Federal Reserve self-funding and real-estate control map

Updated: 2026-09-30 Status: current workbench research; not promoted to the Chronicle Scope: Board of Governors funding, Reserve Bank earnings, Washington real estate, renovation cost claims, procurement, oversight and federal-fiscal incidence. This is a factual/legal control map, not a finding about motive, fraud, monetary policy or project value.

Every monetary amount is written in full nominal dollars with commas and no letter-suffix scaling. Added zeros expand the source's reporting unit; they do not imply precision beyond the underlying disclosure.

Short answer

The clean answer is more unusual than either side's shorthand:

The Board's renovation account is not an annually appropriated taxpayer account, and Congress expressly says that the Reserve Bank assessments used to fund the Board are not Government funds or appropriated moneys. But the money is not ordinary private property either. It is a congressionally created, public-purpose central-bank funding stream controlled by a federal agency, drawn from Reserve Banks with mixed sovereign and commercial income, and economically connected to current or future Treasury receipts.

The strongest description is therefore:

Public-purpose, congressionally created, nonappropriated central-bank funds under unusually broad Fed control, with the United States as the ultimate residual claimant.

That sentence is a functional synthesis, not a statutory label that applies identically to every Fed account.

The renovation dispute exposes a real control seam:

The sharper institutional question is not "How can a private company spend public appropriations?" It is:

Why did Congress give a federal monetary authority a self-assessed, nonappropriated property purse, and what ex ante control substitutes for the appropriations and procurement controls used elsewhere?

September 2026 OIG closure

The answer is now substantially less hypothetical. The September 29 OIG evaluation found no reasonable grounds for a federal criminal referral and no Board-policy violation warranting an administrative-misconduct finding. It also found that the Board did not effectively manage and execute the Eccles-1951 construction-manager-at-risk contract.

The Board had not agreed to a project-level guaranteed maximum price by July 2026, four years after construction began and after more than $2,000,000,000 had been awarded. It accumulated 84 limited-scope price packages, paid a 2.95% construction-cost fee without a project-level cap, did not use its owner representative to independently validate the largest bid variances, and repeatedly reported the project as "on track" against rebased budget and schedule references. The OIG said this execution resembled a higher-risk cost-plus reimbursement contract with a pay-as-you-go approach.

Chairman Kevin Warsh concurred with all seven recommendations. His attached response makes GSA the Project Executive, directs an independent audit of all awarded costs, orders GMP negotiations and fixed cost/schedule metrics, and commits to contract reconciliation and possible reimbursement or credits. Those are operating-control changes, not yet a signed ceiling, completed audit, recovery or final-cost receipt.

Read

`FEDERAL_RESERVE_ECCLES_1951_OIG_EVALUATION_2026-09-29.md`

for the full cost, contract, governance, design-feature and recommendation map.

II. Four entities that "the Fed" shorthand collapses

EntityLegal characterProperty / money boundary
Board of GovernorsFederal government agencyOwns and controls the Washington campus; has its own audited books; levies assessments on the Reserve Banks
Federal Open Market CommitteeStatutory monetary-policy committeeNot the owner or capital-budget approver for the Washington buildings
Twelve Federal Reserve BanksSeparate federally chartered bodies corporate with governmental, corporate and central-bank characteristicsHold their own premises and books; earn System income; pay Board assessments
Member commercial banksRequired subscribers to Reserve Bank stockHold compulsory, nontransferable membership capital; do not own Board buildings or a normal corporate residual

The Board's 2025 audited statements expressly distinguish the federal-agency Board from the Reserve Banks and their separate financial statements.

Each Reserve Bank is a separate body corporate under 12 U.S.C. §341. That does not make the Board a subsidiary of the Reserve Banks or the member banks.

---

III. The statutory purse

1. Assessment authority

Under 12 U.S.C. §243, the Board may levy semiannual assessments on the Reserve Banks sufficient to pay estimated Board expenses and salaries. The statutory allocation is in proportion to each Reserve Bank's capital stock and surplus; the assessment then becomes a Reserve Bank expense that reduces its net earnings.

The same section permits the Board to:

Congress therefore tied the self-funding power directly to the property power.

Under 12 U.S.C. §244:

That last sentence is the strongest legal support for saying the renovation does not use ordinary taxpayer appropriations.

It does not establish that:

The narrow and accurate statement is:

Congress directs that Board assessment proceeds "shall not be construed to be Government funds or appropriated moneys," while the assessing and spending institution is a federal agency exercising powers Congress created.

