Offshore wind after the stop-work orders — first power and commercial operation
Full saved reading
View cited sources (7)
These are the sources cited by this reading. Each source keeps its own date and scope.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: Offshore wind after the stop-work orders — first power and commercial operation
question: Did Revolution Wind and Coastal Virginia Offshore Wind generate power after the court orders, and did both reach commercial operation?
research_id: ai-turbine-asset-management-power-buildout
artifact_role: answer
status: current
evidence_cutoff: 2026-11-10
---
Offshore wind after the stop-work orders — first power and commercial operation
Revolution Wind, LLC reported on March 13, 2026 that the project had started delivering electricity. On November 5, 2026, Ørsted reported that the 704 MW project reached commercial operation in October 2026 under utility offtake contracts in Rhode Island and Connecticut. The records give the first-delivery announcement day and commercial-operation month. The exact first delivery and commercial-operation days, and project-specific MWh, remain unverified. Project first-power release · Ørsted November operating report · Connecticut confirmation
The December 22, 2025 BOEM suspension and January 12, 2026 D.C. District Court preliminary injunction are separate legal dates. The injunction allowed the project to resume affected work while the challenge proceeded. The March and October operating records come from the project and its owner. January injunction announcement · Court’s January 12 order
Dominion Energy reported that the Eastern District of Virginia’s January 16, 2026 preliminary injunction allowed work on its Coastal Virginia Offshore Wind Commercial project to resume after the December BOEM order. The project reported first power in March 2026. Dominion’s Form 10-Q for the quarter ended September 30, 2026 confirms initial operations in March and says installation of the final turbines of the 2.6 GW project is expected by the end of 2027. Full-project commercial operation and delivered MWh remain unverified in the checked records. Dominion January 8-K · Dominion third-quarter 10-Q
The saved U.S. buildout study supplies the earlier framework for planning, construction and operating milestones. The earlier Chronicle study retains its own evidence cutoff.