfolio and preserves subsequent agency revisions separately.

Savings recorded by June 2025

GAO reviewed 68 unclassified projects across 40 agencies with about $1.03 billion in approved Technology Modernization Fund investments through June 2, 2025. GAO's Table 1 lists 11 projects with $13,487,369 in realized savings as of June 2025. GAO separately reports about $1.06 billion in expected savings for 24 projects, with most expected to finish realizing those savings in FY2027 or later. Approved funds, actual outlays and realized savings have different evidence. The audit does not give a portfolio-wide realized return on those approvals. GAO-26-107737, Table 1 and appendix I

The GAO summary describes the 11 as coming from the 24-project forecast group. Table 1 includes a Postal Regulatory Commission project for which no savings had been expected and a USAID project canceled after realizing its expected savings. The published table total and the dated aggregate forecast remain usable. Their membership needs separate treatment for any project-matched comparison. GAO assessed six completed projects with at least one full fiscal year for savings. Two met or were on track to meet their targets and four were below target or off track. GAO full report, Tables 1–2 and appendix I

The VA forecast changed

The June 2025 forecast in Figure 2 includes about $210.36 million for VA Veteran Identity Modernization. In June 2026, VA told GAO that its estimate had fallen to $35 million over fiscal years 2025 through 2028, citing continued identity-verification licensing costs omitted from the earlier estimate. The $1.06 billion figure retains its original date and population. An updated portfolio forecast and later realized savings for the VA project remain open. GAO Figure 2 and its VA revision note