3. What the Board reported in 2025

The Board's audited 2025 financial statements report:

Board item2025 amount
Assessments for Board operations and capital$1,577,000,000
Currency-related assessment revenue$54,500,000
Operating expenses$1,192,000,000
Net income$454,500,000
Net property, equipment and software$1,770,000,000
Construction in progress$1,240,000,000
Cumulative results and accumulated OCIabout $1,474,000,000

The Board also reported total 2025 assessments on Reserve Banks of:

Assessment purpose2025 amount
Currency$1,124,800,000
Board operations and capital$1,577,000,000
CFPB$245,100,000
Total$2,946,900,000

The two currency numbers are not duplicate descriptions of one revenue line. The larger $1,124,800,000 total includes roughly $1,070,000,000 of currency-cost pass-through—principally note-production expense—with an offsetting expense. Only the $54,500,000 component is presented as the Board's currency-related operating/capital assessment revenue.

Reserve Bank remittances to Treasury are not Board operating revenue. The Board acts as intermediary when those remittances pass to Treasury.

4. Fixed-asset and cash-capex bridge

The Board's 2025 audited statements provide a much better actual-spend clock than the project-life budget:

Board fixed-asset measure20242025ChangeChange %
Property, equipment and software — gross cost$1,731,100,000$2,255,400,000+$524,300,000+30.3%
Accumulated depreciation and amortization$(446,700,000)$(485,700,000)+$39,000,000 contra-asset—
Property, equipment and software — net$1,284,500,000$1,769,700,000+$485,300,000+37.8%
Construction in process$721,700,000$1,240,000,000+$518,300,000+71.8%

Construction in process supplied about 98.9% of the gross fixed-asset cost increase. The balance-sheet move was therefore overwhelmingly unfinished capital work, not a revaluation of land or completed buildings:

Gross-cost component20242025Change
Land$49,500,000$49,500,000—
Buildings and improvements$697,100,000$700,400,000+$3,300,000
Construction in process$721,700,000$1,240,000,000+$518,300,000
Furniture and equipment$143,900,000$139,200,000$(4,700,000)
Software in use and in process$84,500,000$90,500,000+$6,000,000
Other listed fixed-asset categories, net movement——about +$1,400,000

The statement of cash flows then shows actual cash used for capital expenditures:

Cash-flow measure20242025Change
Capital expenditures$343,300,000$527,400,000+$184,100,000 / +53.6%

Two-year 2024–2025 cash capital expenditures were $870,700,000.

The three numbers answer three different questions:

The cash-flow number is not disclosed as Eccles–1951-only spending. It includes the Board's property, equipment and software capital activity. The notes also identify noncash accrued and retainage liabilities for capital assets, so a project invoice, a capitalized asset and a cash payment need not land in the same reporting year.

Disposal, borrowing and noncash checks

The 2025 statements do not support a simple equation of:

cash capital expenditures = gross additions = net fixed-asset increase

The disclosed bridge items are:

Possible bridge item2025 evidenceRuling
Cash capital expenditures$527,426,000 outflowDirect cash-spend evidence
Disposal of property/equipment$1,003,000 net lossDisposals occurred; gross asset cost and any cash proceeds are not separately disclosed
Proceeds from fixed-asset salesNo separate investing inflowNo material sale proceeds are separately reported; do not assume zero proceeds below the statement's disclosure threshold
New finance-lease asset/liability$453,000 asset / $456,000 liabilitySmall noncash financing addition; not material to the $524,300,000 gross-cost increase
Finance-lease principal paid$459,000 cash outflowOnly financing cash-flow line reported
Accrued liabilities for noncash capital assets$(18,110,000) net changeTiming bridge between goods/services recognized and cash paid
Retainage liabilities for noncash capital assets$(33,477,000) net changeAdditional contractor-payment timing bridge
Conventional borrowing or loan proceedsNo line reportedNo evidence in the Board-only statements that 2025 fixed-asset growth was financed by ordinary loans

The negative liability changes indicate that cash paid during 2025 can include settlement of capital obligations recorded earlier. The statements do not provide a complete gross additions/disposals roll-forward, so the exact bridge from $527,426,000 cash capex to the +$524,292,000 net gross-cost movement cannot be fully reconstructed from this public statement alone.

This is also why $527,400,000 of capital cash outflow can coexist with $454,500,000 of reported net income. Capital expenditure is initially recorded on the balance sheet and cash-flow statement; only depreciation, amortization and disposal effects flow through current operating expense. In cash terms, $477,700,000 from operations did not fully cover the $527,400,000 capital outflow; after $500,000 of finance-lease payments, Board cash fell by $50,200,000 during 2025.

