title: Sovereign siting, operating services and the permit record
research_id: sovereign-compute
artifact_role: answer
status: current
evidence_cutoff: 2026-11-18
evidence_scope: Selected named project and policy records; not a new national tribal data-center census or legal opinion on every parcel.
---

# Sovereign siting, operating services and the permit record

The [October return](TRIBAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md) supplies the starting findings. This pass reads the material Cherokee chapters, checks named operator/sponsor statements and recovers the actual Pocatello packet. The cases have different owners, land positions and operating states.

## Cherokee: a policy recommendation, with project-specific resource questions

The Cherokee Nation report is dated June 30, 2026; its download page records August 5 publication. It distinguishes land status and direct tribal land-use policy from influence on non-tribal land. It favors workforce/supplier opportunities, cost-causation and enforceable community terms over direct hyperscale investment or tax-arbitrage. Its environmental discussion calls for site-specific power, cooling, water and emissions evidence. The recommended advisory committee is not itself a project approval or proof of an adopted moratorium. [Task-force page](https://www.cherokee.gov/our-government/executive-branch/task-forces/data-center-task-force/); [report](https://www.cherokee.gov/media/qpwnx21l/data-center-task-force.pdf), PDF pp. 10, 13–16, 24–26, 31–32 and 37.

Those chapters caution against transferring generic resource figures onto a new site. This return does not independently validate their secondary-source consumption estimates. A facility's cooling circuit and its electricity supply also have different water implications. Permits, design and actual site measurements are the evidence needed for a project claim.

## Data Holdings: an operating service with named physical dependencies

In DOE's published webinar transcript, Data Holdings' Ryan Brooks describes a tribally owned Milwaukee colocation business, in-house operation, a 17 MW site buying electricity from We Energies, closed-loop mechanical cooling, free cooling in suitable weather and local network/peering services. He also says it hosts some limited AI. These are attributable operator statements, not a metered AI-load breakdown or an independent uptime/cooling audit. [DOE transcript](https://www.energy.gov/indianenergy/beyond-land-leases-harnessing-data-centers-tribal-economic-development-webinar), Brooks presentation.

The current provider page separately describes Forest County Potawatomi ownership, trust-land location and colocation/private-cloud services. That supports an existing operating-service example. It does not establish that all tribal facilities share the same jurisdictional position, that all customer records are immune from process, or that this is a newly commissioned hyperscale AI campus. [Provider page](https://dataholdings.com/data-sovereignty-tribal-nations).

## Colusa: a named partnership and sponsor-reported proof of concept

Colusa Indian Energy's March 25, 2026 announcement names Strata Expanse, a planned AI/energy campus on Cachil Dehe Band land, an existing microgrid and proof-of-concept deployments claimed by the sponsors. It names DDN, Supermicro, NVIDIA, Intel and AMD in a technology ecosystem and targets more than 100 MW of later onsite generation. Those statements do not disclose supplier purchase instruments, paid-in campus capital, accepted equipment or a revenue-bearing tenant. [Sponsor announcement](https://www.colusaindianenergy.com/post/colusa-indian-energy-and-strata-expanse-announce-strategic-partnership).

This preserves the [earlier public-company briefing's](PUBLIC_COMPANY_TRIBAL_DATA_CENTER_ONE_PAGE.md) distinction between an operating facility and prospective supplier exposure. Sponsor naming is not the same evidence as a supplier's executed order or a measured commercial workload. No broad current nonexistence claim is made from the inspected announcement/news surface.

## Pocatello: recover the proposed disposition without manufacturing adoption

The official October 1, 2026 consent packet identifies Lex Developments, LLC, Portneuf Capital, LLC and the proposed roughly 59-acre data-center site at 1800 River Park Way. Its CUP section reports a September 17 Council vote of 3–2 to retain the denial and a separate 3–2 vote to waive the twelve-month reapplication wait. The proposed decision expressly keeps the denial. PDF page 11 has blank date/signature fields, verified visually. The packet is not proof that its written disposition was adopted and executed on October 1. [Agenda](https://pocatello.gov/AgendaCenter/ViewFile/Agenda/_10012026-1953?html=true); [packet, PDF pp. 9–11](https://pocatello.gov/AgendaCenter/ViewFile/Item/5674?fileID=15373).

The same packet recites July 16's earlier 4–1 appeal vote and an August 6 written decision. These are reported antecedents, not new November rulings. The November 18 Agenda Center check exposed the relevant agenda/packet but no October 1 minutes link. A signed final instrument, complete adjudicative record, treaty/consultation treatment and any judicial-review result remain separate questions. [Agenda Center](https://pocatello.gov/AgendaCenter/City-Council-4).

The [Shoshone-Bannock statement held in the October return](TRIBAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md#2-pocatello-moved-from-appeal-uncertainty-to-a-prepared-denial-disposition) remains a separate account of opposition and ceded-land concerns. It does not make this private site tribal trust land. Reapplication eligibility does not supply the denied permit.

## What remains a real return

For Colusa, seek parcel/lease, named customer, equipment, financing, acceptance and power-delivery instruments. For Pocatello, seek the executed disposition and any later application or court result. For Data Holdings, a workload or performance claim needs its own record. The DOE tribal-energy selection estimate of November 20 and later final-award estimate in the October return remain prospective programme clocks at this review; they are not data-center-serving awards.

**Read/check scope:** complete October return and public-company briefing; selected Cherokee report chapters listed above; sponsor/operator pages; DOE transcript's Brooks presentation; official Pocatello agenda, Agenda Center and the complete three-page CUP portion of its eleven-page consent packet, including visual signature-page inspection. No full Cherokee report review, independent audit, complete parcel/title opinion, comprehensive docket search or new general project census is claimed.