---
title: Intel's amended CHIPS agreement changed the test for project completion
question: What did GAO report about Intel's milestones, eligible costs and CHIPS disbursements?
research_id: us-inbound-investment-industrial-capex
artifact_role: answer
status: current
source_date: 2026-08-06
evidence_cutoff: 2026-11-18
---

# Intel's amended CHIPS completion test

GAO's August 6, 2026 report says Commerce amended Intel's award for six projects in August 2025. Required project milestones not yet achieved were removed. Under the amended terms, each project would count as complete once Intel incurred eligible costs equal to its award amount. GAO says Commerce considered all six projects complete at amendment because Intel had already incurred the eligible costs. Commerce no longer required reporting against the removed original milestones.

GAO reports $7.865 billion disbursed to Intel, largely under that amended eligible-cost arrangement. It excluded Intel's milestones from the separate analysis of 24 completed and 125 in-progress milestones. The reported payment therefore cannot be treated as proof that Intel met the original physical-project milestones. The report describes completion under the amended award, not commissioning or production at every fab.

[GAO-26-109121, “Commerce and Awardees Have Continued to Make Progress,” the Intel amendment paragraph and “Commerce Disbursed $13 Billion as of April 2026”](https://files.gao.gov/reports/GAO-26-109121/index.html).

## Relationship to the existing study

This adds the amended completion condition beneath the [existing investment research](README.md) and the CHIPS factual chronology's August 6 report step. It preserves that chronology's different $31.2 billion detailed-section and $31.5 billion Highlights figures. The report was checked on November 18; it is not a new payment measurement or a later review of the executed amendment itself.