---

IV. Where the underlying money comes from

The Reserve Banks do not receive a renovation appropriation and then pass it to the Board. The Board allocates its statutory assessments among them in proportion to capital stock and surplus. Those assessments are Reserve Bank expenses paid from their pooled resources and reduce net earnings.

The 2025 combined Reserve Bank statements report approximately:

Reserve Bank inflow2025 amount
Interest on Treasury securities$106,600,000,000
Interest on agency MBS$48,000,000,000
Financial-service income$542,000,000
Reimbursed fiscal-agency services$934,000,000

They also reported approximately:

Reserve Bank outflow2025 amount
Interest paid on reserve balances and similar depository-institution balances$147,700,000,000
Interest on repo liabilities$19,700,000,000
Board operations and currency included in combined operating expenses$2,702,000,000
CFPB$245,000,000

This produces a mixed-source pool:

Treasury and agency-security interest
+ loan and other asset income
+ payment-service fees
+ reimbursed Treasury fiscal-agent work
                         |
                         v
                 12 Reserve Banks
                         |
        +----------------+----------------+
        |                |                |
        v                v                v
 interest expense   Bank operations   Board assessments
 dividends/surplus  priced services   currency + CFPB
        \                |                /
         \_______________|_______________/
                         |
                         v
          excess earnings to Treasury, if any

Payment-service users do pay fees, and Treasury reimburses Reserve Banks for specified fiscal-agent services. But it would be inaccurate to say that the renovation is a direct $3,000,000,000 bill sent to private businesses or a direct $3,000,000,000 Treasury appropriation. The assessment falls on pooled Reserve Bank earnings.

---

V. Who ultimately bears the spending?

The ordinary positive-earnings case

Reserve Banks ordinarily pay:

  1. operating expenses;
  2. the statutory member-bank dividend;
  3. the capped surplus requirement; then
  4. remit remaining earnings to Treasury.

An additional Board expense therefore reduces the residual otherwise available for Treasury.

The current deferred-asset case

At year-end 2025, the Reserve Banks reported a $243,481,000,000 deferred asset. When earnings do not cover costs, dividends and surplus requirements:

In calendar 2025:

The 12-Bank distribution, remittance-clock reconciliation and property scan are in FEDERAL_RESERVE_BANK_BY_BANK_ASSET_AND_EARNINGS_SCAN_2025.md.

As of July 1, 2026, the Fed reported that the deferred asset had fallen to about $236,000,000,000.

A particular construction payment therefore need not produce a matching same-year assessment, Reserve Bank loss or deferred-asset increase. Construction outlays are capitalized on the Board's books; the Board can carry an accumulated fund balance; and Reserve Banks expense assessments when they are levied. Over time, assessment financing reduces Reserve Bank net earnings and therefore reduces current remittances or prolongs the earnings hurdle that must be recovered before normal Treasury remittances resume.

The clean fiscal-incidence statement is:

Not an appropriated taxpayer dollar does not mean economically unrelated to taxpayers or Treasury. Board spending reduces Reserve Bank net earnings and therefore reduces current remittances or delays future ones.

OMB classification

OMB describes the Federal Reserve as self-financing and independent of Executive budget review. Most Fed operations are nonbudgetary; excess-income transfers to Treasury are federal receipts. The Board's budget appears in the Budget Appendix for information, while regional Reserve Bank budgets do not.

This creates an asymmetric federal-budget presentation:

---

VI. Member-bank stock is not normal private ownership

Member banks must subscribe to Reserve Bank stock. But under 12 U.S.C. §§282, 287, 289 and 290, that stock:

The 2025 Reserve Bank statements report:

The member-bank stake is real but narrow. It does not mean JPMorgan, a local member bank or the banking industry owns the Eccles Building, approves the Board's renovation budget, or can distribute the Board's accumulated property value to private shareholders.

The Supreme Court's 2024 CFPB funding decision is an important limiting case. It treated Federal Reserve System earnings otherwise destined for Treasury as public funds for constitutional appropriations analysis. That holding concerns the CFPB's separate statutory funding regime, not the Board's §§243–244 assessment proceeds. It nevertheless makes "all Fed money is private" legally untenable.

