title: "DOE renews the Campbell power plant order through February 12"
research_id: federal-government-deep-website-review-2026-09-22
status: current
artifact_role: answer
evidence_cutoff: 2026-11-16T19:00:00-05:00
---

# DOE renews the Campbell power plant order through February 12

On November 13, 2026, Energy Secretary Chris Wright issued Order 202-26-51 under Federal Power Act §202(c). The order directs MISO and Consumers Energy to keep the J.H. Campbell Generating Facility available from November 15, 2026 through February 12, 2027. MISO must use economic dispatch only in hours needed to meet the emergency and report compliance daily; its availability plan is due to DOE by November 28. The order excludes Campbell as a capacity resource and directs Consumers Energy to file FERC tariff revisions or waivers as needed. [Signed order, paragraphs A–H](https://www.energy.gov/documents/doe-order-no-202-26-51) · [DOE docket entry](https://www.energy.gov/ceser/federal-power-act-section-202c-midcontinent-independent-system-operator-miso-order-no-202-2).

Order 202-26-39 held Campbell available through November 14. The replacement order's clock preserves availability without a calendar-day gap. The signed order cites 201,962 MWh during January 23–February 1 based on EPA data; that quantity is historical evidence for the agency rationale, separate from dispatch under this new order. The records checked do not show a November 15–16 unit dispatch, the daily compliance reports or approved cost recovery under 202-26-51. [Prior order and rehearing record](https://www.energy.gov/ceser/federal-power-act-section-202c-midcontinent-independent-system-operator-miso-order-no-202-1) · [EPA emissions and operating data route](https://campd.epa.gov/data/custom-data-download). Next: MISO availability and generation reports, any rehearing/stay, and FERC cost-recovery filings and orders.