Program → portfolio → operating proof

What FORTRESS America promises—and what is not proved

A five-pillar resilience program whose installation-power objective is real—but whose technical constitution and delivered portfolio still have to be proved.

Current evidence state: program established → implementation constitution not yet public → fleet-wide delivery unproven.

Five mutually dependent pillars

Energy independenceIndependent power for every major U.S. installation
Supply chain + industrial baseMaterials, components, production and skilled capacity
Strategic defense reserveMunitions, fuel, medicine and blood through disruption
Installation hardening + cyberProtection against intrusion, sabotage and drones
Space + spectrumAssured sensing, navigation and communications

Three statements that must not be collapsed

Object
Covered boundary
Evidence state
FORTRESS
Every major U.S. installation; “independent power” undefined
Program objective established
10 U.S.C. §2920
Each installation’s critical-mission load
99.9% minimum annual availability required by end FY2030
Next Great American Base
One future model installation
Completely off-grid design objective, not an operating site

Evidence ladder

Select a state to see the receipt required before a claim can move.

Where the public record stops

Program direction

FORTRESS AmericaSite list, definition and funding unresolved

Selection / negotiation

Army SCISix conditional pairings
Janus + NWS CranePairings and planned 2028 deployment
EielsonNotice of intent; up to 5 MW critical load

Prototype lane

Project PeleINL demonstration, not base service

Operational description

MCAS YumaFull-load backup described
SUBASE New LondonEssential functions
McCoy + SigonellaGate / tenant-facility scope

Island test observed

MCAS MiramarMission-critical islanding; endurance still separate
Decision rule: an independence claim is only as strong as its load boundary + duration + operating-test receipt.
About this graphic and its research

Compare the program's five parts with the separate legal requirement for critical loads, then see which bases have plans, funded work, completed systems or tested results.