---

VII. Property, procurement and control

Washington Board campus

PropertyCurrent control state
Eccles BuildingBoard-owned headquarters property
1951 Constitution Avenue / former South Interior BuildingGSA transferred custody to the Board in 2018; current OIG and design-review records describe Board ownership
Martin BuildingBoard-owned; main renovation reopened in 2021; later program authority includes related exterior work
1709 New York AvenueBoard retained the property after abandoning the planned full renovation; limited program remains

The precise 1951 transfer/deed instrument and original Eccles title instrument remain open document targets. The public custody transfer, current owner descriptions and Board control are clear; the exact conveyancing instrument is not yet in this packet.

Regional Reserve Bank real estate

Reserve Bank-owned premises are held on the relevant Bank's corporate books; Reserve Banks may also lease property and record leasehold improvements. Local management and boards originate projects, but Board staff and the full Board retain supervisory and final-budget roles. Regional property must not be merged with the Board-owned Washington campus.

The 2025 bank-by-bank annex shows that Atlanta and San Francisco supplied about 90% of the combined $192,000,000 increase in net Reserve Bank premises and equipment. Unlike the Board, the Reserve Banks do not publish Statements of Cash Flows; their audited year-over-year asset movements cannot be read as cash capital expenditures.

Procurement exception

The Board's published Acquisition Policy says Board expenditures are not "acquisitions" governed by the Federal Acquisition Regulation. The Fed OIG has also said the Board is not required to follow the Public Buildings Act of 1959 or FAR Part 36, although it voluntarily uses GSA and FAR practices as benchmarks.

Consequences:

This is the most important institutional difference from an ordinary executive agency project.

---

VIII. Oversight lattice

Oversight exists. It is largely audit, reporting and retrospective review rather than annual ex ante funding permission.

OverseerActual reachStructural limitation
Full Board of GovernorsApproves the Board capital plan and current project annually; also approves Reserve Bank budgetsThe governed institution is its own budget approver
Fed OIGDirect Board jurisdiction; project planning, governance, contracting, cost growth, security and current discretionary-feature reviewDoes not replace an appropriations committee or approve contracts
GAOMay audit the Board and Reserve Banks; real estate and procurement lie outside the monetary-policy/foreign-central-bank exclusions in 31 U.S.C. §714Audit and recommendation, not routine ex ante approval
Independent auditorsAnnual Board and Reserve Bank financial-statement audits required by 12 U.S.C. §248bFinancial-statement assurance is not a full value-for-money judgment
CongressHearings, document demands, subpoenas, GAO/OIG requests and power to amend §§243–244Ordinary annual appropriations leverage is absent
President / OMB / GSAAppointments, public pressure and generally applicable legal tools; GSA was transferor of 1951No identified authority to approve, reduce or cancel the Board capital budget
NCPC / CFA / SHPO / NPSPlanning, design, environmental and historic reviewNot capital-budget or procurement approvers

Planning-authority collision

The National Capital Planning Commission treated its September 2, 2021 action as final-plan approval under the National Capital Planning Act. The Board says its submission was voluntary and NCPC direction was not binding because §243 grants special property authority notwithstanding other law.

No court, OLC or Attorney General opinion resolving that collision was located. It should remain an open legal question rather than be flattened into either "NCPC had veto power" or "there was no external review."

Historic and environmental review

Those processes constrain design and mitigation. They do not substitute for appropriation or value-for-money review.

---

IX. What the audit record establishes—and does not

Established control weaknesses

Prior OIG work found:

These are genuine management findings, not merely political allegations.

Findings that cut the other way

OIG also found:

In the audited change-order sample, contractors initially proposed $47,400,000; the Board negotiated the amount to $38,700,000.

That evidence does not establish fraud, theft or a sham project. Nor does it establish that the current budget is reasonable. The live value-for-money question remains open.

Current review clock

The OIG evaluation appeared on September 29, 2026. It resolved the criminal and administrative-misconduct questions within its scope, identified contract, cost-control, governance and reporting deficiencies, and issued seven recommendations. It did not determine whether the project's total cost is reasonable, quantify avoidable loss or independently validate every award.

The live clock is implementation: an agreed GMP or other enforceable ceiling, the independent cost audit, fixed metrics, contract reconciliation, any reimbursement or credits, quarterly OIG follow-up, substantial completion and final project closeout.

---

X. Claim-grade table

ClaimGradeRuling
"The Fed spent $3,000,000,000 renovating one building."UnsupportedCollapses at least three projects and confuses authorized budget with cash spend
"The active two-building project has a $2,460,000,000 approved budget."SupportedCurrent official Board budget
"The Board's whole building-capital portfolio is about $3,100,000,000."Supported$3,062,300,000 across several programs
"These are ordinary taxpayer appropriations."False as a legal classification§§243–244 assessments; Congress expressly says the proceeds are not Government funds or appropriated moneys
"These are private bank funds for private owners."MisleadingBoard is a federal agency; member-bank stock is constrained; Treasury/U.S. holds the residual claim
"The spending has no taxpayer or Treasury incidence."FalseIt reduces Reserve Bank earnings, current remittances or the future-remittance recovery path
"The Board owns and controls its Washington property."Supported§243 permits title in the Board's own name and gives sole control
"The project uses the normal FAR/GSA/appropriations stack."FalseBoard follows its own acquisition regime and special property authority
"There is no oversight."FalseCongress, GAO, OIG, outside auditors and planning/historic bodies have roles
"The oversight is equivalent to annual appropriations control."FalseThe Board self-assesses and self-approves; much oversight is fragmented or retrospective
"Past audits proved fraud or theft."UnsupportedAudits identified governance weaknesses but did not make that finding
"Past audits proved the current $2,460,000,000 is good value."UnsupportedFinancial/control audits are not a completed value-for-money ruling; current OIG work remains open

---

XI. The principle exposed

The renovation is a useful diagnostic because it removes monetary-policy complexity. The same institutional design is visible in a tangible asset:

  1. Congress creates the entity and the assessment power.
  2. The Board sets its own expenses and assesses the Reserve Banks.
  3. Congress declares the proceeds nongovernment and nonappropriated.
  4. The Board acquires property in its own name and exercises sole control.
  5. The Board approves its own capital budget outside ordinary Executive review.
  6. The economic cost passes through Reserve Bank earnings and the Treasury remittance channel.
  7. Accountability arrives through audits, hearings, reporting and possible statutory amendment rather than annual funding permission.

This is not a secret privatization. It is a deliberate statutory insulation architecture.

That architecture creates a double boundary:

annual appropriations**, part of the broader insulation intended to protect central-bank operations from short-term political control; and

into property, procurement and administration.

The real research question is where that insulation is functionally necessary and where Congress has allowed monetary-policy independence to carry unnecessarily into ordinary administration.

This joins directly to the prior Observatory reading in KEEP_THE_FED_BIND_ITS_HANDS.md: the architecture question is not simply abolish/keep the Fed. It is which hand should be independent, which hand should be bound, by whom, and at what clock.

---

XII. Exact next digs

Primary-document targets

  1. Complete contract/modification ledger - prime contracts; - every material modification; - approval date; - original and revised value; - schedule effect; - cost-driver category; - Board payment against each obligation.
  1. Property-title instruments - 2018 GSA transfer order/deed for 1951; - original Eccles conveyance/title instrument; - conditions or reversion clauses, if any.
  1. Authority-collision analysis - any OLC, Attorney General, NCPC general counsel or Board general counsel opinion reconciling 12 U.S.C. §243 with 40 U.S.C. §8722.
  1. Congressional appropriations override history - whether Congress has ever enacted a rider expressly conditioning Board property or assessment authority; - whether Congress has used authorizing legislation instead.
  1. Comparable-cost benchmark - historic federal-building renovation cost per gross square foot; - subterranean/security/hazardous-material and occupied-campus adjustments; - DC construction-inflation series; - separately stated preservation premium.

Watchboard

TriggerWhy it mattersFalsifier / correction test
Board/GSA finalize a GMP or another enforceable ceilingConverts the January 2026 proposal and September direction into a binding cost-control stateProposal, negotiation and agreement remain separate
Independent cost audit is releasedTests awarded costs, services received and questioned amountsWarsh's direction is not completed validation
OIG closes individual recommendationsTests whether corrective action is implemented and acceptedConcurrence is not closure
2026/2027 Board budget publishes granular actualsAdvances the actual-spend clock beyond YE2024Separate forecast, obligation, award and cash payment
Board revises $2,455,500,000 or scheduleChanges project-life budget/schedule objectDo not substitute broader $3,062,300,000 portfolio
Congress introduces §§243–244 amendment or project conditionTests whether controversy becomes durable control lawHearing rhetoric alone is not an operative constraint
GAO opens or releases a project reviewAdds outside value/control evidenceConfirm scope is administrative/property, not protected monetary-policy material
Complete contract ledger becomes publicPermits real change-order attributionSubcontract awards are not the same as Board cash spend

---

XIII. Primary source spine

Budgets, financial statements and fiscal incidence

Project, property and oversight

Trump claim clocks

---

Research joins

Sources

Full saved reading

View cited sources (25)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details
About the dates and filing language
Evidence date
When this document or named claim was checked. A newer collection, export or website date does not update it.
Current, private, Workbench or promotion
These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
Master data and projection
The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
Provenance and source join
Where a record came from, and the exact reference connecting a claim to its source.
Gate, receipt and operating evidence
A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

I. Claim audit: what does the "$3,000,000,000" claim refer to?

Ruling

$3,100,000,000 is a defensible rounded description of the Board's entire building-improvement capital portfolio. It is not the approved budget or

amount already spent for the two buildings currently under construction.

There are three separate public budget objects:

ObjectCurrent public figureWhat it means
Eccles + 1951 Constitution Avenue$2,455,500,000Approved project-life budget for the two active historic-building renovations and expansions
All Board building-improvement programs$3,062,300,000Eccles/1951 plus Martin, limited New York Avenue work, post-Eccles reconfiguration and relocation-site authority
Full long-term space planabout $3,600,000,000Capital expenditures plus $555,900,000 of operating expense

None means "$3,000,000,000 already spent renovating one building."

The $3,062,300,000 portfolio

The Board's 2025 budget lists:

Capital programAuthorized program budget
Eccles–1951$2,455,500,000
Martin renovation program$538,400,000
New York Avenue limited program$20,000,000
Post-Eccles reconfiguration$29,800,000
Board relocation site$18,600,000
Total building-improvement programs$3,062,300,000

The Board budget itself uses two nonidentical groupings: Table 3 assigns

$3,044,100,000 of capital to the long-term space plan, while Tables 5 and A2.8

report $3,062,300,000 across all building-improvement programs. The $3,600,000,000

long-term-space figure adds $555,900,000 of operating expenses to its Table 3

capital subtotal. Those published category boundaries should be preserved

rather than forced into a single "renovation total."

The same budget records a net-zero reallocation within the broader capital

plan:

- +$572,000,000 to Eccles–1951;

- -$61,600,000 of unused Martin authority;

- -$510,400,000 from New York Avenue after the full renovation was abandoned.

That raised the two-building project budget without raising the total

building-improvement capital ceiling.

Trump-reference clock

DateVerified public statementEvidence state
2025-07-24At the Fed construction site, President Trump said the cost was about $3,100,000,000 and had risen from $2,700,000,000. A Fed aide identified the paper as the "entire capital" figure; Powell said a third, already renovated building had been added.Official presidential transcript
2026-03-26Trump alleged that the project was over $3,000,000,000 and might exceed $4,000,000,000.Official presidential transcript; allegation/projection, not a Fed budget update
2026-04-25Trump used a $4,000,000,000 figure while also saying nobody knew the final amount.Latest primary-source building-cost reference located in this pass; allegation, not a supported released budget

No released Fed budget located in this pass supports a $4,000,000,000 approved project or

cash-spend figure. The exact newly referenced clip or post was not separately

captured; this packet audits the repeated official claim chain and its

underlying numbers.

Budget is not spend

The latest granular public actual for Eccles–1951 is **$701,600,000 through

year-end 2024. The 2025 budget forecast another $425,000,000 during 2025**, but a

forecast is not verified actual expenditure.

Public snapshotEccles–1951 program budgetDocumented cumulative spend
June 2020$1,273,400,000, excluding the $41,600,000 acquisitionNot stated
2021 budget$1,377,800,000$65,900,000 through YE2020
2023 budget$1,883,500,000$135,400,000 through YE2022
2024 budget$1,883,500,000$356,800,000 through YE2023
2025 budget$2,455,500,000$701,600,000 through YE2024

The current budget is:

- +$572,000,000, or about 30.4%, above the 2023 project budget; and

- about +$1,078,000,000, or 78.2%, above the 2021 project budget.

The much earlier June 2020 program number is lower still, but it should not be

treated as a like-for-like final-design construction baseline without a scope

reconciliation.

Schedule clocks

SnapshotExpected completion
March 2019Q4 2024
June 2020Q3 2026
July 20252027
Later staff descriptionconstruction in fall 2027; employee moves through March 2028

The schedule moved as scope and conditions changed. The public record attributes

cost growth to competitive-bid pricing, post-pandemic labor and material costs,

hazardous-material removal, soil contamination, water-table conditions and

historic-preservation requirements. Those explanations do not by themselves

establish that every cost was necessary or well controlled.

---